OCR MEI D1 2009 January — Question 5 16 marks

Exam BoardOCR MEI
ModuleD1 (Decision Mathematics 1)
Year2009
SessionJanuary
Marks16
PaperDownload PDF ↗
Mark schemeDownload PDF ↗
TopicCritical Path Analysis
TypeCalculate early and late times
DifficultyModerate -0.8 This is a standard Critical Path Analysis question requiring routine application of forward and backward passes to find early/late times, identification of critical path, and basic optimization of task durations. The network is small (8 activities), the precedence relationships are straightforward, and part (iii) only requires comparing a few combinations to reduce completion time by 10 minutes—all mechanical procedures covered in D1 with no novel problem-solving required.
Spec7.05a Critical path analysis: activity on arc networks7.05b Forward and backward pass: earliest/latest times, critical activities7.05c Total float: calculation and interpretation

5 The tasks involved in turning around an "AirGB" aircraft for its return flight are listed in the table. The table gives the durations of the tasks and their immediate predecessors.
ActivityDuration (mins)Immediate Predecessors
A Refuel30-
B Clean cabin25-
C Pre-flight technical check15A
D Load luggage20-
E Load passengers25A, B
F Safety demonstration5E
G Obtain air traffic clearance10C
H Taxi to runway5G, D
  1. Draw an activity on arc network for these activities.
  2. Mark on your diagram the early time and the late time for each event. Give the minimum completion time and the critical activities. Because of delays on the outbound flight the aircraft has to be turned around within 50 minutes, so as not to lose its air traffic slot for the return journey. There are four tasks on which time can be saved. These, together with associated costs, are listed below.
    TaskABDE
    New time (mins)20201515
    Extra cost2505050100
  3. List the activities which need to be speeded up in order to turn the aircraft around within 50 minutes at minimum extra cost. Give the extra cost and the new set of critical activities.

Question 5:
Parts (i) & (ii)
AnswerMarks Guidance
Answer/WorkingMarks Guidance
Activity on arc network drawnM1 sca (activity on arc)
Single start and end nodeA1 single start & end
Dummy activity included correctlyA1 dummy
Remaining activities correctA1 rest
Correct forward passM1 forward pass
Forward pass values correctA1
Correct backward passM1 backward pass
Backward pass values correctA1
Time = 60 minutesB1 \(\checkmark\)
Critical path: \(A; C; E; F; G; H\)B1 cao
Part (iii)
AnswerMarks Guidance
Answer/WorkingMarks Guidance
A and B both needed at £300 eachB1 2 out of A, B, E
Activity A identifiedB1 A
Activity B identifiedB1 B
Cost = £300 from A and BB1 300 from A and B
Schedule: \(A; C; G; H\) and \(B; E; F\)B1
Both sequences correctB1
# Question 5:

## Parts (i) & (ii)

| Answer/Working | Marks | Guidance |
|---|---|---|
| Activity on arc network drawn | M1 | sca (activity on arc) |
| Single start and end node | A1 | single start & end |
| Dummy activity included correctly | A1 | dummy |
| Remaining activities correct | A1 | rest |
| Correct forward pass | M1 | forward pass |
| Forward pass values correct | A1 | |
| Correct backward pass | M1 | backward pass |
| Backward pass values correct | A1 | |
| Time = 60 minutes | B1 | $\checkmark$ |
| Critical path: $A; C; E; F; G; H$ | B1 | cao |

## Part (iii)

| Answer/Working | Marks | Guidance |
|---|---|---|
| A and B both needed at £300 each | B1 | 2 out of A, B, E |
| Activity A identified | B1 | A |
| Activity B identified | B1 | B |
| Cost = £300 from A and B | B1 | 300 from A and B |
| Schedule: $A; C; G; H$ and $B; E; F$ | B1 | |
| Both sequences correct | B1 | |

---
5 The tasks involved in turning around an "AirGB" aircraft for its return flight are listed in the table. The table gives the durations of the tasks and their immediate predecessors.

\begin{center}
\begin{tabular}{|l|l|l|}
\hline
Activity & Duration (mins) & Immediate Predecessors \\
\hline
A Refuel & 30 & - \\
\hline
B Clean cabin & 25 & - \\
\hline
C Pre-flight technical check & 15 & A \\
\hline
D Load luggage & 20 & - \\
\hline
E Load passengers & 25 & A, B \\
\hline
F Safety demonstration & 5 & E \\
\hline
G Obtain air traffic clearance & 10 & C \\
\hline
H Taxi to runway & 5 & G, D \\
\hline
\end{tabular}
\end{center}

(i) Draw an activity on arc network for these activities.\\
(ii) Mark on your diagram the early time and the late time for each event. Give the minimum completion time and the critical activities.

Because of delays on the outbound flight the aircraft has to be turned around within 50 minutes, so as not to lose its air traffic slot for the return journey. There are four tasks on which time can be saved. These, together with associated costs, are listed below.

\begin{center}
\begin{tabular}{ | l | c | c | c | c | }
\hline
Task & A & B & D & E \\
\hline
New time (mins) & 20 & 20 & 15 & 15 \\
\hline
Extra cost & 250 & 50 & 50 & 100 \\
\hline
\end{tabular}
\end{center}

(iii) List the activities which need to be speeded up in order to turn the aircraft around within 50 minutes at minimum extra cost. Give the extra cost and the new set of critical activities.

\hfill \mbox{\textit{OCR MEI D1 2009 Q5 [16]}}