7.05b Forward and backward pass: earliest/latest times, critical activities

206 questions

Sort by: Default | Easiest first | Hardest first
OCR MEI D1 2006 January Q1
8 marks Moderate -0.3
1 Table 1 shows a precedence table for a project. \begin{table}[h]
ActivityImmediate predecessorsDuration (days)
A-5
B-3
CA3
DA, B4
EA, B5
\captionsetup{labelformat=empty} \caption{Table 1}
\end{table}
  1. Draw an activity-on-arc network to represent the precedences.
  2. Find the early event time and late event time for each vertex of your network, and list the critical activities.
  3. Extra resources become available which enable the durations of three activities to be reduced, each by up to two days. Which three activities should have their durations reduced so as to minimise the completion time of the project? What will be the new minimum project completion time?
OCR MEI D1 2008 January Q5
16 marks Moderate -0.3
5 The table shows some of the activities involved in building a block of flats. The table gives their durations and their immediate predecessors.
ActivityDuration (weeks)Immediate Predecessors
ASurvey sites8-
BPurchase land22A
CSupply materials10-
DSupply machinery4-
EExcavate foundations9B, D
FLay drains11B, C, D
GBuild walls9E, F
HLay floor10E, F
IInstall roof3G
JInstall electrics5G
  1. Draw an activity on arc network for these activities.
  2. Mark on your diagram the early and late times for each event. Give the minimum completion time and the critical activities. Each of the tasks E, F, H and J can be speeded up at extra cost. The maximum number of weeks by which each task can be shortened, and the extra cost for each week that is saved, are shown in the table below.
    TaskEFHJ
    Maximum number of weeks by
    which task may be shortened
    3313
    Cost per week of shortening task
    (in thousands of pounds)
    3015620
  3. Find the new shortest time for the flats to be completed.
  4. List the activities which will need to be speeded up to achieve the shortest time found in part (iii), and the times by which each must be shortened.
  5. Find the total extra cost needed to achieve the new shortest time.
OCR MEI D1 2009 January Q5
16 marks Moderate -0.8
5 The tasks involved in turning around an "AirGB" aircraft for its return flight are listed in the table. The table gives the durations of the tasks and their immediate predecessors.
ActivityDuration (mins)Immediate Predecessors
A Refuel30-
B Clean cabin25-
C Pre-flight technical check15A
D Load luggage20-
E Load passengers25A, B
F Safety demonstration5E
G Obtain air traffic clearance10C
H Taxi to runway5G, D
  1. Draw an activity on arc network for these activities.
  2. Mark on your diagram the early time and the late time for each event. Give the minimum completion time and the critical activities. Because of delays on the outbound flight the aircraft has to be turned around within 50 minutes, so as not to lose its air traffic slot for the return journey. There are four tasks on which time can be saved. These, together with associated costs, are listed below.
    TaskABDE
    New time (mins)20201515
    Extra cost2505050100
  3. List the activities which need to be speeded up in order to turn the aircraft around within 50 minutes at minimum extra cost. Give the extra cost and the new set of critical activities.
OCR MEI D1 2010 January Q1
8 marks Easy -1.2
1 The table shows the activities involved in a project, their durations and their precedences.
ActivityDuration (mins)Immediate predecessors
A3-
B2-
C3A
D5A, B
E1C
  1. Draw an activity on arc network for these activities.
  2. Mark on your diagram the early time and the late time for each event. Give the critical activities.
OCR MEI D1 2011 January Q4
16 marks Moderate -0.5
4 The table shows the tasks involved in preparing breakfast, and their durations.
TaskDescriptionDuration (mins)
AFill kettle and switch on0.5
BBoil kettle1.5
CCut bread and put in toaster0.5
DToast bread2
EPut eggs in pan of water and light gas1
FBoil eggs5
GPut tablecloth, cutlery and crockery on table2.5
HMake tea and put on table0.5
ICollect toast and put on table0.5
JPut eggs in cups and put on table1
  1. Show the immediate predecessors for each of these tasks.
  2. Draw an activity on arc network modelling your precedences.
  3. Perform a forward pass and a backward pass to find the early time and the late time for each event.
  4. Give the critical activities, the project duration, and the total float for each activity.
  5. Given that only one person is available to do these tasks, and noting that tasks B, D and F do not require that person's attention, produce a cascade chart showing how breakfast can be prepared in the least possible time.
OCR MEI D1 2012 January Q6
16 marks Moderate -0.8
6 The table shows the tasks involved in making a salad, their durations and their precedences.
TaskDuration (seconds)Immediate predecessors
Bget out bowl and implements10-
Iget out ingredients10-
Lchop lettuce15B, I
Wwash tomatoes and celery25B, I
Tchop tomatoes15W
Cchop celery10W
Ppeel apple20B, I
Achop apple10P
Ddress salad10L, T, C, A
  1. Draw an activity on arc network for these activities.
  2. Mark on your diagram the early and late times for each event. Give the minimum completion time and the critical activities.
  3. Given that each task can only be done by one person, how many people are needed to prepare the salad in the minimum time? What is the minimum time required to prepare the salad if only one person is available?
  4. Show how two people can prepare the salad as quickly as possible.
OCR MEI D1 2013 January Q4
16 marks Moderate -0.3
4 A room has two windows which have the same height but different widths. Each window is to have one curtain. The table lists the tasks involved in making the two curtains, their durations, and their immediate predecessors. The durations assume that only one person is working on the activity.
TaskDuration (minutes)Immediate predecessor(s)
Ameasure windows5-
Bcalculate material required5A
Cchoose material15-
Dbuy material15B, C
Ecut material5D
Fstitch sides of wide curtain30E
Gstitch top of wide curtain30F
Hstitch sides of narrow curtain30E
Istitch top of narrow curtain15H
Jhang curtains and pin hems20G, I
Khem wide curtain30J
Lhem narrow curtain15J
Mfit curtains10K, L
  1. Draw an activity on arc network for these activities.
  2. Mark on your diagram the early time and the late time for each event. Give the minimum completion time and the critical activities. Kate and Pete have two rooms to curtain, each identical to that above. Tasks A, B, C and D only need to be completed once each. All other tasks will have two versions, one for room 1 and one for room 2, eg E1 and E2. Kate and Pete share the tasks between them so that each task is completed by only one person.
  3. Complete the diagram to show how the tasks can be shared between them, and scheduled, so that the project can be completed in the least possible time. Give that least possible time.
  4. How much extra help would be needed to curtain both rooms in the minimum completion time from part (ii)? Explain your answer.
OCR MEI D1 2005 June Q3
8 marks Moderate -0.8
3 Table 3 gives the durations and immediate predecessors for the five activities of a project. \begin{table}[h]
ActivityDuration (hours)Immediate predecessor(s)
A3-
B2-
C5-
D2A
E1A, B
\captionsetup{labelformat=empty} \caption{Table 3}
\end{table}
  1. Draw an activity-on-arc network to represent the precedences.
  2. Find the early and late event times for the vertices of your network, and list the critical activities.
  3. Give the total and independent float for each activity which is not critical.
OCR MEI D1 2006 June Q4
16 marks Moderate -0.8
4 Table 4.1 shows some of the activities involved in preparing for a meeting. \begin{table}[h]
ActivityDuration (hours)Immediate predecessors
AAgree date1-
BConstruct agenda0.5-
CBook venue0.25A
DOrder refreshments0.25C
EInform participants0.5B, C
\captionsetup{labelformat=empty} \caption{Table 4.1}
\end{table}
  1. Draw an activity-on-arc network to represent the precedences.
  2. Find the early event time and the late event time for each vertex of your network, and list the critical activities.
  3. Assuming that each activity requires one person and that each activity starts at its earliest start time, draw a resource histogram.
  4. In fact although activity A has duration 1 hour, it actually involves only 0.5 hours work, since 0.5 hours involves waiting for replies. Given this information, and the fact that there is only one person available to do the work, what is the shortest time needed to prepare for the meeting? Fig. 4.2 shows an activity network for the tasks which have to be completed after the meeting. \begin{figure}[h]
    \includegraphics[alt={},max width=\textwidth]{c429bfed-9241-409a-9cd5-9553bf16c9df-5_533_844_1688_294} \captionsetup{labelformat=empty} \caption{Fig. 4.2}
    \end{figure} P: Clean room
    Q: Prepare draft minutes
    R: Allocate action tasks
    S: Circulate draft minutes
    T: Approve task allocations
    U: Obtain budgets for tasks
    V: Post minutes
    W: Pay refreshments bill
  5. Draw a precedence table for these activities.
OCR MEI D1 2007 June Q4
16 marks Moderate -0.3
4 Colin is setting off for a day's sailing. The table and the activity network show the major activities that are involved, their durations and their precedences.
ARig foresail
BLower sprayhood
CStart engine
DPump out bilges
ERig mainsail
FCast off mooring ropes
GMotor out of harbour
HRaise foresail
IRaise mainsail
JStop engine and start sailing
\includegraphics[max width=\textwidth, alt={}, center]{21ab732d-435e-4f0b-bc88-21ddc2a398c9-3_480_912_555_925}
  1. Complete the table in your answer book showing the immediate predecessors for each activity.
  2. Find the early time and the late time for each event. Give the project duration and list the critical activities. When he sails on his own Colin can only do one thing at a time with the exception of activity G, motoring out of the harbour.
  3. Use the activity network to determine which activities Colin can perform whilst motoring out of the harbour.
  4. Find the minimum time to complete the activities when Colin sails on his own, and give a schedule for him to achieve this.
  5. Find the minimum time to complete the activities when Colin sails with one other crew member, and give a schedule for them to achieve this.
OCR MEI D1 2008 June Q5
16 marks Moderate -0.5
5
  1. The graphs below illustrate the precedences involved in running two projects, each consisting of the same activities \(\mathrm { A } , \mathrm { B } , \mathrm { C } , \mathrm { D }\) and E . \begin{figure}[h]
    \captionsetup{labelformat=empty} \caption{Project 1} \includegraphics[alt={},max width=\textwidth]{8eba759f-38bc-4d14-ac65-9a0ee6c79741-6_280_385_429_495}
    \end{figure} \begin{figure}[h]
    \captionsetup{labelformat=empty} \caption{Project 2} \includegraphics[alt={},max width=\textwidth]{8eba759f-38bc-4d14-ac65-9a0ee6c79741-6_255_392_429_1187}
    \end{figure}
    1. For one activity the precedences in the two projects are different. State which activity and describe the difference.
    2. The table below shows the durations of the five activities.
      ActivityABCDE
      Duration21\(x\)32
      Give the total time for project 1 for all possible values of \(x\).
      Give the total time for project 2 for all possible values of \(x\).
  2. The durations and precedences for the activities in a project are shown in the table.
    ActivityDurationImmediate predecessors
    R2-
    S1-
    T5-
    w3R, S
    X2R, S, T
    Y3R
    Z1W, Y
    1. Draw an activity on arc network to represent this information.
    2. Find the early time and the late time for each event. Give the project duration and list the critical activities.
OCR MEI D1 2009 June Q6
16 marks Standard +0.3
6 Joan and Keith have to clear and tidy their garden. The table shows the jobs that have to be completed, their durations and their precedences.
JobsDuration (mins)Immediate predecessors
Aprune bushes100-
Bweed borders60A
Ccut hedges150-
Dhoe vegetable patch60-
Emow lawns40B
Fedge lawns20D, E
Gclean up cuttings30B, C
Hclean tools10F, G
  1. Draw an activity on arc network for these activities.
  2. Mark on your diagram the early time and the late time for each event. Give the minimum completion time and the critical activities.
  3. Each job is to be done by one person only. Joan and Keith are equally able to do all jobs. Draw a cascade chart indicating how to organise the jobs so that Joan and Keith can complete the project in the least time. Give that least time and explain why the minimum project completion time is shorter.
OCR MEI D1 2010 June Q6
16 marks Standard +0.3
6 The table shows the tasks that have to be completed in building a stadium for a sporting event, their durations and their precedences. The stadium has to be ready within two years.
TaskDuration (months)Immediate predecessors
A4-
B2-
C7-
D12A
E5A
F7A, B
G6D, J
H3C
I12E, F, H
J7E, F, H
K12C
  1. Draw an activity on arc network for these activities.
  2. Mark on your diagram the early time and the late time for each event. Give the project duration and the critical activities. In the later stages of planning the project it is discovered that task J will actually take 9 months to complete. However, other tasks can have their durations shortened by employing extra resources. The costs of "crashing" tasks (i.e. the costs of employing extra resources to complete them more quickly) are given in the table.
    Tasks which can be completed more quickly by employing extra resourcesNumber of months which can be savedCost per month of employing extra resources (£m)
    A23
    D11
    C33
    F22
    G24
  3. Find the cheapest way of completing the project within two years.
  4. If the delay in completing task J is not discovered until it is started, how can the project be completed in time, and how much extra will it cost?
OCR MEI D1 2011 June Q5
16 marks Moderate -0.3
5 The activity network and table together show the tasks involved in constructing a house extension, their durations and precedences. \includegraphics[max width=\textwidth, alt={}, center]{2e03f6fb-69db-438a-a79e-3e04fab0d08a-5_231_985_338_539}
ActivityDescriptionDuration (days)
AArchitect produces plans10
PlObtain planning permission14
DemoDemolish existing structure3
FoExcavate foundations4
WBuild walls3
PbInstall plumbing2
RConstruct roof3
FlLay floor2
EFit electrics2
WDInstall windows and doors1
DecoDecorate5
  1. Show the immediate predecessors for each activity.
  2. Perform a forward pass and a backward pass to find the early time and the late time for each event.
  3. Give the critical activities, the project duration, and the total float for each activity.
  4. The activity network includes one dummy activity. Explain why this dummy activity is needed. Whilst the foundations are being dug the customer negotiates the installation of a decorative corbel. This will take one day. It must be done after the walls have been built, and before the roof is constructed. The windows and doors cannot be installed until it is completed. It will not have any effect on the construction of the floor.
  5. Redraw the activity network incorporating this extra activity.
  6. Find the revised critical activities and the revised project duration.
OCR MEI D1 2012 June Q6
16 marks Moderate -0.8
6 The table shows the tasks involved in making a batch of buns, the time in minutes required for each task, and their precedences.
TaskTime (minutes)Immediate predecessors
Ameasure out flour0.5-
Bmix flour and water1A
Cshell eggs0.5-
Dmix in eggs and fat2B, C
Eget currants ready0.5-
Fget raisins ready0.5-
Gfold fruit into mix0.5D, E, F
Hbake10G
  1. Draw an activity on arc network for these activities.
  2. Mark on your diagram the early time and the late time for each event. Give the minimum completion time and the critical activities. Preparing the batch for baking consists of tasks A to G ; each of these tasks can only be done by one person. Baking, task H, requires no people.
  3. How many people are required to prepare the batch for baking in the minimum time?
  4. What is the minimum time required to prepare the batch for baking if only one person is available? Jim is preparing and baking three batches of buns. He has one oven available for baking. For the rest of the question you should consider 'preparing the batch for baking' as one activity.
  5. Assuming that the oven can bake only one batch at a time, draw an activity on arc diagram for this situation and give the minimum time in which the three batches of buns can be prepared and baked.
  6. Assuming that the oven is big enough to bake all three batches of buns at the same time, give the minimum time in which the three batches of buns can be prepared and baked.
OCR MEI D1 2014 June Q4
16 marks Moderate -0.3
4 The table lists tasks which are involved in adding a back door to a garage. The table also lists the duration and immediate predecessor(s) for each task. Each task is undertaken by one person.
TaskDuration (hours)Immediate predecessor(s)
Ameasure0.5-
Bmanufacture frame and door5A
Ccut hole in wall2A
Dfit lintel and marble step1.5C
Efit frame1B, C
Ffit door1E
Grepair plaster around door1E
  1. Draw an activity on arc network for these activities.
  2. Mark on your diagram the early time and the late time for each event. Give the minimum completion time and the critical activities.
  3. Produce a schedule to show how two people can complete the project in the minimum time. Soon after starting activity D , the marble step breaks. Getting a replacement step adds 4 hours to the duration of activity D.
  4. How does this delay affect the minimum completion time, the critical activities and the minimum time needed for two people to complete the project? \section*{Question 5 begins on page 6}
OCR MEI D1 2015 June Q5
16 marks Moderate -0.3
5 The table lists activities which are involved in framing a picture. The table also lists their durations and their immediate predecessors. Except for activities C and H, each activity is undertaken by one person. Activities C and H require no people.
ActivityDuration (mins)Immediate predecessor(s)
Aselect mounting5-
Bglue picture to mounting5A
Callow mounting glue to dry20B
Dmeasure for frame5A
Eselect type of frame10A
Fcut four frame pieces5D, E
Gpin and glue frame pieces together5F
Hallow frame glue to dry20G
Icut and bevel glass30D
Jfit glass to frame5H, I
Kfit mounted picture to frame5C, J
  1. Draw an activity on arc network for these activities.
  2. Mark on your diagram the early time and the late time for each event. Give the minimum completion time and the critical activities. A picture is to be framed as quickly as possible. Two people are available to do the job.
  3. Produce a schedule to show how two people can complete the picture framing in the minimum time. To reduce the completion time an instant glue is to be used. This will reduce the time for activities C and H to 0 minutes.
  4. Produce a schedule for two people to complete the framing in the new minimum completion time, and give that time.
OCR MEI D1 2016 June Q5
16 marks Moderate -0.8
5 A village amateur dramatic society is planning its annual pantomime. Three rooms in the village hall have been booked for one evening per week for 12 weeks. The following activities must take place. Their durations are shown.
ActivityDuration (weeks)
Achoose lead actors1
Bchoose rest of actors1
Cchoose dancers1
Drehearse lead actors8
Erehearse rest of actors6
Frehearse dancers6
Gprepare scenery6
Hinstall scenery1
Iprepare music2
Jmake costumes4
Kdress rehearsals2
Each activity needs a room except for activities G, I and J.
Choosing actors and dancers can be done in the same week. Rehearsals can begin after this. Rehearsing the dancers cannot begin until the music has been prepared. The scenery must be installed after rehearsals, but before dress rehearsals.
Making the costumes cannot start until after the actors and dancers have been chosen. Everything must be ready for the dress rehearsals in the final two weeks of the 12-week preparation period.
  1. Complete the table in your answer book by showing the immediate predecessors for each activity.
  2. Draw an activity on arc network for these activities.
  3. Mark on your network the early time and the late time for each event. Give the critical activities. It is discovered that there is a double booking and that one of the rooms will not be available after week 6.
  4. Using the space provided, produce a schedule showing how the pantomime can be ready in time for its first performance.
Edexcel D1 Q3
8 marks Moderate -0.8
3. This question should be answered on the sheet provided. \begin{figure}[h]
\includegraphics[alt={},max width=\textwidth]{6c6b7934-ab46-4a87-8a11-f99bf9a5d743-03_744_1524_319_315} \captionsetup{labelformat=empty} \caption{Fig. 2}
\end{figure} Figure 2 shows an activity network. The nodes represent events and the arcs represent the activities. The number in each bracket gives the time, in days, needed to complete the activity.
  1. Calculate the early and late times for each event using appropriate forward and backward scanning.
    (5 marks)
  2. Hence, determine the activities which lie on the critical path.
  3. State the minimum number of days needed to complete the entire project.
Edexcel D1 Q7
15 marks Moderate -0.3
7. This question should be answered on the sheet provided. \begin{figure}[h]
\includegraphics[alt={},max width=\textwidth]{acc09687-11a3-4392-af17-3d4d331d5ab4-08_586_1372_333_303} \captionsetup{labelformat=empty} \caption{Fig. 5}
\end{figure} The activity network in Figure 5 models the work involved in laying the foundations and putting in services for an industrial complex. The activities are represented by the arcs and the numbers in brackets give the time, in days, to complete each activity. Activity \(C\) is a dummy.
  1. Execute a forward scan to calculate the early times and a backward scan to calculate the late times, for each event.
  2. Determine which activities lie on the critical path and list them in order.
  3. State the minimum length of time needed to complete the project. The contractor is committed to completing the project in this minimum time and faces a penalty of \(\pounds 50000\) for each day that the project is late. Unfortunately, before any work has begun, flooding means that activity \(F\) will take 3 days longer than the 7 days allocated.
  4. Activity \(N\) could be completed in 1 day at an extra cost of \(\pounds 90000\). Explain why doing this is not economical.
    (3 marks)
  5. If the time taken to complete any one activity, other than \(F\), could be reduced by 2 days at an extra cost of \(\pounds 80000\), for which activities on their own would this be profitable. Explain your reasoning.
    (3 marks) END \section*{Please hand this sheet in for marking}
    ABCDE\(F\)
    A-130190155140125
    B130-215200190170
    C190215-110180100
    D155200110-7045
    E14019018070-75
    \(F\)1251701004575-
    \section*{Please hand this sheet in for marking}
    1. \(n\)\(x _ { n }\)\(a\)Any more data?\(x _ { n + 1 }\)\(b\)\(( b - a ) > 0\) ?\(a\)
      188Yes22No2
      2--
      Final output
    2. \(\_\_\_\_\) Sheet for answering question 3
      NAME \section*{Please hand this sheet in for marking}
      1. \includegraphics[max width=\textwidth, alt={}, center]{acc09687-11a3-4392-af17-3d4d331d5ab4-11_716_1218_502_331}
      2. \includegraphics[max width=\textwidth, alt={}, center]{acc09687-11a3-4392-af17-3d4d331d5ab4-11_709_1214_1498_333} Maximum flow =
      1. \(\_\_\_\_\)
      2. \(\_\_\_\_\) \section*{Please hand this sheet in for marking}
    3. \includegraphics[max width=\textwidth, alt={}, center]{acc09687-11a3-4392-af17-3d4d331d5ab4-12_764_1612_402_255}
    4. \(\_\_\_\_\)
    5. \(\_\_\_\_\)
    6. \(\_\_\_\_\)
    7. \(\_\_\_\_\)
Edexcel D1 Q7
16 marks Moderate -0.8
7. A project involves six tasks, some of which cannot be started until others have been completed. This is shown in the table below. \includegraphics[max width=\textwidth, alt={}, center]{e1fd42f7-c97c-4bf2-92d3-69afc8bb6e29-09_2036_1555_349_248}
  1. \(\_\_\_\_\)
  2. \(\_\_\_\_\) \section*{Sheet for answering question 5} NAME \section*{Please hand this sheet in for marking} Sheet for answering question 6
    NAME \section*{Please hand this sheet in for marking}
      1. \includegraphics[max width=\textwidth, alt={}, center]{e1fd42f7-c97c-4bf2-92d3-69afc8bb6e29-11_666_1280_461_374}
      2. \includegraphics[max width=\textwidth, alt={}, center]{e1fd42f7-c97c-4bf2-92d3-69afc8bb6e29-11_657_1276_1356_376} Maximum Flow = \(\_\_\_\_\)
    1. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
    2. \(\_\_\_\_\)
    3. \(\_\_\_\_\)
Edexcel D1 Q7
14 marks Standard +0.3
7. This question should be answered on the sheet provided. \begin{figure}[h]
\includegraphics[alt={},max width=\textwidth]{1e518ab0-9852-4d1d-a4c9-344a5edf9547-07_576_1360_331_278} \captionsetup{labelformat=empty} \caption{Fig. 2}
\end{figure} Figure 2 shows an activity network modelling the tasks involved in widening a bridge over the B451. The arcs represent the tasks and the numbers in brackets gives the time, in days, to complete each task.
  1. Find the early and late times for each event.
  2. Determine those activities which lie on the critical path and list them in order.
  3. State the minimum length of time needed to widen the bridge. Each task needs a single worker.
  4. Show that two men would not be sufficient to widen the bridge in the shortest time.
    (2 marks)
  5. Draw up a schedule showing how 3 men could complete the project in the shortest time. \section*{Please hand this sheet in for marking}
    1. Complete matching:
      \(P\)\(\bullet\)\(\bullet\)\(D\)
      \(Q\)\(\bullet\)\(\bullet\)\(G\)
      \(R\)\(\bullet\)\(\bullet\)\(E\)
      \(S\)\(\bullet\)\(\bullet\)\(L ( H )\)
      \(T\)\(\bullet\)\(\bullet\)\(L\)
      \section*{Please hand this sheet in for marking}
    2. \(x\)\(a\)\(b\)\(( a - b ) < 0.01\) ?
      1005026No
      -2614.923No
      Final output
    3. \(\_\_\_\_\)
    4. \(x\)\(a\)\(b\)\(( a - b ) < 0.01 ?\)
      100
    5. \(\_\_\_\_\) \section*{Please hand this sheet in for marking}
    6. \includegraphics[max width=\textwidth, alt={}, center]{1e518ab0-9852-4d1d-a4c9-344a5edf9547-11_768_1689_427_221}
    7. \(\_\_\_\_\)
    8. \(\_\_\_\_\)
    9. 051015202530354045505560
      Worker 1
      Worker 2
    10. 051015202530354045505560
      Worker 1
      Worker 2
      Worker 3
AQA D2 2010 January Q1
13 marks Moderate -0.8
1 [Figures 1 and 2, printed on the insert, are provided for use in this question.]
Figure 1 shows the activity network and the duration, in days, of each activity for a particular project.
  1. On Figure 1:
    1. find the earliest start time for each activity;
    2. find the latest finish time for each activity.
  2. Find the float for activity \(G\).
  3. Find the critical paths and state the minimum time for completion.
  4. The number of workers required for each activity is shown in the table.
    Activity\(A\)\(B\)\(C\)\(D\)\(E\)\(F\)\(G\)\(H\)\(I\)\(J\)
    Number of workers required2232321352
    Given that each activity starts as late as possible and assuming that there is no limit to the number of workers available, draw a resource histogram for the project on Figure 2, indicating clearly which activities take place at any given time.
AQA D2 2011 January Q1
14 marks Moderate -0.5
1
A group of workers is involved in a decorating project. The table shows the activities involved. Each worker can perform any of the given activities.
ActivityA\(B\)CD\(E\)\(F\)GHI\(J\)\(K\)\(L\)
Duration (days)256794323231
Number of workers required635252445324
The activity network for the project is given in Figure 1 below.
  1. Find the earliest start time and the latest finish time for each activity, inserting their values on Figure 1.
  2. Hence find:
    1. the critical path;
    2. the float time for activity \(D\).
      1. \begin{figure}[h]
        \captionsetup{labelformat=empty} \caption{Figure 1} \includegraphics[alt={},max width=\textwidth]{172c5c92-4254-4593-b741-1caa83a1e833-02_647_1657_1640_180}
        \end{figure}
        1. The critical path is \(\_\_\_\_\)
        2. The float time for activity \(D\) is \(\_\_\_\_\)
    3. Given that each activity starts as early as possible and assuming that there is no limit to the number of workers available, draw a resource histogram for the project on Figure 2 below, indicating clearly which activities are taking place at any given time.
    4. It is later discovered that there are only 8 workers available at any time. Use resource levelling to construct a new resource histogram on Figure 3 below, showing how the project can be completed with the minimum extra time. State the minimum extra time required.
    5. \begin{figure}[h]
      \captionsetup{labelformat=empty} \caption{Figure 2} \includegraphics[alt={},max width=\textwidth]{172c5c92-4254-4593-b741-1caa83a1e833-03_586_1708_922_150}
      \end{figure}
    6. \begin{figure}[h]
      \captionsetup{labelformat=empty} \caption{Figure 3} \includegraphics[alt={},max width=\textwidth]{172c5c92-4254-4593-b741-1caa83a1e833-03_496_1705_1672_153}
      \end{figure} The minimum extra time required is \(\_\_\_\_\)
AQA D2 2012 January Q1
14 marks Standard +0.3
1 The diagram shows the activity network and the duration, in days, of each activity for a particular project. Some of the earliest start times and latest finish times are shown on the diagram. \includegraphics[max width=\textwidth, alt={}, center]{b23828c8-01ee-4b5a-b6d2-41b7e27190d6-02_830_1447_678_301}
  1. Find the values of the constants \(x , y\) and \(z\).
  2. Find the critical paths.
  3. Find the activity with the largest float and state the value of this float.
  4. The number of workers required for each activity is shown in the table.
    Activity\(A\)\(B\)\(C\)\(D\)\(E\)\(F\)\(G\)\(H\)\(I\)\(J\)
    Number of workers required4234243356
    Given that each activity starts as early as possible and assuming that there is no limit to the number of workers available, draw a resource histogram for the project on Figure 1 below, indicating clearly which activities are taking place at any given time.
  5. It is later discovered that there are only 9 workers available at any time. Use resource levelling to find the new earliest start time for activity \(J\) so that the project can be completed with the minimum extra time. State the minimum extra time required. (d) Number of workers \begin{figure}[h]
    \captionsetup{labelformat=empty} \caption{Figure 1} \includegraphics[alt={},max width=\textwidth]{b23828c8-01ee-4b5a-b6d2-41b7e27190d6-03_803_1330_1224_468}
    \end{figure}