OCR Further Discrete AS 2018 June — Question 6

Exam BoardOCR
ModuleFurther Discrete AS (Further Discrete AS)
Year2018
SessionJune
TopicPermutations & Arrangements
TypeAssignment/allocation matching problems

6 Sheona and Tim are making a short film. The activities involved, their durations and immediate predecessors are given in the table below.
ActivityDuration (days)Immediate predecessorsST
APlanning2-
BWrite script1A
CChoose locations1A
DCasting0.5A
ERehearsals2B, D
FGet permissions1C
GFirst day filming1E, F
HFirst day edits1G
ISecond day filming0.5G
JSecond day edits2H, I
KFinishing1J
  1. By using an activity network, find:
    • the minimum project completion time
    • the critical activities
    • the float on each non-critical activity.
    • Give two reasons why the filming may take longer than the minimum project completion time.
    Each activity will involve either Sheona or Tim or both.
    • The activities that Sheona will do are ticked in the S column.
    • The activities that Tim will do are ticked in the T column.
    • They will do the planning and finishing together.
    • Some of the activities involve other people as well.
    An additional restriction is that Sheona and Tim can each only do one activity at a time.
  2. Explain why the minimum project completion is longer than in part (i) when this additional restriction is taken into account.
  3. The project must be completed in 14 days. Find:
    (a) the longest break that either Sheona or Tim can take,
    (b) the longest break that Sheona and Tim can take together,
    (c) the float on each activity.