OCR MEI D1 2005 January — Question 4 16 marks

Exam BoardOCR MEI
ModuleD1 (Decision Mathematics 1)
Year2005
SessionJanuary
Marks16
PaperDownload PDF ↗
Mark schemeDownload PDF ↗
TopicCritical Path Analysis
TypeDraw activity network from table
DifficultyModerate -0.8 This is a standard textbook critical path analysis question requiring routine application of well-defined algorithms (drawing network, forward/backward pass, finding float). The precedence table is straightforward with no ambiguities, and parts (i)-(iii) are mechanical procedures taught in D1. Part (iv) scheduling adds minor complexity but follows standard methods. Easier than average A-level as it's purely algorithmic with no problem-solving insight required.
Spec7.05b Forward and backward pass: earliest/latest times, critical activities7.05c Total float: calculation and interpretation7.05d Latest start and earliest finish: independent and interfering float

4 Answer this question on the insert provided. The table shows activities involved in a "perm" in a hair salon, their durations and immediate predecessors. \begin{table}[h]
ActivityDuration (mins)Immediate predecessor(s)
Ashampoo5-
Bprepare perm lotion2-
Cmake coffee for customer3-
Dtrim5A
Eclean sink3A
Fput rollers in15D
Gclean implements3D
Happly perm lotion5B, F
Ileave to set20C,H
Jclean lotion pot and spreaders3H
Kneutralise and rinse10I, E
Ldry10K
Mwash up and clean up15K
Nstyle4G, L
\captionsetup{labelformat=empty} \caption{Table 4}
\end{table}
  1. Complete the activity-on-arc network in the insert to represent the precedences.
  2. Perform a forward pass and a backward pass to find early and late event times. Give the critical activities and the time needed to complete the perm.
  3. Give the total float time for the activity \(G\). Activities \(\mathrm { D } , \mathrm { F } , \mathrm { H } , \mathrm { K }\) and N require a stylist.
    Activities \(\mathrm { A } , \mathrm { B } , \mathrm { C } , \mathrm { E } , \mathrm { G } , \mathrm { J }\) and M are done by a trainee.
    Activities \(I\) and \(L\) require no-one in attendance.
    A stylist and a trainee are to give a perm to a customer.
  4. Use the chart in the insert to show a schedule for the activities, assuming that all activities are started as early as possible.
  5. Which activity would be better started at its latest start time?

Question 4:
Parts (i) & (ii)
AnswerMarks Guidance
AnswerMarks Guidance
Network drawn with single start/end nodeM1
I and J correctly placedA1
Activities A D F H K L N correctA1
Activities B C E G M correctA1
Forward pass correctM1 A1
Backward pass correctM1 A1
Results correctB1 B1
Critical path: A, D, F, H, I, K, M; duration = 75 minutesB1 B1
Part (iii)
AnswerMarks Guidance
AnswerMarks Guidance
Total float for G = 58B1\(\checkmark\) Follow through
Part (iv)
AnswerMarks Guidance
AnswerMarks Guidance
Gantt chart with stylist row correctM1 A1
Gantt chart with trainee row correctA1
Part (v)
AnswerMarks Guidance
AnswerMarks Guidance
C — make coffeeB1
# Question 4:

## Parts (i) & (ii)
| Answer | Marks | Guidance |
|--------|-------|----------|
| Network drawn with single start/end node | M1 | |
| I and J correctly placed | A1 | |
| Activities A D F H K L N correct | A1 | |
| Activities B C E G M correct | A1 | |
| Forward pass correct | M1 A1 | |
| Backward pass correct | M1 A1 | |
| Results correct | B1 B1 | |
| Critical path: A, D, F, H, I, K, M; duration = 75 minutes | B1 B1 | |

## Part (iii)
| Answer | Marks | Guidance |
|--------|-------|----------|
| Total float for G = 58 | B1$\checkmark$ | Follow through |

## Part (iv)
| Answer | Marks | Guidance |
|--------|-------|----------|
| Gantt chart with stylist row correct | M1 A1 | |
| Gantt chart with trainee row correct | A1 | |

## Part (v)
| Answer | Marks | Guidance |
|--------|-------|----------|
| C — make coffee | B1 | |

---
4 Answer this question on the insert provided.
The table shows activities involved in a "perm" in a hair salon, their durations and immediate predecessors.

\begin{table}[h]
\begin{center}
\begin{tabular}{|l|l|l|l|}
\hline
 & Activity & Duration (mins) & Immediate predecessor(s) \\
\hline
A & shampoo & 5 & - \\
\hline
B & prepare perm lotion & 2 & - \\
\hline
C & make coffee for customer & 3 & - \\
\hline
D & trim & 5 & A \\
\hline
E & clean sink & 3 & A \\
\hline
F & put rollers in & 15 & D \\
\hline
G & clean implements & 3 & D \\
\hline
H & apply perm lotion & 5 & B, F \\
\hline
I & leave to set & 20 & C,H \\
\hline
J & clean lotion pot and spreaders & 3 & H \\
\hline
K & neutralise and rinse & 10 & I, E \\
\hline
L & dry & 10 & K \\
\hline
M & wash up and clean up & 15 & K \\
\hline
N & style & 4 & G, L \\
\hline
\end{tabular}
\captionsetup{labelformat=empty}
\caption{Table 4}
\end{center}
\end{table}

(i) Complete the activity-on-arc network in the insert to represent the precedences.\\
(ii) Perform a forward pass and a backward pass to find early and late event times. Give the critical activities and the time needed to complete the perm.\\
(iii) Give the total float time for the activity $G$.

Activities $\mathrm { D } , \mathrm { F } , \mathrm { H } , \mathrm { K }$ and N require a stylist.\\
Activities $\mathrm { A } , \mathrm { B } , \mathrm { C } , \mathrm { E } , \mathrm { G } , \mathrm { J }$ and M are done by a trainee.\\
Activities $I$ and $L$ require no-one in attendance.\\
A stylist and a trainee are to give a perm to a customer.\\
(iv) Use the chart in the insert to show a schedule for the activities, assuming that all activities are started as early as possible.\\
(v) Which activity would be better started at its latest start time?

\hfill \mbox{\textit{OCR MEI D1 2005 Q4 [16]}}