AQA Further Paper 3 Discrete 2023 June — Question 7 6 marks

Exam BoardAQA
ModuleFurther Paper 3 Discrete (Further Paper 3 Discrete)
Year2023
SessionJune
Marks6
PaperDownload PDF ↗
Mark schemeDownload PDF ↗
TopicCritical Path Analysis
TypeDraw cascade/Gantt chart
DifficultyModerate -0.8 This is a standard critical path analysis question requiring routine application of forward/backward pass algorithms, identifying the critical path, and drawing a Gantt chart. These are textbook procedures in Decision Maths with minimal problem-solving required. Part (c) requires basic understanding of how removing non-critical activities affects project duration. While multi-part, each component is algorithmic and well-practiced.
Spec7.05a Critical path analysis: activity on arc networks7.05b Forward and backward pass: earliest/latest times, critical activities

7
    1. Find the earliest start time and the latest finish time for each activity and write these values on the activity network in Figure 1 7
      1. (ii) Write down the critical path. 7
    2. On Figure 2 below, draw a cascade diagram (Gantt chart) for the planned building project, assuming that each activity starts as early as possible. \begin{figure}[h]
      \captionsetup{labelformat=empty} \caption{Figure 2} \includegraphics[alt={},max width=\textwidth]{5ff6e3bb-6392-49cf-b64d-23bc595cd92e-11_1127_1641_539_201}
      \end{figure} 7
    3. During further planning of the building project, Nova Merit Construction find that activity \(F\) is not necessary and they remove it from the project. Explain the effect removing activity \(F\) has on the minimum completion time of the project.

Question 7(a)(i):
AnswerMarks Guidance
Earliest start times correctly foundB1 See activity network diagram
Latest finish times correctly foundB1 See activity network diagram
Activity network values:
- \(A\): \(0 \mid 12 \mid 18\)
- \(B\): \(0 \mid 17 \mid 17\)
- \(C\): \(0 \mid 16 \mid 17\)
- \(D\): \(17 \mid 11 \mid 29\)
- \(E\): \(17 \mid 12 \mid 29\)
- \(F\): \(29 \mid 7 \mid 36\)
- \(G\): \(29 \mid 5 \mid 36\)
- \(H\): \(36 \mid 6 \mid 45\)
- \(I\): \(36 \mid 8 \mid 45\)
- \(J\): \(36 \mid 9 \mid 45\)
- \(K\): \(45 \mid 4 \mid 49\)
Question 7(a)(ii):
AnswerMarks Guidance
Critical path is \(BEFJK\)B1 Must be correct path stated
Question 7(b):
AnswerMarks Guidance
Translates activity network into diagram showing and labelling all 11 activitiesM1 AO 3.1a
All 5 critical activities shown correctly, either on individual rows or all on single rowA1 AO 1.1b
Fully correct diagram including all labelling and all floats. Condone float of 5 for activity \(A\) if latest finish time is 17 in (a)(i)A1 AO 1.1b
Question 7(c):
AnswerMarks Guidance
Removing activity \(F\) makes \(G\) critical, and \(G\) has a duration 2 weeks less than activity \(F\). Explains that activity \(G\) now becomes critical OR earliest start time of \(H\), \(I\) and \(J\) each decreases by 2 weeks, PI by earliest start time of 34 for \(H\), \(I\) and \(J\) shown on activity networkB1 AO 1.1b
Therefore the minimum completion time for the project reduces by 2 weeks. Deduces that minimum completion time reduces by 2 weeks or reduces to 47 weeksB1 AO 2.2a
## Question 7(a)(i):

Earliest start times correctly found | B1 | See activity network diagram
Latest finish times correctly found | B1 | See activity network diagram

Activity network values:
- $A$: $0 \mid 12 \mid 18$
- $B$: $0 \mid 17 \mid 17$
- $C$: $0 \mid 16 \mid 17$
- $D$: $17 \mid 11 \mid 29$
- $E$: $17 \mid 12 \mid 29$
- $F$: $29 \mid 7 \mid 36$
- $G$: $29 \mid 5 \mid 36$
- $H$: $36 \mid 6 \mid 45$
- $I$: $36 \mid 8 \mid 45$
- $J$: $36 \mid 9 \mid 45$
- $K$: $45 \mid 4 \mid 49$

---

## Question 7(a)(ii):

Critical path is $BEFJK$ | B1 | Must be correct path stated

---

## Question 7(b):

Translates activity network into diagram showing and labelling all 11 activities | M1 | AO 3.1a
All 5 critical activities shown correctly, either on individual rows or all on single row | A1 | AO 1.1b
Fully correct diagram including all labelling and all floats. Condone float of 5 for activity $A$ if latest finish time is 17 in (a)(i) | A1 | AO 1.1b

---

## Question 7(c):

Removing activity $F$ makes $G$ critical, and $G$ has a duration 2 weeks less than activity $F$. Explains that activity $G$ now becomes critical OR earliest start time of $H$, $I$ and $J$ each decreases by 2 weeks, PI by earliest start time of 34 for $H$, $I$ and $J$ shown on activity network | B1 | AO 1.1b

Therefore the minimum completion time for the project reduces by 2 weeks. Deduces that minimum completion time reduces by 2 weeks or reduces to 47 weeks | B1 | AO 2.2a

---
7
\begin{enumerate}[label=(\alph*)]
\item (i) Find the earliest start time and the latest finish time for each activity and write these values on the activity network in Figure 1

7 (a) (ii) Write down the critical path.

7
\item On Figure 2 below, draw a cascade diagram (Gantt chart) for the planned building project, assuming that each activity starts as early as possible.

\begin{figure}[h]
\begin{center}
\captionsetup{labelformat=empty}
\caption{Figure 2}
  \includegraphics[alt={},max width=\textwidth]{5ff6e3bb-6392-49cf-b64d-23bc595cd92e-11_1127_1641_539_201}
\end{center}
\end{figure}

7
\item During further planning of the building project, Nova Merit Construction find that activity $F$ is not necessary and they remove it from the project.

Explain the effect removing activity $F$ has on the minimum completion time of the project.
\end{enumerate}

\hfill \mbox{\textit{AQA Further Paper 3 Discrete 2023 Q7 [6]}}