Edexcel D1 2015 June — Question 7 13 marks

Exam BoardEdexcel
ModuleD1 (Decision Mathematics 1)
Year2015
SessionJune
Marks13
PaperDownload PDF ↗
Mark schemeDownload PDF ↗
TopicCritical Path Analysis
TypeDraw activity network from table
DifficultyModerate -0.8 This is a standard D1 critical path analysis question requiring routine application of well-practiced algorithms: drawing an activity network from a precedence table, finding early/late times, calculating lower bound for workers, and scheduling. While multi-part with 13 marks, each component follows textbook procedures with no novel problem-solving required, making it easier than average A-level maths questions.
Spec7.05a Critical path analysis: activity on arc networks7.05b Forward and backward pass: earliest/latest times, critical activities7.05c Total float: calculation and interpretation7.05e Cascade charts: scheduling and effect of delays

7.
ActivityTime taken (days)Immediately preceding activities
A5-
B7-
C8-
D5A
E7A
F10B, C
G4B, C
H9C
I8G, H
J12G, H
K7D
L10E, F, I, J
The table shows the activities required for the completion of a building project. For each activity the table shows the time taken, in days, and the immediately preceding activities. Each activity requires one worker. The project is to be completed in the shortest possible time. \begin{figure}[h]
\includegraphics[alt={},max width=\textwidth]{ba22b22e-c0d5-438d-821b-88619eacdb5d-8_768_1162_1238_431} \captionsetup{labelformat=empty} \caption{Figure 6}
\end{figure} Figure 6 shows a partially completed activity network used to model the project. The activities are represented by the arcs and the numbers in brackets on the arcs are the times taken, in days, to complete each activity.
  1. Add activities, E, F and I, and exactly one dummy to Diagram 1 in the answer book.
  2. Complete Diagram 1 in the answer book to show the early event times and late event times.
  3. Calculate a lower bound for the number of workers needed to complete the project in the shortest possible time. You must show your working.
    (2)
  4. Schedule the activities, using the minimum number of workers, so that the project is completed in the minimum time.
    (Total 13 marks)

7.

\begin{center}
\begin{tabular}{|l|l|l|}
\hline
Activity & Time taken (days) & Immediately preceding activities \\
\hline
A & 5 & - \\
\hline
B & 7 & - \\
\hline
C & 8 & - \\
\hline
D & 5 & A \\
\hline
E & 7 & A \\
\hline
F & 10 & B, C \\
\hline
G & 4 & B, C \\
\hline
H & 9 & C \\
\hline
I & 8 & G, H \\
\hline
J & 12 & G, H \\
\hline
K & 7 & D \\
\hline
L & 10 & E, F, I, J \\
\hline
\end{tabular}
\end{center}

The table shows the activities required for the completion of a building project. For each activity the table shows the time taken, in days, and the immediately preceding activities. Each activity requires one worker. The project is to be completed in the shortest possible time.

\begin{figure}[h]
\begin{center}
  \includegraphics[alt={},max width=\textwidth]{ba22b22e-c0d5-438d-821b-88619eacdb5d-8_768_1162_1238_431}
\captionsetup{labelformat=empty}
\caption{Figure 6}
\end{center}
\end{figure}

Figure 6 shows a partially completed activity network used to model the project. The activities are represented by the arcs and the numbers in brackets on the arcs are the times taken, in days, to complete each activity.
\begin{enumerate}[label=(\alph*)]
\item Add activities, E, F and I, and exactly one dummy to Diagram 1 in the answer book.
\item Complete Diagram 1 in the answer book to show the early event times and late event times.
\item Calculate a lower bound for the number of workers needed to complete the project in the shortest possible time. You must show your working.\\
(2)
\item Schedule the activities, using the minimum number of workers, so that the project is completed in the minimum time.\\
(Total 13 marks)
\end{enumerate}

\hfill \mbox{\textit{Edexcel D1 2015 Q7 [13]}}