Edexcel D1 2012 January — Question 7 16 marks

Exam BoardEdexcel
ModuleD1 (Decision Mathematics 1)
Year2012
SessionJanuary
Marks16
PaperDownload PDF ↗
Mark schemeDownload PDF ↗
TopicCritical Path Analysis
TypeExplain dummy activities
DifficultyModerate -0.8 This is a standard D1 critical path analysis question testing routine procedures: explaining dummy activities (textbook definitions), calculating early/late times (algorithmic), finding float (formula application), and drawing a Gantt chart. All parts are procedural recall with no problem-solving or novel insight required, making it easier than average.
Spec7.05a Critical path analysis: activity on arc networks7.05b Forward and backward pass: earliest/latest times, critical activities7.05c Total float: calculation and interpretation7.05d Latest start and earliest finish: independent and interfering float7.05e Cascade charts: scheduling and effect of delays

7. \begin{figure}[h]
\includegraphics[alt={},max width=\textwidth]{e02c4a9a-d2ab-489f-b838-9b4d902c4457-9_1042_1426_267_315} \captionsetup{labelformat=empty} \caption{Figure 7}
\end{figure} A project is modelled by the activity network shown in Figure 7. The activities are represented by the arcs. The number in brackets on each arc gives the time required, in hours, to complete the activity. The numbers in circles are the event numbers. Each activity requires one worker.
  1. Explain the significance of the dummy activity
    1. from event 4 to event 6 ,
    2. from event 5 to event 7
      (3)
  2. Calculate the early time and the late time for each event. Write these in the boxes in the answer book.
  3. Calculate the total float on each of activities D and G. You must make the numbers you use in your calculations clear.
  4. Calculate a lower bound for the minimum number of workers required to complete the project in the minimum time.
  5. On the grid in your answer book, draw a cascade (Gantt) chart for this project.

Question 7:
Part (a)(i)
AnswerMarks Guidance
AnswerMarks Guidance
I depends on B, E and F only; K depends on B, E, F and DB1 DB1 K, I, D and at least one of B, E, F referred to. Correct but maybe incomplete: bod
Part (a)(ii)
AnswerMarks Guidance
AnswerMarks Guidance
So that G and H will not share the same start and end events; so that G and H can be uniquely described in terms of their end eventsB1 Clear correct statement. No bod. Must refer to either events or activities. 'unique' alone not enough. 3 marks total
Part (b)
AnswerMarks Guidance
AnswerMarks Guidance
All top boxes complete, values generally increasing left to rightM1 A1 Condone one rogue. CAO
All bottom boxes complete, values generally decreasing R to LM1 A1 Condone one rogue. CAO. 4 marks total
Part (c)
AnswerMarks Guidance
AnswerMarks Guidance
Correct calculation of floats, all three numbers correct (ft)M1 A1ft One float \((\geq 0)\) correct
Both floats correctB1 Independent of working. 3 marks total
Part (d)
AnswerMarks Guidance
AnswerMarks Guidance
Total float on \(D = 18 - 5 - 6 = 7\)M1 A1cso Attempt to calculate a lower bound. Accept awrt 2.81. 2 marks total
Part (e)
AnswerMarks Guidance
AnswerMarks Guidance
Total float on \(G = 17 - 4 - 7 = 6\)M1 A1 At least 7 activities including at least 4 floats. Do not accept scheduling diagram. Critical activities dealt with correctly
Lower bound \(= \dfrac{59}{21} = 3\) workersM1 A1 All 11 activities including at least 8 floats. Non-critical activities dealt with correctly. 4 marks total
Total: 16 marks
# Question 7:

## Part (a)(i)
| Answer | Marks | Guidance |
|--------|-------|----------|
| I depends on B, E and F only; K depends on B, E, F **and** D | B1 DB1 | K, I, D and at least one of B, E, F referred to. Correct but maybe incomplete: bod |

## Part (a)(ii)
| Answer | Marks | Guidance |
|--------|-------|----------|
| So that G and H will not share the same start and end events; so that G and H can be uniquely described in terms of their end events | B1 | Clear correct statement. No bod. Must refer to either events or activities. 'unique' alone not enough. **3 marks total** |

## Part (b)
| Answer | Marks | Guidance |
|--------|-------|----------|
| All top boxes complete, values generally increasing left to right | M1 A1 | Condone one rogue. CAO |
| All bottom boxes complete, values generally decreasing R to L | M1 A1 | Condone one rogue. CAO. **4 marks total** |

## Part (c)
| Answer | Marks | Guidance |
|--------|-------|----------|
| Correct calculation of floats, all three numbers correct (ft) | M1 A1ft | One float $(\geq 0)$ correct |
| Both floats correct | B1 | Independent of working. **3 marks total** |

## Part (d)
| Answer | Marks | Guidance |
|--------|-------|----------|
| Total float on $D = 18 - 5 - 6 = 7$ | M1 A1cso | Attempt to calculate a lower bound. Accept awrt 2.81. **2 marks total** |

## Part (e)
| Answer | Marks | Guidance |
|--------|-------|----------|
| Total float on $G = 17 - 4 - 7 = 6$ | M1 A1 | At least 7 activities including at least 4 floats. Do not accept scheduling diagram. Critical activities dealt with correctly |
| Lower bound $= \dfrac{59}{21} = 3$ workers | M1 A1 | All 11 activities including at least 8 floats. Non-critical activities dealt with correctly. **4 marks total** |

**Total: 16 marks**
7.

\begin{figure}[h]
\begin{center}
  \includegraphics[alt={},max width=\textwidth]{e02c4a9a-d2ab-489f-b838-9b4d902c4457-9_1042_1426_267_315}
\captionsetup{labelformat=empty}
\caption{Figure 7}
\end{center}
\end{figure}

A project is modelled by the activity network shown in Figure 7. The activities are represented by the arcs. The number in brackets on each arc gives the time required, in hours, to complete the activity. The numbers in circles are the event numbers. Each activity requires one worker.
\begin{enumerate}[label=(\alph*)]
\item Explain the significance of the dummy activity
\begin{enumerate}[label=(\roman*)]
\item from event 4 to event 6 ,
\item from event 5 to event 7\\
(3)
\end{enumerate}\item Calculate the early time and the late time for each event. Write these in the boxes in the answer book.
\item Calculate the total float on each of activities D and G. You must make the numbers you use in your calculations clear.
\item Calculate a lower bound for the minimum number of workers required to complete the project in the minimum time.
\item On the grid in your answer book, draw a cascade (Gantt) chart for this project.
\end{enumerate}

\hfill \mbox{\textit{Edexcel D1 2012 Q7 [16]}}