1 [Figures 1 and 2, printed on the insert, are provided for use in this question.]
The following diagram shows an activity network for a project. The time needed for each activity is given in days.
\includegraphics[max width=\textwidth, alt={}, center]{f98d4434-458a-4118-92ed-309510d7975a-02_940_1698_721_164}
- Find the earliest start time and the latest finish time for each activity and insert their values on Figure 1.
- Find the critical paths and state the minimum time for completion.
- On Figure 2, draw a cascade diagram (Gantt chart) for the project, assuming each activity starts as early as possible.
- Activity \(C\) takes 5 days longer than first expected. Determine the effect on the earliest start time for other activities and the minimum completion time for the project.
(2 marks)