AQA Further Paper 3 Discrete 2024 June — Question 8 8 marks

Exam BoardAQA
ModuleFurther Paper 3 Discrete (Further Paper 3 Discrete)
Year2024
SessionJune
Marks8
PaperDownload PDF ↗
Mark schemeDownload PDF ↗
TopicNetwork Flows
TypeAdd supersource and/or supersink
DifficultyStandard +0.8 This is a multi-source/multi-sink max flow problem requiring supersource/supersink construction, flow augmentation algorithm application, and critical analysis of network changes. While the techniques are standard Further Maths content, the three-part structure with conceptual reasoning in part (c) about flow reduction elevates it above routine textbook exercises. The need to track augmenting paths systematically and then analyze the impact of edge removal requires solid understanding rather than just mechanical application.
Spec7.02p Networks: weighted graphs, modelling connections7.04b Minimum spanning tree: Prim's and Kruskal's algorithms

Figure 1 shows a network of water pipes. The number on each arc represents the upper capacity for each pipe in litres per second. The numbers in the circles represent an initial feasible flow of 103 litres per second. \includegraphics{figure_1}
  1. On Figure 1 above, add a supersource \(S\) and a supersink \(T\) to the network. [2 marks]
  2. Using flow augmentation, find the maximum flow through the network. You must indicate any flow augmenting paths clearly in the table below. You may use Figure 2, on the opposite page, in your solution. [4 marks]
    Augmenting PathExtra Flow
    Maximum Flow ______________ litres per second
  3. While the flow through the network is at its maximum value, the pipe \(EG\) develops a leak. To repair the leak, an engineer turns off the flow of water through \(EG\) The engineer claims that the maximum flow of water through the network will reduce by 31 litres per second. Comment on the validity of the engineer's claim. [2 marks]

Question 8:
AnswerMarks Guidance
88 18

AnswerMarks
8(a)Connects supersource S to
nodes A and B with directed
arcs and connects supersink T
to nodes F and G with directed
AnswerMarks Guidance
arcs1.1b B1
Includes a correct upper
capacity on each of the four
AnswerMarks Guidance
correct arcs1.1b B1
Subtotal2
QMarking instructions AO

AnswerMarks
8(b)Finds at least one correct
augmenting path and the extra
flow (may be seen on diagram).
Condone S & T not included in
AnswerMarks Guidance
augmenting path3.1a M1
Path Flow
SADFT 4
SBGT 2
SBCEGT 1
Maximum flow = 110 litres per
second
Finds a second correct
augmenting path and the extra
flow.
Condone S & T not included in
AnswerMarks Guidance
augmenting path1.1b A1
Finds a third correct augmenting
path and the extra flow, and no
incorrect paths.

Total of all extra flows must be 7

Condone S & T not included in
AnswerMarks Guidance
augmenting path1.1b A1
Obtains 1102.2a B1
Subtotal4
Augmenting
AnswerMarks
PathExtra
Flow
AnswerMarks Guidance
SADFT4
SBGT2
SBCEGT1
QMarking instructions AO

AnswerMarks Guidance
8(c)Explains that EG is saturated/at
maximum flow before the leak2.4 E1
flow through EG can be re-routed
as each of BG, DG and DF are
also saturated.
Hence, the maximum flow through
the network decreases by 31 litres
per second and so the engineer’s
claim is correct.
Explains that the flow of 31 litres
per second through EG cannot
be re-routed as BG, DG & DF
are also all saturated or that EG
is part of the minimum cut of the
network and then concludes that
AnswerMarks Guidance
the engineer’s claim is correct2.3 R1
Subtotal2
Question total8
QMarking instructions AO
Question 8:
8 | 8 | 18 | 7 | 12 | 1 | 11
--- 8(a) ---
8(a) | Connects supersource S to
nodes A and B with directed
arcs and connects supersink T
to nodes F and G with directed
arcs | 1.1b | B1
Includes a correct upper
capacity on each of the four
correct arcs | 1.1b | B1
Subtotal | 2
Q | Marking instructions | AO | Marks | Typical solution
--- 8(b) ---
8(b) | Finds at least one correct
augmenting path and the extra
flow (may be seen on diagram).
Condone S & T not included in
augmenting path | 3.1a | M1 | Augmenting Extra
Path Flow
SADFT 4
SBGT 2
SBCEGT 1
Maximum flow = 110 litres per
second
Finds a second correct
augmenting path and the extra
flow.
Condone S & T not included in
augmenting path | 1.1b | A1
Finds a third correct augmenting
path and the extra flow, and no
incorrect paths.
Total of all extra flows must be 7
Condone S & T not included in
augmenting path | 1.1b | A1
Obtains 110 | 2.2a | B1
Subtotal | 4
Augmenting
Path | Extra
Flow
SADFT | 4
SBGT | 2
SBCEGT | 1
Q | Marking instructions | AO | Marks | Typical solution
--- 8(c) ---
8(c) | Explains that EG is saturated/at
maximum flow before the leak | 2.4 | E1 | EG is saturated, and none of the
flow through EG can be re-routed
as each of BG, DG and DF are
also saturated.
Hence, the maximum flow through
the network decreases by 31 litres
per second and so the engineer’s
claim is correct.
Explains that the flow of 31 litres
per second through EG cannot
be re-routed as BG, DG & DF
are also all saturated or that EG
is part of the minimum cut of the
network and then concludes that
the engineer’s claim is correct | 2.3 | R1
Subtotal | 2
Question total | 8
Q | Marking instructions | AO | Marks | Typical solution
Figure 1 shows a network of water pipes.

The number on each arc represents the upper capacity for each pipe in litres per second.

The numbers in the circles represent an initial feasible flow of 103 litres per second.

\includegraphics{figure_1}

\begin{enumerate}[label=(\alph*)]
\item On Figure 1 above, add a supersource $S$ and a supersink $T$ to the network.
[2 marks]

\item Using flow augmentation, find the maximum flow through the network.

You must indicate any flow augmenting paths clearly in the table below.

You may use Figure 2, on the opposite page, in your solution.
[4 marks]

\begin{tabular}{|c|c|}
\hline Augmenting Path & Extra Flow \\
\hline & \\
\hline & \\
\hline & \\
\hline & \\
\end{tabular}

Maximum Flow ______________ litres per second

\item While the flow through the network is at its maximum value, the pipe $EG$ develops a leak.

To repair the leak, an engineer turns off the flow of water through $EG$

The engineer claims that the maximum flow of water through the network will reduce by 31 litres per second.

Comment on the validity of the engineer's claim.
[2 marks]
\end{enumerate}

\hfill \mbox{\textit{AQA Further Paper 3 Discrete 2024 Q8 [8]}}