5.
\begin{figure}[h]
\includegraphics[alt={},max width=\textwidth]{27586973-89f4-45e1-9cc4-04c4044cd3db-08_1099_1700_194_139}
\captionsetup{labelformat=empty}
\caption{Figure 2}
\end{figure}
The network in Figure 2 shows the activities that need to be completed for a project. Each activity is represented by an arc and the duration of the activity, in days, is shown in brackets. The early event times are shown in Figure 2.
- Complete Table 1 in the answer book to show the immediately preceding activities for each activity.
It is given that \(4 < x \leqslant m\)
- State the largest possible integer value of \(m\).
- Complete Diagram 1 in the answer book to show the late event times.
- State the activities that must be critical.
- Calculate the total float for activity G.
The resource histogram in Figure 3 shows the number of workers required when each activity starts at its earliest possible time. The histogram also shows which activities happen at each time.
\begin{figure}[h]
\includegraphics[alt={},max width=\textwidth]{27586973-89f4-45e1-9cc4-04c4044cd3db-09_682_1612_356_230}
\captionsetup{labelformat=empty}
\caption{Figure 3}
\end{figure} - Complete Table 2 in the answer book to show the number of workers required for each activity of the project.
- Draw a Gantt chart on Grid 1 in the answer book to represent the activity network.