AQA D2 2007 June — Question 1 10 marks

Exam BoardAQA
ModuleD2 (Decision Mathematics 2)
Year2007
SessionJune
Marks10
PaperDownload PDF ↗
Mark schemeDownload PDF ↗
TopicCritical Path Analysis
TypeComplete precedence table from network
DifficultyEasy -1.2 This is a routine Critical Path Analysis question requiring standard algorithmic procedures: reading a network diagram to complete a precedence table, performing forward/backward passes for earliest/latest times, identifying the critical path, and calculating float times. All steps follow mechanical algorithms with no problem-solving or novel insight required—purely procedural application of taught methods.
Spec7.05a Critical path analysis: activity on arc networks7.05b Forward and backward pass: earliest/latest times, critical activities7.05c Total float: calculation and interpretation7.05d Latest start and earliest finish: independent and interfering float

1 [Figures 1 and 2, printed on the insert, are provided for use in this question.]
The following diagram shows an activity diagram for a building project. The time needed for each activity is given in days. \includegraphics[max width=\textwidth, alt={}, center]{0c40b693-72d3-459c-bbb7-b9584a108b8e-02_698_1321_767_354}
  1. Complete the precedence table for the project on Figure 1.
  2. Find the earliest start times and latest finish times for each activity and insert their values on Figure 2.
  3. Find the critical path and state the minimum time for completion of the project.
  4. Find the activity with the greatest float time and state the value of its float time.

Question 1:
Part (a)
AnswerMarks Guidance
AnswerMarks Guidance
Precedence table completed correctly showing: A,B precede C,D,E; C,D precede F,G; E precede H; F,G precede I; G,H precede J; I,J precede KB1 B1 B1 for each correct column of predecessors
Part (b)
AnswerMarks Guidance
AnswerMarks Guidance
Earliest start times: A=0, B=0, C=2, D=1, E=1, F=5, G=6, H=4, I=11, J=11, K=16M1 A1 M1 for attempt at forward pass
Latest finish times: A=2, B=6, C=5, D=6, E=4, F=11, G=9, H=9, I=16, J=16, K=17M1 A1 M1 for attempt at backward pass
Part (c)
AnswerMarks Guidance
AnswerMarks Guidance
Critical path: \(B \to D \to G \to J \to K\)B1 Must be stated as a path
Minimum completion time = 17 daysB1
Part (d)
AnswerMarks Guidance
AnswerMarks Guidance
Activity \(E\) has greatest floatB1
Float = \(4 - 1 - 3 = 0\)... Activity \(A\): float \(= 6-0-2=4\) or Activity \(C\): float \(= 5-2-3=0\)M1 A1 M1 for correct float calculation method: LF - ES - duration
# Question 1:

## Part (a)
| Answer | Marks | Guidance |
|--------|-------|----------|
| Precedence table completed correctly showing: A,B precede C,D,E; C,D precede F,G; E precede H; F,G precede I; G,H precede J; I,J precede K | B1 B1 | B1 for each correct column of predecessors |

## Part (b)
| Answer | Marks | Guidance |
|--------|-------|----------|
| Earliest start times: A=0, B=0, C=2, D=1, E=1, F=5, G=6, H=4, I=11, J=11, K=16 | M1 A1 | M1 for attempt at forward pass |
| Latest finish times: A=2, B=6, C=5, D=6, E=4, F=11, G=9, H=9, I=16, J=16, K=17 | M1 A1 | M1 for attempt at backward pass |

## Part (c)
| Answer | Marks | Guidance |
|--------|-------|----------|
| Critical path: $B \to D \to G \to J \to K$ | B1 | Must be stated as a path |
| Minimum completion time = 17 days | B1 | |

## Part (d)
| Answer | Marks | Guidance |
|--------|-------|----------|
| Activity $E$ has greatest float | B1 | |
| Float = $4 - 1 - 3 = 0$... Activity $A$: float $= 6-0-2=4$ or Activity $C$: float $= 5-2-3=0$ | M1 A1 | M1 for correct float calculation method: LF - ES - duration |

---
1 [Figures 1 and 2, printed on the insert, are provided for use in this question.]\\
The following diagram shows an activity diagram for a building project. The time needed for each activity is given in days.\\
\includegraphics[max width=\textwidth, alt={}, center]{0c40b693-72d3-459c-bbb7-b9584a108b8e-02_698_1321_767_354}
\begin{enumerate}[label=(\alph*)]
\item Complete the precedence table for the project on Figure 1.
\item Find the earliest start times and latest finish times for each activity and insert their values on Figure 2.
\item Find the critical path and state the minimum time for completion of the project.
\item Find the activity with the greatest float time and state the value of its float time.
\end{enumerate}

\hfill \mbox{\textit{AQA D2 2007 Q1 [10]}}