OCR MEI D1 2010 January — Question 1 8 marks

Exam BoardOCR MEI
ModuleD1 (Decision Mathematics 1)
Year2010
SessionJanuary
Marks8
PaperDownload PDF ↗
Mark schemeDownload PDF ↗
TopicCritical Path Analysis
TypeCalculate early and late times
DifficultyEasy -1.2 This is a straightforward application of standard Critical Path Analysis algorithms with only 5 activities and simple precedence relationships. Drawing the network and calculating early/late times using the forward and backward pass are routine procedures taught directly in D1, requiring no problem-solving insight beyond following the algorithm.
Spec7.05a Critical path analysis: activity on arc networks7.05b Forward and backward pass: earliest/latest times, critical activities

1 The table shows the activities involved in a project, their durations and their precedences.
ActivityDuration (mins)Immediate predecessors
A3-
B2-
C3A
D5A, B
E1C
  1. Draw an activity on arc network for these activities.
  2. Mark on your diagram the early time and the late time for each event. Give the critical activities.

1 The table shows the activities involved in a project, their durations and their precedences.

\begin{center}
\begin{tabular}{|l|l|l|}
\hline
Activity & Duration (mins) & Immediate predecessors \\
\hline
A & 3 & - \\
\hline
B & 2 & - \\
\hline
C & 3 & A \\
\hline
D & 5 & A, B \\
\hline
E & 1 & C \\
\hline
\end{tabular}
\end{center}

(i) Draw an activity on arc network for these activities.\\
(ii) Mark on your diagram the early time and the late time for each event. Give the critical activities.

\hfill \mbox{\textit{OCR MEI D1 2010 Q1 [8]}}