AQA Further AS Paper 2 Discrete 2022 June — Question 3 4 marks

Exam BoardAQA
ModuleFurther AS Paper 2 Discrete (Further AS Paper 2 Discrete)
Year2022
SessionJune
Marks4
PaperDownload PDF ↗
Mark schemeDownload PDF ↗
TopicCritical Path Analysis
TypeEffect of activity delay/change
DifficultyModerate -0.5 Part (a) requires simply reading the critical path from a completed activity network diagram (1 mark). Part (b) involves understanding how doubling activity G's duration affects downstream activities' earliest start and latest finish times - this requires basic critical path analysis concepts but is straightforward application once the network is given. The question tests understanding rather than construction or complex reasoning, making it slightly easier than average.
Spec7.05a Critical path analysis: activity on arc networks7.05b Forward and backward pass: earliest/latest times, critical activities

3 A project consists of 11 activities \(A , B , \ldots , K\) A completed activity network for the project is shown in the diagram below. \includegraphics[max width=\textwidth, alt={}, center]{ecbeedf5-148e-40ad-b8a2-a7aa3db4a115-04_972_1604_445_219} All times on the activity network are given in days.
3
  1. Write down the critical path.
    [0pt] [1 mark] 3
  2. Due to an issue with the supply of materials, the duration of activity \(G\) is doubled. Deduce the effect, if any, that this change will have on the earliest start time and latest finish time for each of the activities \(I , J\) and \(K\)

Question 3(a):
AnswerMarks Guidance
Critical path is \(ADEHK\)B1 Must state correct critical path and no others
Question 3(b):
AnswerMarks Guidance
Uses model to assess effect of change of activity \(G\) on earliest start times of activities \(I\) and \(J\), or states that \(G\) remains non-criticalM1 PI by A1
States explicitly that earliest start time and latest finish time of activity \(K\) remain unchangedB1
Deduces that earliest start times of \(I\) and \(J\) increase to 14 and that latest finish times of \(I\) and \(J\) are unchangedA1
## Question 3(a):

Critical path is $ADEHK$ | B1 | Must state correct critical path and no others

---

## Question 3(b):

Uses model to assess effect of change of activity $G$ on earliest start times of activities $I$ and $J$, or states that $G$ remains non-critical | M1 | PI by A1

States explicitly that earliest start time and latest finish time of activity $K$ remain unchanged | B1 |

Deduces that earliest start times of $I$ and $J$ increase to 14 and that latest finish times of $I$ and $J$ are unchanged | A1 |

---
3 A project consists of 11 activities $A , B , \ldots , K$

A completed activity network for the project is shown in the diagram below.\\
\includegraphics[max width=\textwidth, alt={}, center]{ecbeedf5-148e-40ad-b8a2-a7aa3db4a115-04_972_1604_445_219}

All times on the activity network are given in days.\\
3
\begin{enumerate}[label=(\alph*)]
\item Write down the critical path.\\[0pt]
[1 mark]

3
\item Due to an issue with the supply of materials, the duration of activity $G$ is doubled.

Deduce the effect, if any, that this change will have on the earliest start time and latest finish time for each of the activities $I , J$ and $K$
\end{enumerate}

\hfill \mbox{\textit{AQA Further AS Paper 2 Discrete 2022 Q3 [4]}}