OCR D2 — Question 5 12 marks

Exam BoardOCR
ModuleD2 (Decision Mathematics 2)
Marks12
PaperDownload PDF ↗
Mark schemeDownload PDF ↗
TopicCritical Path Analysis
TypeDraw activity network from table
DifficultyModerate -0.8 This is a standard Critical Path Analysis question requiring routine application of well-defined algorithms. Parts (a)-(b) involve straightforward network construction and critical path identification from a simple precedence table. Parts (c)-(d) add a timing constraint requiring a dummy activity, which is a textbook technique in D2. The question involves no novel problem-solving or complex reasoning—just methodical application of standard procedures.
Spec7.05a Critical path analysis: activity on arc networks7.05b Forward and backward pass: earliest/latest times, critical activities7.05c Total float: calculation and interpretation7.05d Latest start and earliest finish: independent and interfering float

  1. A project involves six tasks, some of which cannot be started until others have been completed. This is shown in the table below.
TaskDuration (minutes)Immediate predecessors
A18-
B23-
C13\(A , B\)
D9A
E28\(B , D\)
\(F\)23C
  1. Draw an activity network for this project.
  2. By labelling your network, find the critical path and the minimum duration of the project. An extra condition is now imposed. Task \(A\) may not begin until task \(B\) has been underway for at least 10 minutes.
  3. Draw a new network taking into account this restriction.
  4. Find a revised value for the minimum duration of the project and state the new critical path.

Question 5:
AnswerMarks Guidance
Answer/WorkingMark Guidance
(a) Network with correct forward and backward scan values completedM1 A2
(b) Lower figures give forward scanM1
Upper figures give backward scanM1
Critical path is \(BCF\)A1
Minimum time is 59 minutesA1
(c) New network with \(B\) split into \(B_1, B_2\); correct forward and backward scan valuesM1 A1
(d) New minimum time is 65 minutesM1 A1
New critical path is \(B_1ADE\)A1 (12)
# Question 5:

| Answer/Working | Mark | Guidance |
|---|---|---|
| **(a)** Network with correct forward and backward scan values completed | M1 A2 | |
| **(b)** Lower figures give forward scan | M1 | |
| Upper figures give backward scan | M1 | |
| Critical path is $BCF$ | A1 | |
| Minimum time is 59 minutes | A1 | |
| **(c)** New network with $B$ split into $B_1, B_2$; correct forward and backward scan values | M1 A1 | |
| **(d)** New minimum time is 65 minutes | M1 A1 | |
| New critical path is $B_1ADE$ | A1 | **(12)** |

---
\begin{enumerate}
  \item A project involves six tasks, some of which cannot be started until others have been completed. This is shown in the table below.
\end{enumerate}

\begin{center}
\begin{tabular}{|l|l|l|}
\hline
Task & Duration (minutes) & Immediate predecessors \\
\hline
A & 18 & - \\
\hline
B & 23 & - \\
\hline
C & 13 & $A , B$ \\
\hline
D & 9 & A \\
\hline
E & 28 & $B , D$ \\
\hline
$F$ & 23 & C \\
\hline
\end{tabular}
\end{center}

(a) Draw an activity network for this project.\\
(b) By labelling your network, find the critical path and the minimum duration of the project.

An extra condition is now imposed. Task $A$ may not begin until task $B$ has been underway for at least 10 minutes.\\
(c) Draw a new network taking into account this restriction.\\
(d) Find a revised value for the minimum duration of the project and state the new critical path.\\

\hfill \mbox{\textit{OCR D2  Q5 [12]}}