Edexcel D1 2003 November — Question 4 7 marks

Exam BoardEdexcel
ModuleD1 (Decision Mathematics 1)
Year2003
SessionNovember
Marks7
PaperDownload PDF ↗
Mark schemeDownload PDF ↗
TopicCritical Path Analysis
TypeFind range for variable duration
DifficultyStandard +0.3 This is a straightforward critical path analysis question requiring students to identify when activity D becomes critical by setting up and solving simple inequalities. It involves standard D1 techniques (comparing path lengths) with minimal algebraic manipulation, making it slightly easier than average for A-level maths.
Spec7.05a Critical path analysis: activity on arc networks7.05b Forward and backward pass: earliest/latest times, critical activities

4. (a) Draw an activity network described in this precedence table, using as few dummies as possible.
ActivityMust be preceded by:
A-
BA
CA
DA
EC
FC
GB, \(D , E , F\)
H\(B , D , E , F\)
IF, \(D\)
JG, H, I
K\(F , D\)
L\(K\)
  1. A different project is represented by the activity network shown in Fig. 3. The duration of each activity is shown in brackets. \begin{figure}[h]
    \captionsetup{labelformat=empty} \caption{Figure 3} \includegraphics[alt={},max width=\textwidth]{75ea31c7-11e7-4dd9-9312-4cf32bba622b-05_710_1580_1509_239}
    \end{figure} Find the range of values of \(x\) that will make \(D\) a critical activity.
    (2)

Question 4:
Part (a)
AnswerMarks Guidance
Precedence network diagram as shown (with nodes A,B,C,D,E,F,G,H,I,J,K,L)M1, A1, A1, A1, A1, A1 (6)
Part (b)
D will only be critical if it lies on a longest route.
\(ABEG - 14\)
\(ACFG - 15\)
AnswerMarks Guidance
\(ACDEG - 13 + x\)M1
So D critical if \(x \geq 2\) (must be \(\geq\) not \(>\))A1 (2)
Total: 8 marks
# Question 4:

## Part (a)
Precedence network diagram as shown (with nodes A,B,C,D,E,F,G,H,I,J,K,L) | M1, A1, A1, A1, A1, A1 | (6)

## Part (b)
D will only be critical if it lies on a longest route.

$ABEG - 14$
$ACFG - 15$
$ACDEG - 13 + x$ | M1 |

So D critical if $x \geq 2$ (must be $\geq$ not $>$) | A1 | (2)

**Total: 8 marks**

---
4. (a) Draw an activity network described in this precedence table, using as few dummies as possible.

\begin{center}
\begin{tabular}{|l|l|}
\hline
Activity & Must be preceded by: \\
\hline
A & - \\
\hline
B & A \\
\hline
C & A \\
\hline
D & A \\
\hline
E & C \\
\hline
F & C \\
\hline
G & B, $D , E , F$ \\
\hline
H & $B , D , E , F$ \\
\hline
I & F, $D$ \\
\hline
J & G, H, I \\
\hline
K & $F , D$ \\
\hline
L & $K$ \\
\hline
\end{tabular}
\end{center}

(a) A different project is represented by the activity network shown in Fig. 3. The duration of each activity is shown in brackets.

\begin{figure}[h]
\begin{center}
\captionsetup{labelformat=empty}
\caption{Figure 3}
  \includegraphics[alt={},max width=\textwidth]{75ea31c7-11e7-4dd9-9312-4cf32bba622b-05_710_1580_1509_239}
\end{center}
\end{figure}

Find the range of values of $x$ that will make $D$ a critical activity.\\
(2)\\

\hfill \mbox{\textit{Edexcel D1 2003 Q4 [7]}}