A question is this type if and only if it asks you to perform forward and backward passes to find early event times and late event times on a given or constructed network.
26 questions · Moderate -0.4
| Activity | Duration (weeks) | Immediate Predecessors | |
| A | Survey sites | 8 | - |
| B | Purchase land | 22 | A |
| C | Supply materials | 10 | - |
| D | Supply machinery | 4 | - |
| E | Excavate foundations | 9 | B, D |
| F | Lay drains | 11 | B, C, D |
| G | Build walls | 9 | E, F |
| H | Lay floor | 10 | E, F |
| I | Install roof | 3 | G |
| J | Install electrics | 5 | G |
| Task | E | F | H | J | ||
| 3 | 3 | 1 | 3 | ||
| 30 | 15 | 6 | 20 |
| Activity | Duration (mins) | Immediate Predecessors |
| A Refuel | 30 | - |
| B Clean cabin | 25 | - |
| C Pre-flight technical check | 15 | A |
| D Load luggage | 20 | - |
| E Load passengers | 25 | A, B |
| F Safety demonstration | 5 | E |
| G Obtain air traffic clearance | 10 | C |
| H Taxi to runway | 5 | G, D |
| Task | A | B | D | E |
| New time (mins) | 20 | 20 | 15 | 15 |
| Extra cost | 250 | 50 | 50 | 100 |
| Activity | Duration (mins) | Immediate predecessors |
| A | 3 | - |
| B | 2 | - |
| C | 3 | A |
| D | 5 | A, B |
| E | 1 | C |
| Task | Description | Duration (mins) |
| A | Fill kettle and switch on | 0.5 |
| B | Boil kettle | 1.5 |
| C | Cut bread and put in toaster | 0.5 |
| D | Toast bread | 2 |
| E | Put eggs in pan of water and light gas | 1 |
| F | Boil eggs | 5 |
| G | Put tablecloth, cutlery and crockery on table | 2.5 |
| H | Make tea and put on table | 0.5 |
| I | Collect toast and put on table | 0.5 |
| J | Put eggs in cups and put on table | 1 |
| Task | Duration (seconds) | Immediate predecessors | |
| B | get out bowl and implements | 10 | - |
| I | get out ingredients | 10 | - |
| L | chop lettuce | 15 | B, I |
| W | wash tomatoes and celery | 25 | B, I |
| T | chop tomatoes | 15 | W |
| C | chop celery | 10 | W |
| P | peel apple | 20 | B, I |
| A | chop apple | 10 | P |
| D | dress salad | 10 | L, T, C, A |
| Activity | Description | Duration (days) |
| A | Architect produces plans | 10 |
| Pl | Obtain planning permission | 14 |
| Demo | Demolish existing structure | 3 |
| Fo | Excavate foundations | 4 |
| W | Build walls | 3 |
| Pb | Install plumbing | 2 |
| R | Construct roof | 3 |
| Fl | Lay floor | 2 |
| E | Fit electrics | 2 |
| WD | Install windows and doors | 1 |
| Deco | Decorate | 5 |
| Task | Time (minutes) | Immediate predecessors | |
| A | measure out flour | 0.5 | - |
| B | mix flour and water | 1 | A |
| C | shell eggs | 0.5 | - |
| D | mix in eggs and fat | 2 | B, C |
| E | get currants ready | 0.5 | - |
| F | get raisins ready | 0.5 | - |
| G | fold fruit into mix | 0.5 | D, E, F |
| H | bake | 10 | G |
| Activity | Duration (mins) | Immediate predecessor(s) | |
| A | select mounting | 5 | - |
| B | glue picture to mounting | 5 | A |
| C | allow mounting glue to dry | 20 | B |
| D | measure for frame | 5 | A |
| E | select type of frame | 10 | A |
| F | cut four frame pieces | 5 | D, E |
| G | pin and glue frame pieces together | 5 | F |
| H | allow frame glue to dry | 20 | G |
| I | cut and bevel glass | 30 | D |
| J | fit glass to frame | 5 | H, I |
| K | fit mounted picture to frame | 5 | C, J |
| A | B | C | D | E | \(F\) | |
| A | - | 130 | 190 | 155 | 140 | 125 |
| B | 130 | - | 215 | 200 | 190 | 170 |
| C | 190 | 215 | - | 110 | 180 | 100 |
| D | 155 | 200 | 110 | - | 70 | 45 |
| E | 140 | 190 | 180 | 70 | - | 75 |
| \(F\) | 125 | 170 | 100 | 45 | 75 | - |
| \(n\) | \(x _ { n }\) | \(a\) | Any more data? | \(x _ { n + 1 }\) | \(b\) | \(( b - a ) > 0\) ? | \(a\) |
| 1 | 8 | 8 | Yes | 2 | 2 | No | 2 |
| 2 | - | - |
| Activity | A | \(B\) | C | D | \(E\) | \(F\) | G | H | I | \(J\) | \(K\) | \(L\) |
| Duration (days) | 2 | 5 | 6 | 7 | 9 | 4 | 3 | 2 | 3 | 2 | 3 | 1 |
| Number of workers required | 6 | 3 | 5 | 2 | 5 | 2 | 4 | 4 | 5 | 3 | 2 | 4 |
| Activity | Duration (hours) | Immediate predecessors | Number of workers |
| \(A\) : Choose summerhouse | 2 | - | 2 |
| \(B\) : Buy slabs for base | 1 | - | 2 |
| \(C\) : Take goods home | 2 | \(A , B\) | 2 |
| \(D\) : Level ground | 3 | - | 1 |
| E: Lay slabs | 2 | \(C , D\) | 2 |
| \(F\) : Treat wood | 3 | C | 1 |
| \(G\) : Install floor, walls and roof | 4 | \(E , F\) | 2 |
| \(H\) : Fit windows and door | 2 | \(G\) | 1 |
| \(I\) : Fit patio rail | 1 | \(G\) | 1 |
| \(J\) : Fit shelving | 1 | \(G\) | 1 |
| Activity | Duration (hours) | Immediate predecessors | |
| A | Choose a name for the gardening service | 2 | - |
| B | Think about what the text needs to say | 3 | - |
| C | Arrange a photo shoot | 2 | B |
| D | Visit a leaflet designer | 3 | A, \(C\) |
| E | Design website | 5 | A, \(C\) |
| \(F\) | Get business cards printed | 3 | D |
| G | Identify places to publicise services | 2 | A, \(C\) |
| H | Arrange to go on local radio | 3 | B |
| I | Distribute leaflets | 4 | D, G |
| J | Get name put on van | 1 | E |
| Activity | Duration (days) | Immediate predecessors | S | T | |
| A | Planning | 2 | - | ✓ | ✓ |
| B | Write script | 1 | A | ✓ | |
| C | Choose locations | 1 | A | ✓ | |
| D | Casting | 0.5 | A | ✓ | |
| E | Rehearsals | 2 | B, D | ✓ | |
| F | Get permissions | 1 | C | ✓ | |
| G | First day filming | 1 | E, F | ✓ | |
| H | First day edits | 1 | G | ✓ | |
| I | Second day filming | 0.5 | G | ✓ | |
| J | Second day edits | 2 | H, I | ✓ | |
| K | Finishing | 1 | J | ✓ | ✓ |
| Activity | Immediate predecessors | Duration (hours) | |
| A | Choose the topics | - | 0.5 |
| B | Find questions for round 1 | A | 2 |
| C | Check answers for round 1 | B | 2.5 |
| D | Find questions for round 2 | A | 2 |
| E | Check answers for round 2 | D | 2.5 |
| F | Choose pictures for picture round | A | 1 |
| G | Get permission to use pictures | F | 1.5 |
| H | Choose music for music round | A | 2 |
| I | Get permission to use music | H | 1.5 |
| J | Produce answer sheets | G | 0.5 |
| Activity | Immediate predecessors | Duration (minutes) |
| A | - | 4 |
| B | - | 1 |
| C | A | 2 |
| D | A, B | 5 |
| E | D | 1 |
| F | B, C | 2 |
| G | D, F | 5 |
| H | E, F | 4 |
| Activity | Duration (days) | Immediately preceding activities |
| A | 4 | - |
| B | 7 | - |
| C | 6 | - |
| D | 10 | A |
| E | 5 | A |
| F | 7 | C |
| G | 6 | B, C, E |
| H | 6 | B, C, E |
| I | 7 | B, C, E |
| J | 9 | D, H |
| K | 8 | B, C, E |
| L | 4 | F, G, K |
| M | 6 | F, G, K |
| N | 7 | F, G |
| P | 5 | M, N |
| Activity | Time taken (days) | Immediately preceding activities |
| A | 5 | - |
| B | 7 | - |
| C | 3 | - |
| D | 4 | A, B |
| E | 4 | D |
| F | 2 | B |
| G | 4 | B |
| H | 5 | C, G |
| I | 10 | C, G |
| (i) | \(A \bullet\) |
| \(B \bullet\) | \(\bullet J\) |
| \(C \bullet\) | \(\bullet K\) |
| \(D \bullet\) | \(\bullet L\) |
| \(E \bullet\) | \(\bullet M\) |
| \(F \bullet\) | \(\bullet N\) |
| \(J\) | \(K\) | \(L\) | \(M\) | \(N\) | \(O\) | |
| \(A\) | 2 | 5 | 2 | 2 | 5 | 2 |
| \(B\) | 2 | 5 | 2 | 0 | 5 | 5 |
| \(C\) | 5 | 0 | 5 | 5 | 2 | 2 |
| \(D\) | ||||||
| \(E\) | ||||||
| \(F\) |
| Activity | Immediate predecessor(s) | Duration (weeks) |
| \(A\) | - | 10 |
| B | - | 5 |
| C | B | 12 |
| D | \(A\) | 8 |
| \(E\) | C, D | 4 |
| \(F\) | C, D | 3 |
| \(G\) | C, D | 7 |
| \(H\) | E, F | 8 |
| \(I\) | G | 6 |
| \(J\) | G | 15 |
| K | H, I | 5 |
| \(L\) | K | 4 |
| Activity | Duration (days) | Immediate Predecessors |
| \(A\) | 7 | - |
| B | 6 | - |
| C | 15 | - |
| D | 9 | \(A , B\) |
| \(E\) | 8 | D |
| \(F\) | 6 | C, D |
| G | 7 | C |
| H | 14 | \(E\) |
| \(I\) | 17 | \(F , G\) |
| \(J\) | 9 | H, I |
| K | 8 | \(I\) |
| L | 12 | J, K |