OCR D2 2006 June — Question 4 14 marks

Exam BoardOCR
ModuleD2 (Decision Mathematics 2)
Year2006
SessionJune
Marks14
PaperDownload PDF ↗
Mark schemeDownload PDF ↗
TopicCritical Path Analysis
TypeCalculate early and late times
DifficultyModerate -0.5 This is a standard Critical Path Analysis question requiring calculation of early/late times and identification of critical activities. While it involves multiple steps (forward pass, backward pass, finding critical path), these are routine algorithmic procedures taught directly in D2 with no novel problem-solving required. The question is slightly easier than average A-level standard due to its purely procedural nature.
Spec7.05a Critical path analysis: activity on arc networks7.05b Forward and backward pass: earliest/latest times, critical activities7.05c Total float: calculation and interpretation7.05d Latest start and earliest finish: independent and interfering float

4 Answer this question on the insert provided. The diagram shows an activity network for a project. The table lists the durations of the activities (in hours). \includegraphics[max width=\textwidth, alt={}, center]{e879b1f5-edc7-4819-80be-2a90dbf3d451-05_680_1125_424_244} (ii) Key: \begin{figure}[h]
\includegraphics[alt={},max width=\textwidth]{e879b1f5-edc7-4819-80be-2a90dbf3d451-10_154_225_1119_1509} \captionsetup{labelformat=empty} \caption{Early event Late event time time}
\end{figure}
\includegraphics[max width=\textwidth, alt={}]{e879b1f5-edc7-4819-80be-2a90dbf3d451-10_762_1371_1409_427}
Minimum completion time = \(\_\_\_\_\) hours Critical activities: \(\_\_\_\_\) (iii) \(\_\_\_\_\) (iv) \includegraphics[max width=\textwidth, alt={}, center]{e879b1f5-edc7-4819-80be-2a90dbf3d451-11_513_1189_543_520} Number of workers required = \(\_\_\_\_\)
(i)\(A \bullet\)
\(B \bullet\)\(\bullet J\)
\(C \bullet\)\(\bullet K\)
\(D \bullet\)\(\bullet L\)
\(E \bullet\)\(\bullet M\)
\(F \bullet\)\(\bullet N\)
(ii) \(\_\_\_\_\) (iii)
\(J\)\(K\)\(L\)\(M\)\(N\)\(O\)
\(A\)252252
\(B\)252055
\(C\)505522
\(D\)
\(E\)
\(F\)
Answer part (iv) in your answer booklet.

(i)
AnswerMarks Guidance
ActivityDuration Immediate predecessors
A6 -
B4 -
C5 A
D1 A, B
E5 A, D
F4 D
G2 C, E, F
ANSWERED ON INSERT
AnswerMarks
B1For predecessors for activities \(A, B\) and \(C\) correct
B1For predecessors for activities \(D, F\) and \(G\) correct
B1, [3]For predecessors for activity \(E\) correct
(ii) Network diagram with:
AnswerMarks
- Node at start (0, 0) with 1212
- Node after A with times 66 and label C
- Nodes connected with various times including 77
- Final node with 1414
- Activity G marked
AnswerMarks
M1For carrying out forward pass (no more than one independent error)
A1For all early event times correct
M1For carrying out backwards pass (no more than one independent error)
A1For all late event times correct
Minimum completion time = 14 hours
AnswerMarks Guidance
Critical activities: A, D, E, GB1, B1, [6] For 14 (cao); For A, D, E, G only (cao); For stating that time increases by 2, or equivalent (cao)
(iii) Increased by 2 (hours)
AnswerMarks Guidance
Becomes 16 (hours)B1, [1] For stating that time increases by 2, or equivalent
B1For a resource histogram with no overhanging cells
(iv) Resource histogram shown with workers on y-axis (0-4) and hours on x-axis (0-14)
AnswerMarks Guidance
Number of workers required = 3M1, A1 For a reasonable attempt, fit their start times if possible; For a completely correct histogram (cao)
B1, [4]For 3 or follow through their histogram if possible
(i) 

| Activity | Duration | Immediate predecessors |
|----------|----------|------------------------|
| A | 6 | - |
| B | 4 | - |
| C | 5 | A |
| D | 1 | A, B |
| E | 5 | A, D |
| F | 4 | D |
| G | 2 | C, E, F |

**ANSWERED ON INSERT**

| B1 | For predecessors for activities $A, B$ and $C$ correct
| B1 | For predecessors for activities $D, F$ and $G$ correct
| B1, [3] | For predecessors for activity $E$ correct

(ii) **Network diagram with:**
- Node at start (0, 0) with 12|12
- Node after A with times 6|6 and label C
- Nodes connected with various times including 7|7
- Final node with 14|14
- Activity G marked

| M1 | For carrying out forward pass (no more than one independent error)
| A1 | For all early event times correct
| M1 | For carrying out backwards pass (no more than one independent error)
| A1 | For all late event times correct

Minimum completion time = 14 hours
Critical activities: A, D, E, G | B1, B1, [6] | For 14 (cao); For A, D, E, G only (cao); For stating that time increases by 2, or equivalent (cao)

(iii) Increased by 2 (hours)
Becomes 16 (hours) | B1, [1] | For stating that time increases by 2, or equivalent
| B1 | For a resource histogram with no overhanging cells

(iv) **Resource histogram shown with workers on y-axis (0-4) and hours on x-axis (0-14)**
Number of workers required = 3 | M1, A1 | For a reasonable attempt, fit their start times if possible; For a completely correct histogram (cao)
| B1, [4] | For 3 or follow through their histogram if possible

---
4 Answer this question on the insert provided.
The diagram shows an activity network for a project. The table lists the durations of the activities (in hours).\\
\includegraphics[max width=\textwidth, alt={}, center]{e879b1f5-edc7-4819-80be-2a90dbf3d451-05_680_1125_424_244}

(ii)

Key:

\begin{figure}[h]
\begin{center}
  \includegraphics[alt={},max width=\textwidth]{e879b1f5-edc7-4819-80be-2a90dbf3d451-10_154_225_1119_1509}
\captionsetup{labelformat=empty}
\caption{Early event Late event time time}
\end{center}
\end{figure}

\begin{center}
\includegraphics[max width=\textwidth, alt={}]{e879b1f5-edc7-4819-80be-2a90dbf3d451-10_762_1371_1409_427}
\end{center}

Minimum completion time = $\_\_\_\_$ hours

Critical activities: $\_\_\_\_$\\
(iii) $\_\_\_\_$\\

(iv)\\
\includegraphics[max width=\textwidth, alt={}, center]{e879b1f5-edc7-4819-80be-2a90dbf3d451-11_513_1189_543_520}

Number of workers required = $\_\_\_\_$

\begin{center}
\begin{tabular}{ l l }
(i) & $A \bullet$ \\
$B \bullet$ & $\bullet J$ \\
$C \bullet$ & $\bullet K$ \\
$D \bullet$ & $\bullet L$ \\
$E \bullet$ & $\bullet M$ \\
$F \bullet$ & $\bullet N$ \\
\end{tabular}
\end{center}

(ii) $\_\_\_\_$\\

(iii)

\begin{center}
\begin{tabular}{ c | c c c c c c }
 & $J$ & $K$ & $L$ & $M$ & $N$ & $O$ \\
\hline
$A$ & 2 & 5 & 2 & 2 & 5 & 2 \\
$B$ & 2 & 5 & 2 & 0 & 5 & 5 \\
$C$ & 5 & 0 & 5 & 5 & 2 & 2 \\
$D$ &  &  &  &  &  &  \\
$E$ &  &  &  &  &  &  \\
$F$ &  &  &  &  &  &  \\
\end{tabular}
\end{center}

Answer part (iv) in your answer booklet.

\hfill \mbox{\textit{OCR D2 2006 Q4 [14]}}