AQA D2 2014 June — Question 8

Exam BoardAQA
ModuleD2 (Decision Mathematics 2)
Year2014
SessionJune
TopicCritical Path Analysis

8 An activity diagram for a project is shown below. The duration of each activity is given in weeks. The earliest start time and the latest finish time for each activity are shown on the diagram.
\includegraphics[max width=\textwidth, alt={}, center]{c2b62fee-d320-4701-a5bb-b2e4b8cc0952-22_640_1626_475_209}
  1. Find the values of \(x , y\) and \(z\).
  2. State the critical path.
  3. Some of the activities can be speeded up at an additional cost. The following table lists the activities that can be speeded up together with the minimum possible duration of these activities. The table also shows the additional cost of reducing the duration of each of these activities by one week.