Edexcel FD1 2021 June — Question 7 8 marks

Exam BoardEdexcel
ModuleFD1 (Further Decision 1)
Year2021
SessionJune
Marks8
PaperDownload PDF ↗
Mark schemeDownload PDF ↗
TopicCritical Path Analysis
TypeIdentify guaranteed critical activities
DifficultyModerate -0.5 This is a standard Critical Path Analysis question from Further Maths Decision 1. Part (a) requires reading a network diagram, part (b) is routine network construction with dummies, and part (c) asks for conceptual understanding of critical activities. While it requires careful work and understanding of CPA conventions, it follows standard textbook patterns with no novel problem-solving required. Slightly easier than average A-level due to being methodical rather than requiring insight.
Spec7.05a Critical path analysis: activity on arc networks

7. \begin{figure}[h]
\includegraphics[alt={},max width=\textwidth]{43bc1e60-d8b2-4ea5-9652-4603a26c2f78-08_583_670_260_699} \captionsetup{labelformat=empty} \caption{Figure 5}
\end{figure} Figure 5 shows a partially completed activity network for a project that consists of 14 activities.
  1. Complete the precedence table in the answer book for the 8 activities in Figure 5. The precedence table for the remaining 6 activities is given below.
    ActivityImmediately preceding activities
    ID, E, G, H
    JD, E, G, H
    KE, G, H
    LI, J, K
    MJ, K
    NJ, K
  2. Complete the activity network in the answer book for the project. Your completed activity network must contain only the minimum number of dummies. Given that all 14 activities have the same duration,
  3. explain why activity D cannot be critical.

Question 7(a):
AnswerMarks Guidance
AnswerMark Guidance
Either row G or H correct: G preceded by B, F; H preceded by B, C, FB1 1.1b
All rows correct (condone blanks in A, B, C rows)B1 1.1b
Question 7(b):
AnswerMarks Guidance
AnswerMark Guidance
At least five activities (labelled on arc), at least two dummies placedM1 2.1
Activities I, J, K and first dummy + arrow dealt with correctlyA1 1.1b
Activities L, M, N and a second dummy + arrows dealt with correctlyA1 1.1b
cso – all arrows present for every activity, exactly one finish, exactly three dummiesA1 1.1b; note M and N could be interchanged
IPA reference table:
AnswerMarks Guidance
ActivityI J
IPAD, E, G, H D, E, G, H
Question 7(c):
AnswerMarks Guidance
AnswerMark Guidance
All critical paths must contain 5 activities (oe, e.g. forward/backward pass with equal durations)B1 2.4
D cannot be critical as all paths through D only contain 4 activities (oe, e.g. total float on D is non-zero)B1 2.4; SCB1 for stating/implying D has float of 1 by forward pass consideration
# Question 7(a):

| Answer | Mark | Guidance |
|--------|------|----------|
| Either row G or H correct: G preceded by B, F; H preceded by B, C, F | B1 | 1.1b |
| All rows correct (condone blanks in A, B, C rows) | B1 | 1.1b |

# Question 7(b):

| Answer | Mark | Guidance |
|--------|------|----------|
| At least five activities (labelled on arc), at least two dummies placed | M1 | 2.1 |
| Activities I, J, K and first dummy + arrow dealt with correctly | A1 | 1.1b |
| Activities L, M, N and a second dummy + arrows dealt with correctly | A1 | 1.1b |
| cso – all arrows present for every activity, exactly one finish, exactly three dummies | A1 | 1.1b; note M and N could be interchanged |

**IPA reference table:**

| Activity | I | J | K | L | M | N |
|----------|---|---|---|---|---|---|
| IPA | D, E, G, H | D, E, G, H | E, G, H | I, J, K | J, K | J, K |

# Question 7(c):

| Answer | Mark | Guidance |
|--------|------|----------|
| All critical paths must contain 5 activities (oe, e.g. forward/backward pass with equal durations) | B1 | 2.4 |
| D cannot be critical as all paths through D only contain 4 activities (oe, e.g. total float on D is non-zero) | B1 | 2.4; SCB1 for stating/implying D has float of 1 by forward pass consideration |
7.

\begin{figure}[h]
\begin{center}
  \includegraphics[alt={},max width=\textwidth]{43bc1e60-d8b2-4ea5-9652-4603a26c2f78-08_583_670_260_699}
\captionsetup{labelformat=empty}
\caption{Figure 5}
\end{center}
\end{figure}

Figure 5 shows a partially completed activity network for a project that consists of 14 activities.
\begin{enumerate}[label=(\alph*)]
\item Complete the precedence table in the answer book for the 8 activities in Figure 5.

The precedence table for the remaining 6 activities is given below.

\begin{center}
\begin{tabular}{ | c | c | }
\hline
Activity & Immediately preceding activities \\
\hline
I & D, E, G, H \\
\hline
J & D, E, G, H \\
\hline
K & E, G, H \\
\hline
L & I, J, K \\
\hline
M & J, K \\
\hline
N & J, K \\
\hline
\end{tabular}
\end{center}
\item Complete the activity network in the answer book for the project. Your completed activity network must contain only the minimum number of dummies.

Given that all 14 activities have the same duration,
\item explain why activity D cannot be critical.
\end{enumerate}

\hfill \mbox{\textit{Edexcel FD1 2021 Q7 [8]}}