AQA Further AS Paper 2 Discrete 2019 June — Question 2 1 marks

Exam BoardAQA
ModuleFurther AS Paper 2 Discrete (Further AS Paper 2 Discrete)
Year2019
SessionJune
Marks1
PaperDownload PDF ↗
Mark schemeDownload PDF ↗
TopicCritical Path Analysis
TypeFind missing early/late times
DifficultyModerate -0.5 This is a straightforward critical path analysis question requiring students to recognize that if ABC is on the critical path, then early and late times must be equal at each node, leading to a simple equation to solve for d. It tests basic understanding of critical path concepts but requires minimal calculation and no complex problem-solving.
Spec7.05a Critical path analysis: activity on arc networks7.05b Forward and backward pass: earliest/latest times, critical activities

2 Part of an activity network is shown in the diagram below. \(A B C\) is part of the critical path of the activity network. \includegraphics[max width=\textwidth, alt={}, center]{dcf97b92-d067-41d4-89a6-ea5bab9ea4ff-04_264_908_447_566} The duration of activity \(B\) is \(d\).
Which of the following statements about \(d\) is correct? Circle your answer. $$0 < d < 10 \quad d = 10 \quad 10 < d < 20 \quad d = 20$$

Question 2:
AnswerMarks Guidance
AnswerMark Guidance
\(d = 10\)B1 Circles correct answer
Total: 1 mark
## Question 2:

| Answer | Mark | Guidance |
|--------|------|----------|
| $d = 10$ | B1 | Circles correct answer |

**Total: 1 mark**

---
2 Part of an activity network is shown in the diagram below.\\
$A B C$ is part of the critical path of the activity network.\\
\includegraphics[max width=\textwidth, alt={}, center]{dcf97b92-d067-41d4-89a6-ea5bab9ea4ff-04_264_908_447_566}

The duration of activity $B$ is $d$.\\
Which of the following statements about $d$ is correct?

Circle your answer.

$$0 < d < 10 \quad d = 10 \quad 10 < d < 20 \quad d = 20$$

\hfill \mbox{\textit{AQA Further AS Paper 2 Discrete 2019 Q2 [1]}}