OCR D2 — Question 3 10 marks

Exam BoardOCR
ModuleD2 (Decision Mathematics 2)
Marks10
PaperDownload PDF ↗
Mark schemeDownload PDF ↗
TopicCritical Path Analysis
TypeFind range for variable duration
DifficultyStandard +0.3 This is a standard Critical Path Analysis question requiring network drawing, critical path identification, and float calculation. Part (c) asks for total float of activity F, which is a routine application of CPA techniques taught in D2. The network is straightforward with no complex dependencies or tricky logic.
Spec7.05a Critical path analysis: activity on arc networks7.05b Forward and backward pass: earliest/latest times, critical activities7.05c Total float: calculation and interpretation7.05d Latest start and earliest finish: independent and interfering float

3. A project consists of 11 activities, some of which are dependent on others having been completed. The following precedence table summarises the relevant information.
ActivityDepends onDuration (hours)
A-5
BA4
CA2
DB, C11
EC4
\(F\)D3
GD8
\(H\)D, E2
I\(F\)1
J\(F , G , H\)7
\(K\)\(I , J\)2
  1. Draw an activity network for the project.
  2. Find the critical path and the minimum time in which the project can be completed. Activity \(F\) can be carried out more cheaply if it is allocated more time.
  3. Find the maximum time that can be allocated to activity \(F\) without increasing the minimum time in which the project can be completed.

Question 3:
Part (a)
AnswerMarks Guidance
Completed activity network with all values (forward and backward scan)M2 A2 Must show all early/late event times correctly
Part (b)
AnswerMarks
Lower figures give forward scanM1
Upper figures give backward scanM1 A1
Critical path is \(ABDGJK\)A1
Minimum time is 37 hoursA1
Part (c)
AnswerMarks Guidance
\(28 - 20 = 8\) hoursB1 (10 marks total)
# Question 3:

## Part (a)
| Completed activity network with all values (forward and backward scan) | M2 A2 | Must show all early/late event times correctly |

## Part (b)
| Lower figures give forward scan | M1 | |
| Upper figures give backward scan | M1 A1 | |
| Critical path is $ABDGJK$ | A1 | |
| Minimum time is 37 hours | A1 | |

## Part (c)
| $28 - 20 = 8$ hours | B1 | **(10 marks total)** |

---
3. A project consists of 11 activities, some of which are dependent on others having been completed. The following precedence table summarises the relevant information.

\begin{center}
\begin{tabular}{|l|l|l|}
\hline
Activity & Depends on & Duration (hours) \\
\hline
A & - & 5 \\
\hline
B & A & 4 \\
\hline
C & A & 2 \\
\hline
D & B, C & 11 \\
\hline
E & C & 4 \\
\hline
$F$ & D & 3 \\
\hline
G & D & 8 \\
\hline
$H$ & D, E & 2 \\
\hline
I & $F$ & 1 \\
\hline
J & $F , G , H$ & 7 \\
\hline
$K$ & $I , J$ & 2 \\
\hline
\end{tabular}
\end{center}
\begin{enumerate}[label=(\alph*)]
\item Draw an activity network for the project.
\item Find the critical path and the minimum time in which the project can be completed.

Activity $F$ can be carried out more cheaply if it is allocated more time.
\item Find the maximum time that can be allocated to activity $F$ without increasing the minimum time in which the project can be completed.
\end{enumerate}

\hfill \mbox{\textit{OCR D2  Q3 [10]}}