OCR Further Discrete 2017 Specimen — Question 2 13 marks

Exam BoardOCR
ModuleFurther Discrete (Further Discrete)
Year2017
SessionSpecimen
Marks13
TopicCritical Path Analysis
TypeSchedule with limited workers - create schedule/chart
DifficultyStandard +0.3 This is a standard critical path analysis question requiring cascade chart construction, float calculations (total/independent/interfering), and resource scheduling. While it involves multiple parts and careful bookkeeping, these are routine algorithmic procedures taught in Further Discrete with no novel problem-solving required. The techniques are mechanical once learned, making it slightly easier than average for Further Maths content.
Spec7.05a Critical path analysis: activity on arc networks7.05b Forward and backward pass: earliest/latest times, critical activities7.05c Total float: calculation and interpretation7.05d Latest start and earliest finish: independent and interfering float

Kirstie has bought a house that she is planning to renovate. She has broken the project into a list of activities and constructed an activity network, using activity on arc. \includegraphics{figure_1}
  1. Construct a cascade chart for the project, showing the float for each non-critical activity. [7]
  2. Calculate the float for remodelling the internal layout stating how much of this is independent float and how much is interfering float. [3]
Kirstie needs to supervise the project. This means that she cannot allow more than three activities to happen on any day.
  1. Describe how Kirstie should organise the activities so that the project is completed in the minimum project completion time and no more than three activities happen on any day. [3]

Kirstie has bought a house that she is planning to renovate. She has broken the project into a list of activities and constructed an activity network, using activity on arc.

\includegraphics{figure_1}

\begin{enumerate}[label=(\roman*)]
\item Construct a cascade chart for the project, showing the float for each non-critical activity. [7]

\item Calculate the float for remodelling the internal layout stating how much of this is independent float and how much is interfering float. [3]
\end{enumerate}

Kirstie needs to supervise the project. This means that she cannot allow more than three activities to happen on any day.

\begin{enumerate}[label=(\roman*)]
\setcounter{enumi}{2}
\item Describe how Kirstie should organise the activities so that the project is completed in the minimum project completion time and no more than three activities happen on any day. [3]
\end{enumerate}

\hfill \mbox{\textit{OCR Further Discrete 2017 Q2 [13]}}