OCR D2 — Question 4 11 marks

Exam BoardOCR
ModuleD2 (Decision Mathematics 2)
Marks11
PaperDownload PDF ↗
Mark schemeDownload PDF ↗
TopicCritical Path Analysis
TypeDraw activity network from table
DifficultyModerate -0.3 This is a standard Critical Path Analysis question requiring routine application of forward/backward scan algorithms and basic critical path reasoning. While it involves multiple parts and some interpretation (penalty costs), these are textbook techniques in D2 with no novel problem-solving required, making it slightly easier than average.
Spec7.05a Critical path analysis: activity on arc networks7.05b Forward and backward pass: earliest/latest times, critical activities7.05c Total float: calculation and interpretation7.05d Latest start and earliest finish: independent and interfering float

4.
\$ FMMUMITI7 IP HIZ3 UFHGHQFHIT
ா\$ மோங்கோ
ா\%\%mmum \includegraphics[max width=\textwidth, alt={}, center]{34728928-2a21-463d-982e-c46ab2dc05c8-4_49_268_424_301} \includegraphics[max width=\textwidth, alt={}, center]{34728928-2a21-463d-982e-c46ab2dc05c8-4_46_465_482_301} \includegraphics[max width=\textwidth, alt={}, center]{34728928-2a21-463d-982e-c46ab2dc05c8-4_49_533_539_301} \includegraphics[max width=\textwidth, alt={}, center]{34728928-2a21-463d-982e-c46ab2dc05c8-4_49_472_593_303} \includegraphics[max width=\textwidth, alt={}, center]{34728928-2a21-463d-982e-c46ab2dc05c8-4_49_497_648_303} \includegraphics[max width=\textwidth, alt={}, center]{34728928-2a21-463d-982e-c46ab2dc05c8-4_54_501_703_306} \includegraphics[max width=\textwidth, alt={}, center]{34728928-2a21-463d-982e-c46ab2dc05c8-4_45_467_762_303} \includegraphics[max width=\textwidth, alt={}, center]{34728928-2a21-463d-982e-c46ab2dc05c8-4_49_463_813_303} \includegraphics[max width=\textwidth, alt={}, center]{34728928-2a21-463d-982e-c46ab2dc05c8-4_47_460_872_303} \(\square\) \(\square\) Fig. 2
Construct an activity network to model the work involved in laying the foundations and putting in services for an industrial complex.
  1. Execute a forward scan to find the minimum time in which the project can be completed.
  2. Execute a backward scan to determine which activities lie on the critical path. The contractor is committed to completing the project in this minimum time and faces a penalty of \(\pounds 50000\) for each day that the project is late. Unfortunately, before any work has begun, flooding means that activity \(E\) will take 3 days longer than the 7 days allocated.
  3. Activity \(K\) could be completed in 1 day at an extra cost of \(\pounds 90000\). Explain why doing this is not economical.
    (2 marks)
  4. If the time taken to complete any one activity, other than \(E\), could be reduced by 2 days at an extra cost of \(\pounds 80000\), for which activities on their own would this be profitable. Explain your reasoning.
    (3 marks)
    11 marks

(a)
![Network diagram with forward and backward scan values]
AnswerMarks Guidance
lower figures give forward scan minimum time is 48 daysM1 A1, A1
(b) upper figures give backward scan critical path is \(BCEHKO\)M1 A1, A1
(c) \(E\) on critical path \(\therefore £150,000\) penalty if reduce \(K\) by more than 1 day it is no longer on critical path \(\therefore\) only reduces penalty by £50,000 at cost of £90,000B2
(d) \(B\), \(C\) and \(O\): reducing any of these by 2 days reduces minimum time by 2 days this reduces penalty by £100,000 at cost of £80,000 \(\therefore\) profitableB3 (11)
**(a)**

![Network diagram with forward and backward scan values]

lower figures give forward scan minimum time is 48 days | M1 A1, A1 |

**(b)** upper figures give backward scan critical path is $BCEHKO$ | M1 A1, A1 |

**(c)** $E$ on critical path $\therefore £150,000$ penalty if reduce $K$ by more than 1 day it is no longer on critical path $\therefore$ only reduces penalty by £50,000 at cost of £90,000 | B2 |

**(d)** $B$, $C$ and $O$: reducing any of these by 2 days reduces minimum time by 2 days this reduces penalty by £100,000 at cost of £80,000 $\therefore$ profitable | B3 | **(11)** |

---
4.\\
\$ FMMUMITI7 IP HIZ3 UFHGHQFHIT\\
ா\$ மோங்கோ\\
ா\%\%mmum\\
\includegraphics[max width=\textwidth, alt={}, center]{34728928-2a21-463d-982e-c46ab2dc05c8-4_49_268_424_301}\\
\includegraphics[max width=\textwidth, alt={}, center]{34728928-2a21-463d-982e-c46ab2dc05c8-4_46_465_482_301}\\
\includegraphics[max width=\textwidth, alt={}, center]{34728928-2a21-463d-982e-c46ab2dc05c8-4_49_533_539_301}\\
\includegraphics[max width=\textwidth, alt={}, center]{34728928-2a21-463d-982e-c46ab2dc05c8-4_49_472_593_303}\\
\includegraphics[max width=\textwidth, alt={}, center]{34728928-2a21-463d-982e-c46ab2dc05c8-4_49_497_648_303}\\
\includegraphics[max width=\textwidth, alt={}, center]{34728928-2a21-463d-982e-c46ab2dc05c8-4_54_501_703_306}\\
\includegraphics[max width=\textwidth, alt={}, center]{34728928-2a21-463d-982e-c46ab2dc05c8-4_45_467_762_303}\\
\includegraphics[max width=\textwidth, alt={}, center]{34728928-2a21-463d-982e-c46ab2dc05c8-4_49_463_813_303}\\
\includegraphics[max width=\textwidth, alt={}, center]{34728928-2a21-463d-982e-c46ab2dc05c8-4_47_460_872_303}\\
$\square$\\
$\square$

Fig. 2\\
Construct an activity network to model the work involved in laying the foundations and putting in services for an industrial complex.
\begin{enumerate}[label=(\alph*)]
\item Execute a forward scan to find the minimum time in which the project can be completed.
\item Execute a backward scan to determine which activities lie on the critical path.

The contractor is committed to completing the project in this minimum time and faces a penalty of $\pounds 50000$ for each day that the project is late. Unfortunately, before any work has begun, flooding means that activity $E$ will take 3 days longer than the 7 days allocated.
\item Activity $K$ could be completed in 1 day at an extra cost of $\pounds 90000$. Explain why doing this is not economical.\\
(2 marks)
\item If the time taken to complete any one activity, other than $E$, could be reduced by 2 days at an extra cost of $\pounds 80000$, for which activities on their own would this be profitable. Explain your reasoning.\\
(3 marks)\\
11 marks
\end{enumerate}

\hfill \mbox{\textit{OCR D2  Q4 [11]}}