1 [Figures 1 and 2, printed on the insert, are provided for use in this question.]
The following diagram shows an activity diagram for a building project. The time needed for each activity is given in days.
\includegraphics[max width=\textwidth, alt={}, center]{0c40b693-72d3-459c-bbb7-b9584a108b8e-02_698_1321_767_354}
- Complete the precedence table for the project on Figure 1.
- Find the earliest start times and latest finish times for each activity and insert their values on Figure 2.
- Find the critical path and state the minimum time for completion of the project.
- Find the activity with the greatest float time and state the value of its float time.