OCR MEI D1 2005 June — Question 3 8 marks

Exam BoardOCR MEI
ModuleD1 (Decision Mathematics 1)
Year2005
SessionJune
Marks8
TopicCritical Path Analysis

3 Table 3 gives the durations and immediate predecessors for the five activities of a project. \begin{table}[h]
ActivityDuration (hours)Immediate predecessor(s)
A3-
B2-
C5-
D2A
E1A, B
\captionsetup{labelformat=empty} \caption{Table 3}
\end{table}
  1. Draw an activity-on-arc network to represent the precedences.
  2. Find the early and late event times for the vertices of your network, and list the critical activities.
  3. Give the total and independent float for each activity which is not critical.