Edexcel FD1 AS Specimen — Question 3 7 marks

Exam BoardEdexcel
ModuleFD1 AS (Further Decision 1 AS)
SessionSpecimen
Marks7
PaperDownload PDF ↗
Mark schemeDownload PDF ↗
TopicCritical Path Analysis
TypeCalculate early and late times
DifficultyModerate -0.3 This is a standard Critical Path Analysis question requiring construction of an activity network and calculation of early/late times. While it involves multiple steps and careful bookkeeping, it follows a completely algorithmic procedure taught directly in the syllabus with no problem-solving insight required. The presence of dummy activities adds minor complexity, but this is routine for CPA questions.
Spec7.05a Critical path analysis: activity on arc networks7.05b Forward and backward pass: earliest/latest times, critical activities7.05c Total float: calculation and interpretation

3.
ActivityTime taken (days)Immediately preceding activities
A5-
B7-
C3-
D4A, B
E4D
F2B
G4B
H5C, G
I10C, G
The table above shows the activities required for the completion of a building project. For each activity, the table shows the time taken in days to complete the activity and the immediately preceding activities. Each activity requires one worker. The project is to be completed in the shortest possible time.
  1. Draw the activity network described in the table, using activity on arc. Your activity network must contain the minimum number of dummies only.
    1. Show that the project can be completed in 21 days, showing your working.
    2. Identify the critical activities.

Question 3(a)(b):
AnswerMarks Guidance
Answer/WorkingMark Guidance
Network diagram: at least 5 activities and one dummy, one startM1
A, B, C, D, F, G and first dummy correctA1
E, H, I correct, second dummy correct and one finishA1
All boxes completed, numbers generally increasing L to R (condone one "rogue")M1
All values caoA1
Deduction that result in diagram indicates project can be completed in 21 daysA1ft All boxes completed, numbers generally increasing in direction of arrows for top boxes and generally decreasing in opposite direction for bottom boxes
Critical activities: B, G, IA1 Critical activities correct
## Question 3(a)(b):

| Answer/Working | Mark | Guidance |
|---|---|---|
| Network diagram: at least 5 activities and one dummy, one start | M1 | |
| A, B, C, D, F, G and first dummy correct | A1 | |
| E, H, I correct, second dummy correct and one finish | A1 | |
| All boxes completed, numbers generally increasing L to R (condone one "rogue") | M1 | |
| All values cao | A1 | |
| Deduction that result in diagram indicates project can be completed in 21 days | A1ft | All boxes completed, numbers generally increasing in direction of arrows for top boxes and generally decreasing in opposite direction for bottom boxes |
| Critical activities: B, G, I | A1 | Critical activities correct |

---
3.

\begin{center}
\begin{tabular}{|l|l|l|}
\hline
Activity & Time taken (days) & Immediately preceding activities \\
\hline
A & 5 & - \\
\hline
B & 7 & - \\
\hline
C & 3 & - \\
\hline
D & 4 & A, B \\
\hline
E & 4 & D \\
\hline
F & 2 & B \\
\hline
G & 4 & B \\
\hline
H & 5 & C, G \\
\hline
I & 10 & C, G \\
\hline
\end{tabular}
\end{center}

The table above shows the activities required for the completion of a building project. For each activity, the table shows the time taken in days to complete the activity and the immediately preceding activities. Each activity requires one worker. The project is to be completed in the shortest possible time.
\begin{enumerate}[label=(\alph*)]
\item Draw the activity network described in the table, using activity on arc. Your activity network must contain the minimum number of dummies only.
\item \begin{enumerate}[label=(\roman*)]
\item Show that the project can be completed in 21 days, showing your working.
\item Identify the critical activities.
\end{enumerate}\end{enumerate}

\hfill \mbox{\textit{Edexcel FD1 AS  Q3 [7]}}