1 Figure 1 opposite shows an activity diagram for a project. The duration required for each activity is given in hours. The project is to be completed in the minimum time.
- Find the earliest start time and the latest finish time for each activity and insert their values on Figure 1.
- Find the critical path.
- Find the float time of activity \(E\).
- Given that activities \(H\) and \(K\) will both overrun by 10 hours, find the new minimum completion time for the project.
\includegraphics[max width=\textwidth, alt={}]{5123be51-168e-4487-8cd3-33aee9e3b23f-02_1515_1709_1192_153}
\begin{figure}[h]
\captionsetup{labelformat=empty}
\caption{Figure 1}
\includegraphics[alt={},max width=\textwidth]{5123be51-168e-4487-8cd3-33aee9e3b23f-03_1656_869_627_611}
\end{figure}