Identify critical path and activities

A question is this type if and only if it asks you to determine which activities lie on the critical path and/or state the minimum project completion time.

4 questions · Easy -1.1

7.05a Critical path analysis: activity on arc networks
Sort by: Default | Easiest first | Hardest first
OCR D2 Specimen Q4
13 marks Moderate -0.5
4 Henry is planning a surprise party for Lucinda. He has left the arrangements until the last moment, so he will hold the party at their home. The table below lists the activities involved, the expected durations, the immediate predecessors and the number of people needed for each activity. Henry has some friends who will help him, so more than one activity can be done at a time.
ActivityDuration (hours)Preceded byNumber of people
A: Telephone other friends2-3
\(B\) : Buy food1A2
C: Prepare food4B5
D: Make decorations3A3
\(E\) : Put up decorations1D3
\(F\) : Guests arrive1C, E1
  1. Draw an activity network to represent these activities and the precedences. Carry out forward and reverse passes to determine the minimum completion time and the critical activities. If Lucinda is expected home at 7.00 p.m., what is the latest time that Henry or his friends can begin telephoning the other friends?
  2. Draw a resource histogram showing time on the horizontal axis and number of people needed on the vertical axis, assuming that each activity starts at its earliest possible start time. What is the maximum number of people needed at any one time?
  3. Now suppose that Henry's friends can start buying the food and making the decorations as soon as the telephoning begins. Construct a timetable, with a column for 'time' and a column for each person, showing who should do which activity when, in order than the party can be organised in the minimum time using a total of only six people (Henry and five friends). When should the telephoning begin with this schedule?
AQA D2 2007 January Q1
11 marks Easy -1.2
1 [Figure 1, printed on the insert, is provided for use in this question.]
A building project is to be undertaken. The table shows the activities involved.
ActivityImmediate PredecessorsDuration (weeks)
A-2
B-1
CA3
DA, B2
EB4
FC1
G\(C , D , E\)3
HE5
I\(F , G\)2
J\(H , I\)3
  1. Complete an activity network for the project on Figure 1.
  2. Find the earliest start time for each activity.
  3. Find the latest finish time for each activity.
  4. State the minimum completion time for the building project and identify the critical paths.
AQA Further Paper 3 Discrete 2021 June Q1
1 marks Easy -1.8
1 Which of the following statements about critical path analysis is always true? Tick ( \(\checkmark\) ) one box. All activity networks have exactly one critical path. □ All critical activities have a non-zero float. □ The first activity in a critical path has an earliest start time of zero. □ A delay on a critical activity may not delay the project. □
OCR D2 Q2
12 marks Moderate -0.8
ActivityTimePrecedence
A5
B20A
C3A
D7A
E4B
F15C
G6C
H17D
I10F, G
J2G, H
K6E, I
L9I, J
M3K, L
Fig. 1 Construct an activity network Use appropriate forward and backward scanning to find
  1. the minimum number of days needed to complete the entire project, [3 marks]
  2. the activities which lie on the critical path. [3 marks]
[6 marks]