Edexcel D1 2003 November — Question 4

Exam BoardEdexcel
ModuleD1 (Decision Mathematics 1)
Year2003
SessionNovember
TopicCritical Path Analysis

4. (a) Draw an activity network described in this precedence table, using as few dummies as possible.
ActivityMust be preceded by:
A-
BA
CA
DA
EC
FC
GB, \(D , E , F\)
H\(B , D , E , F\)
IF, \(D\)
JG, H, I
K\(F , D\)
L\(K\)
  1. A different project is represented by the activity network shown in Fig. 3. The duration of each activity is shown in brackets. \begin{figure}[h]
    \captionsetup{labelformat=empty} \caption{Figure 3} \includegraphics[alt={},max width=\textwidth]{75ea31c7-11e7-4dd9-9312-4cf32bba622b-05_710_1580_1509_239}
    \end{figure} Find the range of values of \(x\) that will make \(D\) a critical activity.
    (2)