AQA D2 2007 January — Question 1

Exam BoardAQA
ModuleD2 (Decision Mathematics 2)
Year2007
SessionJanuary
TopicCritical Path Analysis

1 [Figure 1, printed on the insert, is provided for use in this question.]
A building project is to be undertaken. The table shows the activities involved.
ActivityImmediate PredecessorsDuration (weeks)
A-2
B-1
CA3
DA, B2
EB4
FC1
G\(C , D , E\)3
HE5
I\(F , G\)2
J\(H , I\)3
  1. Complete an activity network for the project on Figure 1.
  2. Find the earliest start time for each activity.
  3. Find the latest finish time for each activity.
  4. State the minimum completion time for the building project and identify the critical paths.