Edexcel FD1 2023 June — Question 2

Exam BoardEdexcel
ModuleFD1 (Further Decision 1)
Year2023
SessionJune
TopicCritical Path Analysis

2. \begin{figure}[h]
\includegraphics[alt={},max width=\textwidth]{6ccce35f-4e62-4b6b-acf6-f9b3e18d4b52-04_474_958_210_555} \captionsetup{labelformat=empty} \caption{Figure 3}
\end{figure} The network in Figure 3 shows the activities that need to be undertaken to complete a project. Each activity is represented by an arc and the duration, in hours, of the corresponding activity is shown in brackets.
    1. Complete Diagram 1 in the answer book to show the early event times and the late event times.
    2. State the minimum completion time of the project. The table below lists the number of workers required for each activity in the project.
      ActivityNumber of workers
      A2
      B1
      C2
      D2
      E3
      F2
      G1
      H3
      Each worker is able to do any of the activities. Once an activity is started it must be completed without interruption. It is given that each activity begins at its earliest possible start time.
    1. On Grid 1 in the answer book, draw a resource histogram to show the number of workers required at each time.
    2. Hence state the time interval(s) when six workers are required.