1
Figure 1 below shows an activity diagram for a project. Each activity requires one worker. The duration required for each activity is given in hours.
- Find the earliest start time and the latest finish time for each activity and insert these values on Figure 1.
- Find the critical path.
- Find the float time of activity \(F\).
- Using Figure 2 on page 3, draw a resource histogram to illustrate how the project can be completed in the minimum time, assuming that each activity is to start as early as possible.
- Given that there are two workers available for the project, find the minimum completion time for the project.
- Write down an allocation of tasks to the two workers that corresponds to your answer in part (d)(i).
\section*{Answer space for question 1}
\begin{figure}[h]
\captionsetup{labelformat=empty}
\caption{Figure 1}
\includegraphics[alt={},max width=\textwidth]{34de3f03-a275-44fb-88b2-b88038bcec97-02_687_1655_1941_189}
\end{figure}
\section*{Answer space for question 1}
\begin{figure}[h]
\captionsetup{labelformat=empty}
\caption{Figure 2}
\includegraphics[alt={},max width=\textwidth]{34de3f03-a275-44fb-88b2-b88038bcec97-03_1115_1575_434_283}
\end{figure}
\includegraphics[max width=\textwidth, alt={}]{34de3f03-a275-44fb-88b2-b88038bcec97-03_1024_1593_1683_267}