AQA Further Paper 3 Discrete 2023 June — Question 7

Exam BoardAQA
ModuleFurther Paper 3 Discrete (Further Paper 3 Discrete)
Year2023
SessionJune
TopicCritical Path Analysis

7
    1. Find the earliest start time and the latest finish time for each activity and write these values on the activity network in Figure 1 7
  1. (ii) Write down the critical path. 7
  2. On Figure 2 below, draw a cascade diagram (Gantt chart) for the planned building project, assuming that each activity starts as early as possible. \begin{figure}[h]
    \captionsetup{labelformat=empty} \caption{Figure 2} \includegraphics[alt={},max width=\textwidth]{5ff6e3bb-6392-49cf-b64d-23bc595cd92e-11_1127_1641_539_201}
    \end{figure} 7
  3. During further planning of the building project, Nova Merit Construction find that activity \(F\) is not necessary and they remove it from the project. Explain the effect removing activity \(F\) has on the minimum completion time of the project.