| Exam Board | Edexcel |
|---|---|
| Module | FD1 AS (Further Decision 1 AS) |
| Year | 2020 |
| Session | June |
| Marks | 14 |
| Paper | Download PDF ↗ |
| Mark scheme | Download PDF ↗ |
| Topic | Critical Path Analysis |
| Type | Complete precedence table from network |
| Difficulty | Moderate -0.3 This is a standard Critical Path Analysis question covering routine techniques (precedence table, early/late times, critical path, float calculation, lower bound, cascade chart). While multi-part with 7 sub-questions, each part follows textbook procedures with no novel problem-solving required. The network diagram interpretation and calculations are straightforward for Further Maths students who have studied this topic. |
| Spec | 7.05a Critical path analysis: activity on arc networks7.05b Forward and backward pass: earliest/latest times, critical activities7.05c Total float: calculation and interpretation7.05d Latest start and earliest finish: independent and interfering float |
| Answer | Marks | Guidance |
|---|---|---|
| Answer | Mark | Guidance |
| 5 non-empty rows correct (any 5 of rows D to K) | B1 | 1.1b |
| All 11 rows correct: I preceded by D; J preceded by D, E, F, G, H; K preceded by H | B1 | 1.1b |
| Answer | Marks | Guidance |
|---|---|---|
| Answer | Mark | Guidance |
| All boxes completed, numbers generally increasing L to R and decreasing R to L (condone one "rogue") | M1 | 2.1 |
| All top boxes correct: early times 0, 0, 5, 5, 6, 5, 6, 13, 13, 12, 13 giving final value 22 | A1 | 1.1b |
| All bottom boxes correct | A1 | 1.1b |
| Answer | Marks | Guidance |
|---|---|---|
| Answer | Mark | Guidance |
| Minimum project completion time is 22 hours | B1ft | 1.1b - CAO following through from completed top boxes in (b) |
| Answer | Marks | Guidance |
|---|---|---|
| Answer | Mark | Guidance |
| Critical activities are A, E and J | B1 | 1.1b - CAO (A, E and J only) |
| Answer | Marks | Guidance |
|---|---|---|
| Answer | Mark | Guidance |
| H could be delayed by \(13 - 5 - 7 = 1\) hour | B1ft | 3.4 - Correct calculation for activity H from (b); must see all 3 numbers (so just \(13-12=1\) is B0) |
| Answer | Marks | Guidance |
|---|---|---|
| Answer | Mark | Guidance |
| \(\dfrac{5+3+4+\ldots+8+9+6}{22}\) | M1 | 1.1b - (55 to 73 inclusive) / their duration; answers to (b) and (c)(i) must be consistent |
| \(= 2.909\ldots\) so a lower bound of 3 workers | A1 | 2.2a - Correct deduction; answer of 3 with no working scores no marks |
| Answer | Marks | Guidance |
|---|---|---|
| Answer | Mark | Guidance |
| At least 9 activities including at least 6 floats shown on Gantt chart | M1 | 2.1 |
| All correct critical activities present (A, E, J) and 5 non-critical activities correct | A1 | 1.1b |
| All non-critical activities correct | A1 | 1.1b |
| Answer | Marks | Guidance |
|---|---|---|
| Answer | Mark | Guidance |
| e.g. between times 5 and 13, activities E, D, F, G and H must all be happening. Total time for these five activities is 29 hours and \(29/8 > 3\) so not possible with lower bound of 3 workers. Or: at time 8.5, activities E, D, F and H must be happening so not possible with only 3 workers | B1 | 3.4 - Must refer to both times and activities (as indication they have used (f)) |
## Question 2:
**Part 2(a):**
| Answer | Mark | Guidance |
|--------|------|----------|
| 5 non-empty rows correct (any 5 of rows D to K) | B1 | 1.1b |
| All 11 rows correct: I preceded by D; J preceded by D, E, F, G, H; K preceded by H | B1 | 1.1b |
**Part 2(b):**
| Answer | Mark | Guidance |
|--------|------|----------|
| All boxes completed, numbers generally increasing L to R and decreasing R to L (condone one "rogue") | M1 | 2.1 |
| All top boxes correct: early times 0, 0, 5, 5, 6, 5, 6, 13, 13, 12, 13 giving final value 22 | A1 | 1.1b |
| All bottom boxes correct | A1 | 1.1b |
**Part 2(c)(i):**
| Answer | Mark | Guidance |
|--------|------|----------|
| Minimum project completion time is 22 hours | B1ft | 1.1b - CAO following through from completed top boxes in (b) |
**Part 2(c)(ii):**
| Answer | Mark | Guidance |
|--------|------|----------|
| Critical activities are A, E and J | B1 | 1.1b - CAO (A, E and J only) |
**Part 2(d):**
| Answer | Mark | Guidance |
|--------|------|----------|
| H could be delayed by $13 - 5 - 7 = 1$ hour | B1ft | 3.4 - Correct calculation for activity H from (b); must see all 3 numbers (so just $13-12=1$ is B0) |
**Part 2(e):**
| Answer | Mark | Guidance |
|--------|------|----------|
| $\dfrac{5+3+4+\ldots+8+9+6}{22}$ | M1 | 1.1b - (55 to 73 inclusive) / their duration; answers to (b) and (c)(i) must be consistent |
| $= 2.909\ldots$ so a lower bound of 3 workers | A1 | 2.2a - Correct deduction; answer of 3 with no working scores no marks |
**Part 2(f):**
| Answer | Mark | Guidance |
|--------|------|----------|
| At least 9 activities including at least 6 floats shown on Gantt chart | M1 | 2.1 |
| All correct critical activities present (A, E, J) and 5 non-critical activities correct | A1 | 1.1b |
| All non-critical activities correct | A1 | 1.1b |
**Part 2(g):**
| Answer | Mark | Guidance |
|--------|------|----------|
| e.g. between times 5 and 13, activities E, D, F, G and H must all be happening. Total time for these five activities is 29 hours and $29/8 > 3$ so not possible with lower bound of 3 workers. Or: at time 8.5, activities E, D, F and H must be happening so not possible with only 3 workers | B1 | 3.4 - Must refer to both times and activities (as indication they have used (f)) |
---
2.
\begin{figure}[h]
\begin{center}
\includegraphics[alt={},max width=\textwidth]{a2a6e659-aab5-4eec-9af4-ca6ab895f1c8-03_693_1379_233_342}
\captionsetup{labelformat=empty}
\caption{Figure 1}
\end{center}
\end{figure}
A project is modelled by the activity network shown in Figure 1. The activities are represented by the arcs. The number in brackets on each arc gives the time, in hours, to complete the corresponding activity. Each activity requires one worker. The project is to be completed in the shortest possible time.
\begin{enumerate}[label=(\alph*)]
\item Complete the precedence table in the answer book.
\item Complete Diagram 1 in the answer book to show the early event times and the late event times.
\item \begin{enumerate}[label=(\roman*)]
\item State the minimum project completion time.
\item List the critical activities.
\end{enumerate}\item Calculate the maximum number of hours by which activity H could be delayed without affecting the shortest possible completion time of the project. You must make the numbers used in your calculation clear.
\item Calculate a lower bound for the number of workers needed to complete the project in the minimum time. You must show your working.
\item Draw a cascade chart for this project on Grid 1 in the answer book.
\item Using the answer to (f), explain why it is not possible to complete the project in the shortest possible time using the number of workers found in (e).
\end{enumerate}
\hfill \mbox{\textit{Edexcel FD1 AS 2020 Q2 [14]}}