Edexcel FD1 2022 June — Question 5 14 marks

Exam BoardEdexcel
ModuleFD1 (Further Decision 1)
Year2022
SessionJune
Marks14
PaperDownload PDF ↗
Mark schemeDownload PDF ↗
TopicCritical Path Analysis
TypeFind missing early/late times
DifficultyModerate -0.5 This is a standard Critical Path Analysis question covering routine techniques (precedence tables, late times, critical activities, float, resource histograms, Gantt charts). While multi-part with several marks, each component requires straightforward application of well-defined algorithms taught in FD1 with no novel problem-solving or insight needed. The constraint on x adds minor complexity but remains procedural.
Spec7.05a Critical path analysis: activity on arc networks7.05b Forward and backward pass: earliest/latest times, critical activities7.05c Total float: calculation and interpretation

5. \begin{figure}[h]
\includegraphics[alt={},max width=\textwidth]{27586973-89f4-45e1-9cc4-04c4044cd3db-08_1099_1700_194_139} \captionsetup{labelformat=empty} \caption{Figure 2}
\end{figure} The network in Figure 2 shows the activities that need to be completed for a project. Each activity is represented by an arc and the duration of the activity, in days, is shown in brackets. The early event times are shown in Figure 2.
  1. Complete Table 1 in the answer book to show the immediately preceding activities for each activity. It is given that \(4 < x \leqslant m\)
  2. State the largest possible integer value of \(m\).
    1. Complete Diagram 1 in the answer book to show the late event times.
    2. State the activities that must be critical.
  3. Calculate the total float for activity G. The resource histogram in Figure 3 shows the number of workers required when each activity starts at its earliest possible time. The histogram also shows which activities happen at each time. \begin{figure}[h]
    \includegraphics[alt={},max width=\textwidth]{27586973-89f4-45e1-9cc4-04c4044cd3db-09_682_1612_356_230} \captionsetup{labelformat=empty} \caption{Figure 3}
    \end{figure}
  4. Complete Table 2 in the answer book to show the number of workers required for each activity of the project.
  5. Draw a Gantt chart on Grid 1 in the answer book to represent the activity network.

Question 5:
Part (a)
AnswerMarks Guidance
AnswerMarks Guidance
Four correct rows (F, G, H, J, K with correct IPAs): F→C, G→A,B,E, H→A,B,E, J→D,G, K→D,F,G,HB1 Four correct rows not including A, B, C
All rows correct (A, B, C have no IPA / dash)B1 Any letters in A, B, C rows scores B0
Part (b)
AnswerMarks Guidance
AnswerMarks Guidance
\(m = 9\)B1 cao; allow \(4 < x\), 9 or \(x\), 9 but not \(x=9\) or \(m\), 9 unless stating correct value
Part (c)(i)
AnswerMarks Guidance
AnswerMarks Guidance
Any four of the bottom boxes completed correctlyM1
All bottom boxes correct; \(15-x\) must be seenA1 cao; condone correct expression replaced by value of \(15-x\) ONLY if \(x\) explicitly stated
Part (c)(ii)
AnswerMarks Guidance
AnswerMarks Guidance
C, E, H and K must be criticalB1 cao (C, E, H and K only)
Part (d)
AnswerMarks Guidance
AnswerMarks Guidance
Total float for activity G is \(15 - 11 - 3 = 1\)B1 cao; correct answer with no working (or no incorrect working) can imply this mark
Part (e)
AnswerMarks Guidance
AnswerMarks Guidance
Any six values correct from the workers tableB1
All values correctB1 cao
Part (f)
AnswerMarks Guidance
AnswerMarks Guidance
\(x = 6\)B1 cao; seen or implied by durations of D and F both correct
Cascade chart with at least 8 activities labelled, at least four with non-zero floatM1 A scheduling diagram (no floats evident) scores M0
Critical activities (C, E, H, K) correctA1
Activities B, G and J correctA1
Activities A, D and F correctA1
# Question 5:

## Part (a)
| Answer | Marks | Guidance |
|--------|-------|----------|
| Four correct rows (F, G, H, J, K with correct IPAs): F→C, G→A,B,E, H→A,B,E, J→D,G, K→D,F,G,H | B1 | Four correct rows not including A, B, C |
| All rows correct (A, B, C have no IPA / dash) | B1 | Any letters in A, B, C rows scores B0 |

## Part (b)
| Answer | Marks | Guidance |
|--------|-------|----------|
| $m = 9$ | B1 | cao; allow $4 < x$, 9 or $x$, 9 but not $x=9$ or $m$, 9 unless stating correct value |

## Part (c)(i)
| Answer | Marks | Guidance |
|--------|-------|----------|
| Any four of the bottom boxes completed correctly | M1 | |
| All bottom boxes correct; $15-x$ must be seen | A1 | cao; condone correct expression replaced by value of $15-x$ ONLY if $x$ explicitly stated |

## Part (c)(ii)
| Answer | Marks | Guidance |
|--------|-------|----------|
| C, E, H and K must be critical | B1 | cao (C, E, H and K only) |

## Part (d)
| Answer | Marks | Guidance |
|--------|-------|----------|
| Total float for activity G is $15 - 11 - 3 = 1$ | B1 | cao; correct answer with no working (or no incorrect working) can imply this mark |

## Part (e)
| Answer | Marks | Guidance |
|--------|-------|----------|
| Any six values correct from the workers table | B1 | |
| All values correct | B1 | cao |

## Part (f)
| Answer | Marks | Guidance |
|--------|-------|----------|
| $x = 6$ | B1 | cao; seen or implied by durations of D and F both correct |
| Cascade chart with at least 8 activities labelled, at least four with non-zero float | M1 | A scheduling diagram (no floats evident) scores M0 |
| Critical activities (C, E, H, K) correct | A1 | |
| Activities B, G and J correct | A1 | |
| Activities A, D and F correct | A1 | |

---
5.

\begin{figure}[h]
\begin{center}
  \includegraphics[alt={},max width=\textwidth]{27586973-89f4-45e1-9cc4-04c4044cd3db-08_1099_1700_194_139}
\captionsetup{labelformat=empty}
\caption{Figure 2}
\end{center}
\end{figure}

The network in Figure 2 shows the activities that need to be completed for a project. Each activity is represented by an arc and the duration of the activity, in days, is shown in brackets. The early event times are shown in Figure 2.
\begin{enumerate}[label=(\alph*)]
\item Complete Table 1 in the answer book to show the immediately preceding activities for each activity.

It is given that $4 < x \leqslant m$
\item State the largest possible integer value of $m$.
\item \begin{enumerate}[label=(\roman*)]
\item Complete Diagram 1 in the answer book to show the late event times.
\item State the activities that must be critical.
\end{enumerate}\item Calculate the total float for activity G.

The resource histogram in Figure 3 shows the number of workers required when each activity starts at its earliest possible time. The histogram also shows which activities happen at each time.

\begin{figure}[h]
\begin{center}
  \includegraphics[alt={},max width=\textwidth]{27586973-89f4-45e1-9cc4-04c4044cd3db-09_682_1612_356_230}
\captionsetup{labelformat=empty}
\caption{Figure 3}
\end{center}
\end{figure}
\item Complete Table 2 in the answer book to show the number of workers required for each activity of the project.
\item Draw a Gantt chart on Grid 1 in the answer book to represent the activity network.
\end{enumerate}

\hfill \mbox{\textit{Edexcel FD1 2022 Q5 [14]}}