OCR Further Discrete AS 2022 June — Question 2 7 marks

Exam BoardOCR
ModuleFurther Discrete AS (Further Discrete AS)
Year2022
SessionJune
Marks7
PaperDownload PDF ↗
Mark schemeDownload PDF ↗
TopicCritical Path Analysis
TypeFind range for variable duration
DifficultyStandard +0.3 This is a standard critical path analysis question requiring routine forward/backward pass calculations and float determination. Part (c) adds a slight twist by asking for a maximum value of t, but this is a straightforward application of understanding float and critical path concepts—students just need to recognize that B can be delayed by its float amount without affecting project completion time. The question is slightly above average difficulty due to the multi-part nature and the variable constraint in part (c), but remains a textbook-style exercise with no novel problem-solving required.
Spec7.05a Critical path analysis: activity on arc networks7.05b Forward and backward pass: earliest/latest times, critical activities7.05c Total float: calculation and interpretation

2 The activities involved in a project and their durations, in hours, are represented in the activity network below. \includegraphics[max width=\textwidth, alt={}, center]{74b6f747-7045-4902-8b21-0b59c007f7f6-3_446_1139_338_230}
  1. Carry out a forward pass and a backward pass through the network.
  2. Calculate the float for each activity. A delay means that activity B cannot finish until \(t\) hours have elapsed from the start of the project.
  3. Determine the maximum value of \(t\) for which the project can be completed in 16 hours.

Question 2:
Part (a)
AnswerMarks Guidance
AnswerMarks Guidance
Forward pass: A(5), C(6), D(4), F(3), giving values \(\4\ 14\
Backward pass: B(3), E(2), giving \(\3\ 7\
Final diagram correctA1 cao
Part (b)
AnswerMarks Guidance
AnswerMarks Guidance
\(A=0, C=0, F=0\)B1 A, C and \(F=0\)
\(B=4, D=2, E=5, G=5\) correct or ft from (a)B1 FT B, D, E and G correct or ft their values from (a)
Part (c)
AnswerMarks Guidance
AnswerMarks Guidance
Longest route is now \(BDF = t+7\)M1 Consider any route starting with B, or (their)\(7+(16-\text{their } 14)\) or \(16-(3+4)\), or implied from answer \(t=9\)
Maximum value of \(t=9\)A1 9 as answer
# Question 2:

## Part (a)

| Answer | Marks | Guidance |
|--------|-------|----------|
| Forward pass: A(5), C(6), D(4), F(3), giving values $\|4\|14\|$; nodes $\|0\|0\|$, $\|5\|7\|$ shown | B1 | Forward pass all correct |
| Backward pass: B(3), E(2), giving $\|3\|7\|$, $\|5\|10\|$ with values not increasing working from end to start | M1 | Backward pass with values not increasing working from end to start |
| Final diagram correct | A1 | cao |

## Part (b)

| Answer | Marks | Guidance |
|--------|-------|----------|
| $A=0, C=0, F=0$ | B1 | A, C and $F=0$ |
| $B=4, D=2, E=5, G=5$ correct or ft from (a) | B1 FT | B, D, E and G correct or ft their values from (a) |

## Part (c)

| Answer | Marks | Guidance |
|--------|-------|----------|
| Longest route is now $BDF = t+7$ | M1 | Consider any route starting with B, or (their)$7+(16-\text{their } 14)$ or $16-(3+4)$, or implied from answer $t=9$ |
| Maximum value of $t=9$ | A1 | 9 as answer |

---
2 The activities involved in a project and their durations, in hours, are represented in the activity network below.\\
\includegraphics[max width=\textwidth, alt={}, center]{74b6f747-7045-4902-8b21-0b59c007f7f6-3_446_1139_338_230}
\begin{enumerate}[label=(\alph*)]
\item Carry out a forward pass and a backward pass through the network.
\item Calculate the float for each activity.

A delay means that activity B cannot finish until $t$ hours have elapsed from the start of the project.
\item Determine the maximum value of $t$ for which the project can be completed in 16 hours.
\end{enumerate}

\hfill \mbox{\textit{OCR Further Discrete AS 2022 Q2 [7]}}