AQA Paper 1 2019 June — Question 15 13 marks

Exam BoardAQA
ModulePaper 1 (Paper 1)
Year2019
SessionJune
Marks13
PaperDownload PDF ↗
Mark schemeDownload PDF ↗
TopicParametric curves and Cartesian conversion
TypeFind parameter from gradient condition
DifficultyStandard +0.3 This is a straightforward parametric equations question requiring routine substitution and solving simple equations. Part (a) involves direct substitution at t=0, solving a quadratic for v=0, and another substitution. Part (b) requires finding the maximum of a quadratic (completing the square or differentiation) and substitution. Part (c) is a standard modelling comment. All techniques are standard A-level fare with no novel insight required, making it slightly easier than average.
Spec1.03g Parametric equations: of curves and conversion to cartesian1.07s Parametric and implicit differentiation

At time \(t\) hours after a high tide, the height, \(h\) metres, of the tide and the velocity, \(v\) knots, of the tidal flow can be modelled using the parametric equations $$v = 4 - \left(\frac{2t}{3} - 2\right)^2$$ $$h = 3 - 2\sqrt[3]{t - 3}$$ High tides and low tides occur alternately when the velocity of the tidal flow is zero. A high tide occurs at 2am.
    1. Use the model to find the height of this high tide. [1 mark]
    2. Find the time of the first low tide after 2am. [3 marks]
    3. Find the height of this low tide. [1 mark]
  1. Use the model to find the height of the tide when it is flowing with maximum velocity. [3 marks]
  2. Comment on the validity of the model. [2 marks]

Question 15:

(a)(iii) ---
15
AnswerMarks
(a)(iii)Obtains correct h for their positive t
provided h < 5.88
Accept 0.12
If given to more decimal places
AWFW 0.115 to 0.116
AnswerMarks Guidance
FT their t allow negative hAO3.4 B1F
15(b)
AnswerMarks Guidance
15(c)Identifies t=3 (for maximum
velocity)AO3.1b B1
h=3−23 3−3
h = 3 metres
Substitutes their t into model for h
AnswerMarks Guidance
PI their answer3.4 M1
Finds correct height with units3.2a A1
Explains that the validity of the
AnswerMarks Guidance
model is limited by time.3.5b B1
cycle of the tide.
After 6 hours the model shows
the height continues to decrease.
Explains that the height continues
to decrease after 6 hours (or after
the first cycle or first low tide).
Or explains there are no other
AnswerMarks Guidance
times when v=03.5a B1
Total10
QMarking instructions AO
Question 15:
--- 15
(a)(iii) ---
15
(a)(iii) | Obtains correct h for their positive t
provided h < 5.88
Accept 0.12
If given to more decimal places
AWFW 0.115 to 0.116
FT their t allow negative h | AO3.4 | B1F | 0.12m
15(b)
15(c) | Identifies t=3 (for maximum
velocity) | AO3.1b | B1 | t = 3
h=3−23 3−3
h = 3 metres
Substitutes their t into model for h
PI their answer | 3.4 | M1
Finds correct height with units | 3.2a | A1
Explains that the validity of the
model is limited by time. | 3.5b | B1 | The model breaks down after one
cycle of the tide.
After 6 hours the model shows
the height continues to decrease.
Explains that the height continues
to decrease after 6 hours (or after
the first cycle or first low tide).
Or explains there are no other
times when v=0 | 3.5a | B1
Total | 10
Q | Marking instructions | AO | Mark | Typical solution
At time $t$ hours after a high tide, the height, $h$ metres, of the tide and the velocity, $v$ knots, of the tidal flow can be modelled using the parametric equations

$$v = 4 - \left(\frac{2t}{3} - 2\right)^2$$

$$h = 3 - 2\sqrt[3]{t - 3}$$

High tides and low tides occur alternately when the velocity of the tidal flow is zero.

A high tide occurs at 2am.

\begin{enumerate}[label=(\alph*)]
\item 
\begin{enumerate}[label=(\roman*)]
\item Use the model to find the height of this high tide. [1 mark]
\item Find the time of the first low tide after 2am. [3 marks]
\item Find the height of this low tide. [1 mark]
\end{enumerate}

\item Use the model to find the height of the tide when it is flowing with maximum velocity. [3 marks]

\item Comment on the validity of the model. [2 marks]
\end{enumerate}

\hfill \mbox{\textit{AQA Paper 1 2019 Q15 [13]}}