AQA D2 2014 June — Question 1 9 marks

Exam BoardAQA
ModuleD2 (Decision Mathematics 2)
Year2014
SessionJune
Marks9
PaperDownload PDF ↗
Mark schemeDownload PDF ↗
TopicCritical Path Analysis
TypeDraw activity network from table
DifficultyModerate -0.8 This is a straightforward application of standard activity network construction from a precedence table. It requires only mechanical application of rules for drawing activity-on-arc networks with no problem-solving or novel insight—purely procedural recall of D2 techniques, making it easier than average.
Spec7.05a Critical path analysis: activity on arc networks7.05b Forward and backward pass: earliest/latest times, critical activities

1 A major project has been divided into a number of tasks, as shown in the table. The minimum time required to complete each task is also shown. \section*{Answer space for question 1}
\includegraphics[max width=\textwidth, alt={}]{c2b62fee-d320-4701-a5bb-b2e4b8cc0952-03_424_410_296_685}

Question 1:
Part (a) - Activity Network [3 marks]
AnswerMarks Guidance
AnswerMark Guidance
Correct boxes for \(B\) and \(C\) (predecessors of \(A\), durations 3 and 4)B1 Both boxes correctly drawn with EST and duration
Correct boxes for \(D\), \(E\), \(F\), \(G\), \(H\) with correct predecessorsB1 All arrows correctly showing dependencies
Correct boxes for \(I\), \(J\), \(K\), \(L\) with correct predecessors and single end nodeB1 \(L\) correctly shown with predecessors \(H\), \(I\), \(J\), \(K\)
Part (b) - Earliest Start Times [2 marks]
AnswerMarks Guidance
AnswerMark Guidance
\(A=0\), \(B=3\), \(C=3\), \(H=3\), \(F=7\), \(G=7\)M1 Forward pass attempted
\(D=7\), \(E=7\), \(I=12\), \(J=9\), \(K=8\), \(L=18\)A1 All correct ESTs
Part (c) - Latest Finish Times [2 marks]
AnswerMarks Guidance
AnswerMark Guidance
Backward pass attempted from \(L=19\)M1 Working backwards correctly
\(L=19\), \(K=19\), \(J=19\), \(I=19\), \(H=18\), \(G=9\), \(F=13\), \(E=14\), \(D=13\), \(C=7\), \(B=7\), \(A=3\)A1 All correct LFTs
Part (d) - Critical Activities [2 marks]
AnswerMarks Guidance
AnswerMark Guidance
Correct identification of critical pathB1 \(A\), \(C\), \(D\), \(I\), \(L\) or equivalent stated
All critical activities listed correctlyB1 Must follow from correct EST/LFT values
# Question 1:

## Part (a) - Activity Network [3 marks]

| Answer | Mark | Guidance |
|--------|------|----------|
| Correct boxes for $B$ and $C$ (predecessors of $A$, durations 3 and 4) | B1 | Both boxes correctly drawn with EST and duration |
| Correct boxes for $D$, $E$, $F$, $G$, $H$ with correct predecessors | B1 | All arrows correctly showing dependencies |
| Correct boxes for $I$, $J$, $K$, $L$ with correct predecessors and single end node | B1 | $L$ correctly shown with predecessors $H$, $I$, $J$, $K$ |

## Part (b) - Earliest Start Times [2 marks]

| Answer | Mark | Guidance |
|--------|------|----------|
| $A=0$, $B=3$, $C=3$, $H=3$, $F=7$, $G=7$ | M1 | Forward pass attempted |
| $D=7$, $E=7$, $I=12$, $J=9$, $K=8$, $L=18$ | A1 | All correct ESTs |

## Part (c) - Latest Finish Times [2 marks]

| Answer | Mark | Guidance |
|--------|------|----------|
| Backward pass attempted from $L=19$ | M1 | Working backwards correctly |
| $L=19$, $K=19$, $J=19$, $I=19$, $H=18$, $G=9$, $F=13$, $E=14$, $D=13$, $C=7$, $B=7$, $A=3$ | A1 | All correct LFTs |

## Part (d) - Critical Activities [2 marks]

| Answer | Mark | Guidance |
|--------|------|----------|
| Correct identification of critical path | B1 | $A$, $C$, $D$, $I$, $L$ or equivalent stated |
| All critical activities listed correctly | B1 | Must follow from correct EST/LFT values |

---
1 A major project has been divided into a number of tasks, as shown in the table. The minimum time required to complete each task is also shown.

\section*{Answer space for question 1}
\begin{center}
\includegraphics[max width=\textwidth, alt={}]{c2b62fee-d320-4701-a5bb-b2e4b8cc0952-03_424_410_296_685}
\end{center}

\hfill \mbox{\textit{AQA D2 2014 Q1 [9]}}