Edexcel D1 2004 January — Question 8 14 marks

Exam BoardEdexcel
ModuleD1 (Decision Mathematics 1)
Year2004
SessionJanuary
Marks14
PaperDownload PDF ↗
Mark schemeDownload PDF ↗
TopicCritical Path Analysis
TypeDraw activity network from table
DifficultyModerate -0.8 This is a standard D1 critical path analysis question testing routine procedures: finding earliest/latest times, identifying critical path, calculating float, and drawing an activity network from a precedence table. All techniques are algorithmic and well-practiced, requiring no problem-solving insight, though part (d) requires careful attention to detail with dummies.
Spec7.05b Forward and backward pass: earliest/latest times, critical activities7.05c Total float: calculation and interpretation

\includegraphics{figure_4} A trainee at a building company is using critical path analysis to help plan a project. Figure 4 shows the trainee's activity network. Each activity is represented by an arc and the number in brackets on each arc is the duration of the activity, in hours.
  1. Find the values of \(x\), \(y\) and \(z\). [3]
  2. State the total length of the project and list the critical activities. [2]
  3. Calculate the total float time on
    1. activity \(N\),
    2. activity \(H\). [3]
The trainee's activity network is checked by the supervisor who finds a number of errors and omissions in the diagram. The project should be represented by the following precedence table.
ActivityMust be preceded by:Duration
\(A\)\(-\)4
\(B\)\(-\)3
\(C\)\(-\)5
\(D\)\(B\)2
\(E\)\(A, D\)8
\(F\)\(B\)2
\(G\)\(C\)2
\(H\)\(C\)3
\(I\)\(F, G\)4
\(J\)\(F, G\)2
\(K\)\(F, G\)7
\(L\)\(E, I\)9
\(M\)\(H, J\)3
\(N\)\(E, I, K, M\)3
\(P\)\(E, I\)6
\(Q\)\(H, J\)5
\(R\)\(Q\)7
  1. By adding activities and dummies amend the diagram in the answer book so that it represents the precedence table. (The durations of activities \(A\), \(B\), ..., \(N\) are all correctly given on the diagram in the answer book.) [4]
  2. Find the total time needed to complete this project. [2]

\includegraphics{figure_4}

A trainee at a building company is using critical path analysis to help plan a project. Figure 4 shows the trainee's activity network. Each activity is represented by an arc and the number in brackets on each arc is the duration of the activity, in hours.

\begin{enumerate}[label=(\alph*)]
\item Find the values of $x$, $y$ and $z$. [3]
\item State the total length of the project and list the critical activities. [2]
\item Calculate the total float time on
\begin{enumerate}[label=(\roman*)]
\item activity $N$,
\item activity $H$. [3]
\end{enumerate}
\end{enumerate}

The trainee's activity network is checked by the supervisor who finds a number of errors and omissions in the diagram. The project should be represented by the following precedence table.

\begin{center}
\begin{tabular}{|c|c|c|}
\hline
Activity & Must be preceded by: & Duration \\
\hline
$A$ & $-$ & 4 \\
\hline
$B$ & $-$ & 3 \\
\hline
$C$ & $-$ & 5 \\
\hline
$D$ & $B$ & 2 \\
\hline
$E$ & $A, D$ & 8 \\
\hline
$F$ & $B$ & 2 \\
\hline
$G$ & $C$ & 2 \\
\hline
$H$ & $C$ & 3 \\
\hline
$I$ & $F, G$ & 4 \\
\hline
$J$ & $F, G$ & 2 \\
\hline
$K$ & $F, G$ & 7 \\
\hline
$L$ & $E, I$ & 9 \\
\hline
$M$ & $H, J$ & 3 \\
\hline
$N$ & $E, I, K, M$ & 3 \\
\hline
$P$ & $E, I$ & 6 \\
\hline
$Q$ & $H, J$ & 5 \\
\hline
$R$ & $Q$ & 7 \\
\hline
\end{tabular}
\end{center}

\begin{enumerate}[label=(\alph*)]
\setcounter{enumi}{3}
\item By adding activities and dummies amend the diagram in the answer book so that it represents the precedence table. (The durations of activities $A$, $B$, ..., $N$ are all correctly given on the diagram in the answer book.) [4]
\item Find the total time needed to complete this project. [2]
\end{enumerate}

\hfill \mbox{\textit{Edexcel D1 2004 Q8 [14]}}