Edexcel D1 2002 June — Question 6 12 marks

Exam BoardEdexcel
ModuleD1 (Decision Mathematics 1)
Year2002
SessionJune
Marks12
PaperDownload PDF ↗
Mark schemeDownload PDF ↗
TopicCritical Path Analysis
TypeSchedule with limited workers - create schedule/chart
DifficultyStandard +0.3 This is a standard D1 critical path analysis question requiring identification of critical activities, calculation of floats, drawing a Gantt chart, and determining minimum workers. All techniques are routine textbook exercises with no novel problem-solving required, making it slightly easier than average for A-level.
Spec7.05b Forward and backward pass: earliest/latest times, critical activities7.05c Total float: calculation and interpretation7.05d Latest start and earliest finish: independent and interfering float

6. \begin{figure}[h]
\captionsetup{labelformat=empty} \caption{Figure 4} \includegraphics[alt={},max width=\textwidth]{652477eb-87dc-4a5a-8514-c9be39986142-6_1083_1608_421_259}
\end{figure} A building project is modelled by the activity network shown in Fig. 4. The activities are represented by the arcs. The number in brackets on each arc gives the time, in hours, taken to complete the activity. The left box entry at each vertex is the earliest event time and the right box entry is the latest event time.
  1. Determine the critical activities and state the length of the critical path.
  2. State the total float for each non-critical activity.
  3. On the grid in the answer booklet, draw a cascade (Gantt) chart for the project. Given that each activity requires one worker,
  4. draw up a schedule to determine the minimum number of workers required to complete the project in the critical time. State the minimum number of workers.
    (3)

Question 6:
Part (a)
AnswerMarks Guidance
AnswerMarks Guidance
Critical activities \(B, F, J, K, N\) (not \(I\)); length 25 hoursB1; B1 (2)
Part (b)
AnswerMarks Guidance
AnswerMarks Guidance
\(A = 5-0-3=2\)M1 A1 ft
\(C = 9-0-6=3\)
\(D = 11-3-3=5\)A1
\(E = 9-3-4=2\)
\(G = 9-4-3=2\)
\(H = 16-7-7=2\)
\(I = 16-9-5=2\)
\(L = 22-11-4=7\)
\(M = 22-16-2=4\)
\(P = 25-18-3=4\) (3)
Part (c)
AnswerMarks Guidance
AnswerMarks Guidance
Correct Gantt chart with critical activities \(B, F, J, K, N\) shown on top rowM1 A1
Non-critical activities with float shown correctlyA1 ft
All activities correctly positionedA1 ft (implied)
Part (d)
AnswerMarks Guidance
AnswerMarks Guidance
Correct resource levelling diagram showing schedulingM1
Activities correctly allocated to workersA1
3 workers neededA1 (3)
(12 marks)
# Question 6:

## Part (a)
| Answer | Marks | Guidance |
|--------|-------|----------|
| Critical activities $B, F, J, K, N$ (not $I$); length 25 hours | B1; B1 | **(2)** |

## Part (b)
| Answer | Marks | Guidance |
|--------|-------|----------|
| $A = 5-0-3=2$ | M1 A1 ft | |
| $C = 9-0-6=3$ | | |
| $D = 11-3-3=5$ | A1 | |
| $E = 9-3-4=2$ | | |
| $G = 9-4-3=2$ | | |
| $H = 16-7-7=2$ | | |
| $I = 16-9-5=2$ | | |
| $L = 22-11-4=7$ | | |
| $M = 22-16-2=4$ | | |
| $P = 25-18-3=4$ | | **(3)** |

## Part (c)
| Answer | Marks | Guidance |
|--------|-------|----------|
| Correct Gantt chart with critical activities $B, F, J, K, N$ shown on top row | M1 A1 | |
| Non-critical activities with float shown correctly | A1 ft | |
| All activities correctly positioned | A1 ft | **(implied)** |

## Part (d)
| Answer | Marks | Guidance |
|--------|-------|----------|
| Correct resource levelling diagram showing scheduling | M1 | |
| Activities correctly allocated to workers | A1 | |
| 3 workers needed | A1 | **(3)** |
| | **(12 marks)** | |

---
6.

\begin{figure}[h]
\begin{center}
\captionsetup{labelformat=empty}
\caption{Figure 4}
  \includegraphics[alt={},max width=\textwidth]{652477eb-87dc-4a5a-8514-c9be39986142-6_1083_1608_421_259}
\end{center}
\end{figure}

A building project is modelled by the activity network shown in Fig. 4. The activities are represented by the arcs. The number in brackets on each arc gives the time, in hours, taken to complete the activity. The left box entry at each vertex is the earliest event time and the right box entry is the latest event time.
\begin{enumerate}[label=(\alph*)]
\item Determine the critical activities and state the length of the critical path.
\item State the total float for each non-critical activity.
\item On the grid in the answer booklet, draw a cascade (Gantt) chart for the project.

Given that each activity requires one worker,
\item draw up a schedule to determine the minimum number of workers required to complete the project in the critical time. State the minimum number of workers.\\
(3)
\end{enumerate}

\hfill \mbox{\textit{Edexcel D1 2002 Q6 [12]}}