AQA Further AS Paper 2 Discrete 2021 June — Question 1 2 marks

Exam BoardAQA
ModuleFurther AS Paper 2 Discrete (Further AS Paper 2 Discrete)
Year2021
SessionJune
Marks2
PaperDownload PDF ↗
Mark schemeDownload PDF ↗
TopicCritical Path Analysis
TypeFind missing early/late times
DifficultyEasy -1.8 This is a basic activity network question requiring only reading values from a diagram and applying the fundamental rule that earliest event times are found by taking the maximum of incoming paths. With only 1 mark per part and multiple choice format, it tests minimal understanding of critical path analysis with no calculation complexity or problem-solving required.
Spec7.05b Forward and backward pass: earliest/latest times, critical activities

  1. A project consists of three activities \(A\), \(B\) and \(C\) An activity network for the project is shown in the diagram below. \includegraphics{figure_1} Find the value of \(x\) Circle your answer. [1 mark] 5 \quad 7 \quad 8 \quad 12
  2. Find the value of \(y\) Circle your answer. [1 mark] 5 \quad 7 \quad 8 \quad 15

Question 1:

AnswerMarks Guidance
1(a)Circles correct answer 1.1b
Total1
QMarking instructions AO

AnswerMarks Guidance
1(b)Circles correct answer 1.1b
Total1
Question total2
QMarking instructions AO
Question 1:
--- 1(a) ---
1(a) | Circles correct answer | 1.1b | B1 | 7
Total | 1
Q | Marking instructions | AO | Marks | Typical solution
--- 1(b) ---
1(b) | Circles correct answer | 1.1b | B1 | 7
Total | 1
Question total | 2
Q | Marking instructions | AO | Marks | Typical solution
\begin{enumerate}[label=(\alph*)]
\item A project consists of three activities $A$, $B$ and $C$

An activity network for the project is shown in the diagram below.

\includegraphics{figure_1}

Find the value of $x$

Circle your answer.
[1 mark]

5 \quad 7 \quad 8 \quad 12

\item Find the value of $y$

Circle your answer.
[1 mark]

5 \quad 7 \quad 8 \quad 15
\end{enumerate}

\hfill \mbox{\textit{AQA Further AS Paper 2 Discrete 2021 Q1 [2]}}