AQA
Further Paper 3 Discrete
2023
June
— Question 7
Exam Board
AQA
Module
Further Paper 3 Discrete (Further Paper 3 Discrete)
Year
2023
Session
June
Topic
Critical Path Analysis
7
Find the earliest start time and the latest finish time for each activity and write these values on the activity network in Figure 1
7
(ii) Write down the critical path.
7
On Figure 2 below, draw a cascade diagram (Gantt chart) for the planned building project, assuming that each activity starts as early as possible.
\begin{figure}[h]
During further planning of the building project, Nova Merit Construction find that activity \(F\) is not necessary and they remove it from the project.
Explain the effect removing activity \(F\) has on the minimum completion time of the project.