AQA Further AS Paper 2 Discrete 2020 June — Question 5 4 marks

Exam BoardAQA
ModuleFurther AS Paper 2 Discrete (Further AS Paper 2 Discrete)
Year2020
SessionJune
Marks4
TopicCritical Path Analysis

5 A restoration project is divided into a number of activities. The duration and predecessor(s) of each activity are shown in the table below.
ActivityImmediate predecessor(s)Duration (weeks)
\(A\)-10
B-5
CB12
D\(A\)8
\(E\)C, D4
\(F\)C, D3
\(G\)C, D7
\(H\)E, F8
\(I\)G6
\(J\)G15
KH, I5
\(L\)K4
5
  1. On the opposite page, construct an activity network for the project and fill in the earliest start time and latest finish time for each activity.
    [0pt] [4 marks] \begin{figure}[h]
    \includegraphics[alt={},max width=\textwidth]{21ed3b4e-a089-4607-b5d6-69d8aac03f31-09_533_289_2124_1548} \captionsetup{labelformat=empty} \caption{Turn over -}
    \end{figure} 5
  2. Due to a change of materials during the project, the duration of activity \(C\) is extended by 3 weeks. Determine the new minimum completion time of the project.
    \includegraphics[max width=\textwidth, alt={}, center]{21ed3b4e-a089-4607-b5d6-69d8aac03f31-11_2488_1716_219_153}