AQA Further Paper 3 Discrete Specimen — Question 3 7 marks

Exam BoardAQA
ModuleFurther Paper 3 Discrete (Further Paper 3 Discrete)
SessionSpecimen
Marks7
PaperDownload PDF ↗
Mark schemeDownload PDF ↗
TopicCritical Path Analysis
TypeEffect of activity delay/change
DifficultyModerate -0.3 This is a straightforward critical path analysis question requiring standard forward/backward pass calculations and identifying which critical activity to reduce. Part (b) only requires testing activities on the critical path, and part (c) asks for a standard limitation discussion. While it's Further Maths content, it's a routine application of the CPA algorithm with no novel problem-solving required.
Spec7.05a Critical path analysis: activity on arc networks7.05b Forward and backward pass: earliest/latest times, critical activities7.05c Total float: calculation and interpretation

3 Deva Construction Ltd undertakes a small building project. The activity network for this project is shown below in Figure 1, where each activity's duration is given in hours. \begin{figure}[h]
\captionsetup{labelformat=empty} \caption{Figure 1} \includegraphics[alt={},max width=\textwidth]{88669bc0-9d3f-431a-8939-8aef2682412b-04_844_1428_552_395}
\end{figure} 3
  1. Complete the activity network for the building project. 3
  2. Deva Construction Ltd is able to reduce the duration of a single activity to 1 hour by using specialist equipment. State, with a reason, which activity should have its duration reduced to 1 hour in order to minimise the completion time for the building project.
    3
  3. State one limitation in the building project used by Deva Construction Ltd. Explain how this limitation affects the project.
    [0pt] [2 marks]

Question 3(a):
AnswerMarks Guidance
AnswerMarks Guidance
Correct earliest start time for each activityB1
Correct latest finish time for each activityB1
Question 3(b):
AnswerMarks Guidance
AnswerMarks Guidance
Evaluates effect of reducing duration of one activity on project completion timeM1 Reducing activity \(E\) duration to 1 hour reduces project completion time to 14 hours; all other activities reduce it to 15 hours or more
Compares effects of reducing each critical activity on project completion timeM1
Activity \(E\) clearly identifiedR1 From correct reasoning
Question 3(c):
AnswerMarks Guidance
AnswerMarks Guidance
Correctly identifies a limitation in context of the projectB1 e.g. time between one activity ending and the next starting not accounted for, as workers may need to travel to a different location
Explains how the identified limitation affects project in time or monetary termsE1 e.g. travelling time will cause subsequent activities to be delayed, increasing project completion time
Total: 7 marks
## Question 3(a):

| Answer | Marks | Guidance |
|--------|-------|----------|
| Correct earliest start time for each activity | B1 | |
| Correct latest finish time for each activity | B1 | |

---

## Question 3(b):

| Answer | Marks | Guidance |
|--------|-------|----------|
| Evaluates effect of reducing duration of one activity on project completion time | M1 | Reducing activity $E$ duration to 1 hour reduces project completion time to 14 hours; all other activities reduce it to 15 hours or more |
| Compares effects of reducing each critical activity on project completion time | M1 | |
| Activity $E$ clearly identified | R1 | From correct reasoning |

---

## Question 3(c):

| Answer | Marks | Guidance |
|--------|-------|----------|
| Correctly identifies a limitation in context of the project | B1 | e.g. time between one activity ending and the next starting not accounted for, as workers may need to travel to a different location |
| Explains how the identified limitation affects project in time or monetary terms | E1 | e.g. travelling time will cause subsequent activities to be delayed, increasing project completion time |

**Total: 7 marks**
3 Deva Construction Ltd undertakes a small building project. The activity network for this project is shown below in Figure 1, where each activity's duration is given in hours.

\begin{figure}[h]
\begin{center}
\captionsetup{labelformat=empty}
\caption{Figure 1}
  \includegraphics[alt={},max width=\textwidth]{88669bc0-9d3f-431a-8939-8aef2682412b-04_844_1428_552_395}
\end{center}
\end{figure}

3
\begin{enumerate}[label=(\alph*)]
\item Complete the activity network for the building project.

3
\item Deva Construction Ltd is able to reduce the duration of a single activity to 1 hour by using specialist equipment.

State, with a reason, which activity should have its duration reduced to 1 hour in order to minimise the completion time for the building project.\\

3
\item State one limitation in the building project used by Deva Construction Ltd.

Explain how this limitation affects the project.\\[0pt]
[2 marks]
\end{enumerate}

\hfill \mbox{\textit{AQA Further Paper 3 Discrete  Q3 [7]}}