Edexcel FD1 2021 June — Question 7

Exam BoardEdexcel
ModuleFD1 (Further Decision 1)
Year2021
SessionJune
TopicCritical Path Analysis

7. \begin{figure}[h]
\includegraphics[alt={},max width=\textwidth]{43bc1e60-d8b2-4ea5-9652-4603a26c2f78-08_583_670_260_699} \captionsetup{labelformat=empty} \caption{Figure 5}
\end{figure} Figure 5 shows a partially completed activity network for a project that consists of 14 activities.
  1. Complete the precedence table in the answer book for the 8 activities in Figure 5. The precedence table for the remaining 6 activities is given below.
    ActivityImmediately preceding activities
    ID, E, G, H
    JD, E, G, H
    KE, G, H
    LI, J, K
    MJ, K
    NJ, K
  2. Complete the activity network in the answer book for the project. Your completed activity network must contain only the minimum number of dummies. Given that all 14 activities have the same duration,
  3. explain why activity D cannot be critical.