Edexcel D1 2024 January — Question 4 7 marks

Exam BoardEdexcel
ModuleD1 (Decision Mathematics 1)
Year2024
SessionJanuary
Marks7
PaperDownload PDF ↗
Mark schemeDownload PDF ↗
TopicCritical Path Analysis
TypeIdentify guaranteed critical activities
DifficultyModerate -0.3 This is a standard D1 critical path question requiring network drawing and logical deduction about critical activities. Part (a) is routine application of precedence table conversion. Part (b) requires understanding that if E is critical and there's only one critical path, activities must lie on the path through E, but the logic is straightforward once the network is drawn—easier than average A-level maths questions overall.
Spec7.05a Critical path analysis: activity on arc networks

4.
ActivityImmediately preceding activities
A-
B-
CA, B
DA, B
EB
FC, D, E
GF
HB
IF
JF
KG
LG, H, I, J
MG, I
  1. Draw the activity network described in the precedence table, using activity on arc and the minimum number of dummies.
  2. Given that
    • the activity network contains only one critical path
    • activity E is on this critical path
      state
      1. which activities could never be critical,
      2. which activities must be critical.

Question 4 (Precedence Network):
Part (a) - Activity Network:
AnswerMarks Guidance
AnswerMark Guidance
Nine activities on arcs, one start, at least two dummies placeda1M1
Activities A, B, 1st dummy (correct arrow), C, D, E, H dealt with correctlya1A1
2nd dummy (correct arrow), activities F, G, I, J dealt with correctlya2A1
Activities K, L, M dealt with correctly (third and fourth dummies + arrows)a3A1
All arrows correctly placed, one finish, at most four dummies4A1 CSO
Part (b)(i) - Non-critical Activities:
AnswerMarks Guidance
AnswerMark Guidance
Activities A, C, D and H cannot be criticalb1B1 CAO (A, C, D, H and no others)
Part (b)(ii) - Must be Critical:
AnswerMarks Guidance
AnswerMark Guidance
Activities B and F must be criticalb2B1 CAO (B and F and no others - accept if E mentioned)
# Question 4 (Precedence Network):

## Part (a) - Activity Network:
| Answer | Mark | Guidance |
|--------|------|----------|
| Nine activities on arcs, one start, at least two dummies placed | a1M1 | |
| Activities A, B, 1st dummy (correct arrow), C, D, E, H dealt with correctly | a1A1 | |
| 2nd dummy (correct arrow), activities F, G, I, J dealt with correctly | a2A1 | |
| Activities K, L, M dealt with correctly (third and fourth dummies + arrows) | a3A1 | |
| All arrows correctly placed, one finish, at most four dummies | 4A1 | CSO |

## Part (b)(i) - Non-critical Activities:
| Answer | Mark | Guidance |
|--------|------|----------|
| Activities A, C, D and H cannot be critical | b1B1 | CAO (A, C, D, H and no others) |

## Part (b)(ii) - Must be Critical:
| Answer | Mark | Guidance |
|--------|------|----------|
| Activities B and F must be critical | b2B1 | CAO (B and F and no others - accept if E mentioned) |
4.

\begin{center}
\begin{tabular}{|l|l|}
\hline
Activity & Immediately preceding activities \\
\hline
A & - \\
\hline
B & - \\
\hline
C & A, B \\
\hline
D & A, B \\
\hline
E & B \\
\hline
F & C, D, E \\
\hline
G & F \\
\hline
H & B \\
\hline
I & F \\
\hline
J & F \\
\hline
K & G \\
\hline
L & G, H, I, J \\
\hline
M & G, I \\
\hline
\end{tabular}
\end{center}
\begin{enumerate}[label=(\alph*)]
\item Draw the activity network described in the precedence table, using activity on arc and the minimum number of dummies.
\item Given that

\begin{itemize}
  \item the activity network contains only one critical path
  \item activity E is on this critical path\\
state
\begin{enumerate}[label=(\roman*)]
\item which activities could never be critical,
\item which activities must be critical.
\end{itemize}
\end{enumerate}\end{enumerate}

\hfill \mbox{\textit{Edexcel D1 2024 Q4 [7]}}