OCR Further Discrete 2022 June — Question 2 9 marks

Exam BoardOCR
ModuleFurther Discrete (Further Discrete)
Year2022
SessionJune
Marks9
PaperDownload PDF ↗
Mark schemeDownload PDF ↗
TopicCritical Path Analysis
TypeCalculate early and late times
DifficultyModerate -0.5 This is a standard critical path analysis question requiring routine application of well-defined algorithms (drawing network, forward/backward pass, calculating floats). While it involves multiple steps and careful bookkeeping, it requires no problem-solving insight or novel approaches—just methodical execution of textbook procedures. Slightly easier than average due to the small network size (8 activities) and straightforward precedence relationships.
Spec7.05a Critical path analysis: activity on arc networks7.05b Forward and backward pass: earliest/latest times, critical activities7.05c Total float: calculation and interpretation

2 The table below shows the activities involved in a project together with the immediate predecessors and the duration of each activity.
ActivityImmediate predecessorsDuration (minutes)
A-4
B-1
CA2
DA, B5
ED1
FB, C2
GD, F5
HE, F4
  1. Model the project using an activity network.
  2. Determine the minimum project completion time.
  3. Calculate the total float for each non-critical activity.

Question 2:
AnswerMarks Guidance
2(a) C F
A G
B H
AnswerMarks
D EM1
A1
A1
AnswerMarks
[3]3.1a
1.1
AnswerMarks
1.1Durations and working for parts (b) and (c) may be seen
Single start with activities A, B and single end with activities G, H
(and no others at either end)
Precedences for activities C, D, E, F all correct
All dummies directed and correct with at most 1 extra
AnswerMarks Guidance
2(b) Minimum project completion time = 14 minutes
A1
B1
AnswerMarks
[3]3.4
3.4
AnswerMarks
1.1Forward pass for their network, provided it includes at least one
burst and at least one merge (other than at start and finish)
All forward pass labels correct for a correct network
For reference:
14 cao
AnswerMarks Guidance
2(c) See answer to part (b)
C = 1, F = 1
AnswerMarks
B = 3M1
A1
A1
AnswerMarks
[3]3.4
3.4
AnswerMarks
1.1Their backward pass used to find any one non-zero float
Both cao
cao
If all three are correct but also any other activities are listed with
non-zero floats give M1 A1 A0
Question 2:
2 | (a) | C F
A G
B H
D E | M1
A1
A1
[3] | 3.1a
1.1
1.1 | Durations and working for parts (b) and (c) may be seen
Single start with activities A, B and single end with activities G, H
(and no others at either end)
Precedences for activities C, D, E, F all correct
All dummies directed and correct with at most 1 extra
2 | (b) | Minimum project completion time = 14 minutes | M1
A1
B1
[3] | 3.4
3.4
1.1 | Forward pass for their network, provided it includes at least one
burst and at least one merge (other than at start and finish)
All forward pass labels correct for a correct network
For reference:
14 cao
2 | (c) | See answer to part (b)
C = 1, F = 1
B = 3 | M1
A1
A1
[3] | 3.4
3.4
1.1 | Their backward pass used to find any one non-zero float
Both cao
cao
If all three are correct but also any other activities are listed with
non-zero floats give M1 A1 A0
2 The table below shows the activities involved in a project together with the immediate predecessors and the duration of each activity.

\begin{center}
\begin{tabular}{|l|l|l|}
\hline
Activity & Immediate predecessors & Duration (minutes) \\
\hline
A & - & 4 \\
\hline
B & - & 1 \\
\hline
C & A & 2 \\
\hline
D & A, B & 5 \\
\hline
E & D & 1 \\
\hline
F & B, C & 2 \\
\hline
G & D, F & 5 \\
\hline
H & E, F & 4 \\
\hline
\end{tabular}
\end{center}
\begin{enumerate}[label=(\alph*)]
\item Model the project using an activity network.
\item Determine the minimum project completion time.
\item Calculate the total float for each non-critical activity.
\end{enumerate}

\hfill \mbox{\textit{OCR Further Discrete 2022 Q2 [9]}}