OCR Further Discrete 2023 June — Question 1 7 marks

Exam BoardOCR
ModuleFurther Discrete (Further Discrete)
Year2023
SessionJune
Marks7
PaperDownload PDF ↗
Mark schemeDownload PDF ↗
TopicCritical Path Analysis
TypeEffect of activity delay/change
DifficultyModerate -0.5 This is a straightforward critical path analysis question requiring standard techniques: drawing an activity network, finding earliest/latest times, and analyzing the effect of a delay. While it involves multiple steps, all are routine algorithmic procedures covered in any Decision Maths textbook with no novel problem-solving required.
Spec7.05a Critical path analysis: activity on arc networks7.05b Forward and backward pass: earliest/latest times, critical activities

1 The table below shows the activities involved in a project together with the immediate predecessors and the duration of each activity.
ActivityImmediate predecessorsDuration (hours)
A-2
BA3
C-4
DC2
EB, C2
FD, E3
GE2
HF, G1
  1. Model the project using an activity network.
  2. Determine the minimum project completion time. The start of activity C is delayed by 2 hours.
  3. Determine the minimum project completion time with this delay.

Question 1:
AnswerMarks Guidance
1(a) A(2) B(3) E(2) G(2)
H(1)
AnswerMarks
C(4) D(2) F(3)M1
A1
B1
AnswerMarks
[3]3.3
1.1
AnswerMarks
3.3Activity on arc
Durations not necessary, ignore any working
Single start, precedences correct for A, B, C, D
Single finish, precedences correct for E, F, G, H
Correct use of exactly 2 directed dummy activities
AnswerMarks Guidance
1(b) A(2) 2 B(3) 5 E(2) 7 G(2)
0 10 11
H(1)
C(4) 4 D(2) 7 F(3)
AnswerMarks
11 (hours)M1
A1
AnswerMarks
[2]3.4
1.1Forward pass attempted for their network
Ignore backward pass if shown
Or 2+3+2+3+1 seen
cao
SC B1 answer 11 without valid method seen
AnswerMarks Guidance
1(c) A(2) 2 B(3) 6 E(2) 8 G(2)
0 11 12
H(1)
C(6) 6 D(2) 8 F(3)
AnswerMarks
12 (hours)M1
A1
AnswerMarks
[2]3.4
2.2aAppropriate reasoning
e.g. C becomes critical
delays E by 1 hour o.e.
E starts at 6 instead of 5, E finishes at 8, o.e.
Or 6 + 2 + 3 + 1 seen
cao
SC B1 answer 12 without valid method seen
AnswerMarks Guidance
10 2
10 0.5
10 0
Question 1:
1 | (a) | A(2) B(3) E(2) G(2)
H(1)
C(4) D(2) F(3) | M1
A1
B1
[3] | 3.3
1.1
3.3 | Activity on arc
Durations not necessary, ignore any working
Single start, precedences correct for A, B, C, D
Single finish, precedences correct for E, F, G, H
Correct use of exactly 2 directed dummy activities
1 | (b) | A(2) 2 B(3) 5 E(2) 7 G(2)
0 10 11
H(1)
C(4) 4 D(2) 7 F(3)
11 (hours) | M1
A1
[2] | 3.4
1.1 | Forward pass attempted for their network
Ignore backward pass if shown
Or 2+3+2+3+1 seen
cao
SC B1 answer 11 without valid method seen
1 | (c) | A(2) 2 B(3) 6 E(2) 8 G(2)
0 11 12
H(1)
C(6) 6 D(2) 8 F(3)
12 (hours) | M1
A1
[2] | 3.4
2.2a | Appropriate reasoning
e.g. C becomes critical
delays E by 1 hour o.e.
E starts at 6 instead of 5, E finishes at 8, o.e.
Or 6 + 2 + 3 + 1 seen
cao
SC B1 answer 12 without valid method seen
1 | 0 | 2 | -1 | 0 | 1 | 6
1 | 0 | 0.5 | 0 | 1 | -1.5 | 11
1 | 0 | 0 | 60/k
1 The table below shows the activities involved in a project together with the immediate predecessors and the duration of each activity.

\begin{center}
\begin{tabular}{|l|l|l|}
\hline
Activity & Immediate predecessors & Duration (hours) \\
\hline
A & - & 2 \\
\hline
B & A & 3 \\
\hline
C & - & 4 \\
\hline
D & C & 2 \\
\hline
E & B, C & 2 \\
\hline
F & D, E & 3 \\
\hline
G & E & 2 \\
\hline
H & F, G & 1 \\
\hline
\end{tabular}
\end{center}
\begin{enumerate}[label=(\alph*)]
\item Model the project using an activity network.
\item Determine the minimum project completion time.

The start of activity C is delayed by 2 hours.
\item Determine the minimum project completion time with this delay.
\end{enumerate}

\hfill \mbox{\textit{OCR Further Discrete 2023 Q1 [7]}}