4 A community project consists of 10 activities \(A , B , \ldots , J\), as shown in the activity network below.
\includegraphics[max width=\textwidth, alt={}, center]{372edcfa-c3cd-4c83-89e9-2bb5fd9825f1-06_899_1083_367_466}
The duration of each activity is shown in days.
4
- Complete the activity network in the diagram above, showing the earliest start time and latest finish time for each activity.
4
- (ii) State the minimum completion time for the community project.
4 - Write down the critical activities of the network.
4 - Glyn claims that a project's activity network can be used to determine its minimum completion time by adding together the durations of all the project's critical activities.
4
- Show that Glyn's claim is false for this community project's activity network.
4
- (ii) Describe a situation in which Glyn's claim would be true.