230 questions
| Activity | Immediate predecessors | Duration (days) |
| A | - | 5 |
| B | - | 3 |
| C | A | 3 |
| D | A, B | 4 |
| E | A, B | 5 |
| Activity | Duration (weeks) | Immediate Predecessors | |
| A | Survey sites | 8 | - |
| B | Purchase land | 22 | A |
| C | Supply materials | 10 | - |
| D | Supply machinery | 4 | - |
| E | Excavate foundations | 9 | B, D |
| F | Lay drains | 11 | B, C, D |
| G | Build walls | 9 | E, F |
| H | Lay floor | 10 | E, F |
| I | Install roof | 3 | G |
| J | Install electrics | 5 | G |
| Task | E | F | H | J | ||
| 3 | 3 | 1 | 3 | ||
| 30 | 15 | 6 | 20 |
| Activity | Duration (mins) | Immediate Predecessors |
| A Refuel | 30 | - |
| B Clean cabin | 25 | - |
| C Pre-flight technical check | 15 | A |
| D Load luggage | 20 | - |
| E Load passengers | 25 | A, B |
| F Safety demonstration | 5 | E |
| G Obtain air traffic clearance | 10 | C |
| H Taxi to runway | 5 | G, D |
| Task | A | B | D | E |
| New time (mins) | 20 | 20 | 15 | 15 |
| Extra cost | 250 | 50 | 50 | 100 |
| Activity | Duration (mins) | Immediate predecessors |
| A | 3 | - |
| B | 2 | - |
| C | 3 | A |
| D | 5 | A, B |
| E | 1 | C |
| Task | Description | Duration (mins) |
| A | Fill kettle and switch on | 0.5 |
| B | Boil kettle | 1.5 |
| C | Cut bread and put in toaster | 0.5 |
| D | Toast bread | 2 |
| E | Put eggs in pan of water and light gas | 1 |
| F | Boil eggs | 5 |
| G | Put tablecloth, cutlery and crockery on table | 2.5 |
| H | Make tea and put on table | 0.5 |
| I | Collect toast and put on table | 0.5 |
| J | Put eggs in cups and put on table | 1 |
| Task | Duration (seconds) | Immediate predecessors | |
| B | get out bowl and implements | 10 | - |
| I | get out ingredients | 10 | - |
| L | chop lettuce | 15 | B, I |
| W | wash tomatoes and celery | 25 | B, I |
| T | chop tomatoes | 15 | W |
| C | chop celery | 10 | W |
| P | peel apple | 20 | B, I |
| A | chop apple | 10 | P |
| D | dress salad | 10 | L, T, C, A |
| Task | Duration (minutes) | Immediate predecessor(s) | |
| A | measure windows | 5 | - |
| B | calculate material required | 5 | A |
| C | choose material | 15 | - |
| D | buy material | 15 | B, C |
| E | cut material | 5 | D |
| F | stitch sides of wide curtain | 30 | E |
| G | stitch top of wide curtain | 30 | F |
| H | stitch sides of narrow curtain | 30 | E |
| I | stitch top of narrow curtain | 15 | H |
| J | hang curtains and pin hems | 20 | G, I |
| K | hem wide curtain | 30 | J |
| L | hem narrow curtain | 15 | J |
| M | fit curtains | 10 | K, L |
| Activity | Duration (hours) | Immediate predecessor(s) |
| A | 3 | - |
| B | 2 | - |
| C | 5 | - |
| D | 2 | A |
| E | 1 | A, B |
| Activity | Duration (hours) | Immediate predecessors | |
| A | Agree date | 1 | - |
| B | Construct agenda | 0.5 | - |
| C | Book venue | 0.25 | A |
| D | Order refreshments | 0.25 | C |
| E | Inform participants | 0.5 | B, C |
| A | Rig foresail |
| B | Lower sprayhood |
| C | Start engine |
| D | Pump out bilges |
| E | Rig mainsail |
| F | Cast off mooring ropes |
| G | Motor out of harbour |
| H | Raise foresail |
| I | Raise mainsail |
| J | Stop engine and start sailing |
| Activity | A | B | C | D | E |
| Duration | 2 | 1 | \(x\) | 3 | 2 |
| Activity | Duration | Immediate predecessors |
| R | 2 | - |
| S | 1 | - |
| T | 5 | - |
| w | 3 | R, S |
| X | 2 | R, S, T |
| Y | 3 | R |
| Z | 1 | W, Y |
| Jobs | Duration (mins) | Immediate predecessors | |
| A | prune bushes | 100 | - |
| B | weed borders | 60 | A |
| C | cut hedges | 150 | - |
| D | hoe vegetable patch | 60 | - |
| E | mow lawns | 40 | B |
| F | edge lawns | 20 | D, E |
| G | clean up cuttings | 30 | B, C |
| H | clean tools | 10 | F, G |
| Task | Duration (months) | Immediate predecessors |
| A | 4 | - |
| B | 2 | - |
| C | 7 | - |
| D | 12 | A |
| E | 5 | A |
| F | 7 | A, B |
| G | 6 | D, J |
| H | 3 | C |
| I | 12 | E, F, H |
| J | 7 | E, F, H |
| K | 12 | C |
| Tasks which can be completed more quickly by employing extra resources | Number of months which can be saved | Cost per month of employing extra resources (£m) |
| A | 2 | 3 |
| D | 1 | 1 |
| C | 3 | 3 |
| F | 2 | 2 |
| G | 2 | 4 |
| Activity | Description | Duration (days) |
| A | Architect produces plans | 10 |
| Pl | Obtain planning permission | 14 |
| Demo | Demolish existing structure | 3 |
| Fo | Excavate foundations | 4 |
| W | Build walls | 3 |
| Pb | Install plumbing | 2 |
| R | Construct roof | 3 |
| Fl | Lay floor | 2 |
| E | Fit electrics | 2 |
| WD | Install windows and doors | 1 |
| Deco | Decorate | 5 |
| Task | Time (minutes) | Immediate predecessors | |
| A | measure out flour | 0.5 | - |
| B | mix flour and water | 1 | A |
| C | shell eggs | 0.5 | - |
| D | mix in eggs and fat | 2 | B, C |
| E | get currants ready | 0.5 | - |
| F | get raisins ready | 0.5 | - |
| G | fold fruit into mix | 0.5 | D, E, F |
| H | bake | 10 | G |
| Task | Duration (hours) | Immediate predecessor(s) | |
| A | measure | 0.5 | - |
| B | manufacture frame and door | 5 | A |
| C | cut hole in wall | 2 | A |
| D | fit lintel and marble step | 1.5 | C |
| E | fit frame | 1 | B, C |
| F | fit door | 1 | E |
| G | repair plaster around door | 1 | E |
| Activity | Duration (mins) | Immediate predecessor(s) | |
| A | select mounting | 5 | - |
| B | glue picture to mounting | 5 | A |
| C | allow mounting glue to dry | 20 | B |
| D | measure for frame | 5 | A |
| E | select type of frame | 10 | A |
| F | cut four frame pieces | 5 | D, E |
| G | pin and glue frame pieces together | 5 | F |
| H | allow frame glue to dry | 20 | G |
| I | cut and bevel glass | 30 | D |
| J | fit glass to frame | 5 | H, I |
| K | fit mounted picture to frame | 5 | C, J |
| Activity | Duration (weeks) | |
| A | choose lead actors | 1 |
| B | choose rest of actors | 1 |
| C | choose dancers | 1 |
| D | rehearse lead actors | 8 |
| E | rehearse rest of actors | 6 |
| F | rehearse dancers | 6 |
| G | prepare scenery | 6 |
| H | install scenery | 1 |
| I | prepare music | 2 |
| J | make costumes | 4 |
| K | dress rehearsals | 2 |
| A | B | C | D | E | \(F\) | |
| A | - | 130 | 190 | 155 | 140 | 125 |
| B | 130 | - | 215 | 200 | 190 | 170 |
| C | 190 | 215 | - | 110 | 180 | 100 |
| D | 155 | 200 | 110 | - | 70 | 45 |
| E | 140 | 190 | 180 | 70 | - | 75 |
| \(F\) | 125 | 170 | 100 | 45 | 75 | - |
| \(n\) | \(x _ { n }\) | \(a\) | Any more data? | \(x _ { n + 1 }\) | \(b\) | \(( b - a ) > 0\) ? | \(a\) |
| 1 | 8 | 8 | Yes | 2 | 2 | No | 2 |
| 2 | - | - |
| \(P\) | \(\bullet\) | \(\bullet\) | \(D\) |
| \(Q\) | \(\bullet\) | \(\bullet\) | \(G\) |
| \(R\) | \(\bullet\) | \(\bullet\) | \(E\) |
| \(S\) | \(\bullet\) | \(\bullet\) | \(L ( H )\) |
| \(T\) | \(\bullet\) | \(\bullet\) | \(L\) |
| \(x\) | \(a\) | \(b\) | \(( a - b ) < 0.01\) ? |
| 100 | 50 | 26 | No |
| - | 26 | 14.923 | No |
| \(x\) | \(a\) | \(b\) | \(( a - b ) < 0.01 ?\) |
| 100 |
| 0 | 5 | 10 | 15 | 20 | 25 | 30 | 35 | 40 | 45 | 50 | 55 | 60 |
| Worker 1 | ||||||||||||
| Worker 2 |
| 0 | 5 | 10 | 15 | 20 | 25 | 30 | 35 | 40 | 45 | 50 | 55 | 60 |
| Worker 1 | ||||||||||||
| Worker 2 | ||||||||||||
| Worker 3 |
| Activity | \(A\) | \(B\) | \(C\) | \(D\) | \(E\) | \(F\) | \(G\) | \(H\) | \(I\) | \(J\) |
| Number of workers required | 2 | 2 | 3 | 2 | 3 | 2 | 1 | 3 | 5 | 2 |
| Activity | A | \(B\) | C | D | \(E\) | \(F\) | G | H | I | \(J\) | \(K\) | \(L\) |
| Duration (days) | 2 | 5 | 6 | 7 | 9 | 4 | 3 | 2 | 3 | 2 | 3 | 1 |
| Number of workers required | 6 | 3 | 5 | 2 | 5 | 2 | 4 | 4 | 5 | 3 | 2 | 4 |
| Activity | \(A\) | \(B\) | \(C\) | \(D\) | \(E\) | \(F\) | \(G\) | \(H\) | \(I\) | \(J\) |
| Number of workers required | 4 | 2 | 3 | 4 | 2 | 4 | 3 | 3 | 5 | 6 |