AQA D2 2006 June — Question 1 14 marks

Exam BoardAQA
ModuleD2 (Decision Mathematics 2)
Year2006
SessionJune
Marks14
PaperDownload PDF ↗
Mark schemeDownload PDF ↗
TopicCritical Path Analysis
TypeDraw cascade/Gantt chart
DifficultyModerate -0.8 This is a standard textbook critical path analysis question requiring systematic application of well-defined algorithms (forward pass, backward pass, float calculation) with no novel problem-solving. The multi-part structure and drawing requirements add length but not conceptual difficulty, making it easier than average A-level maths.
Spec7.05a Critical path analysis: activity on arc networks7.05b Forward and backward pass: earliest/latest times, critical activities7.05c Total float: calculation and interpretation7.05d Latest start and earliest finish: independent and interfering float7.05e Cascade charts: scheduling and effect of delays

1 [Figures 1 and 2, printed on the insert, are provided for use in this question.] A construction project is to be undertaken. The table shows the activities involved.
ActivityImmediate PredecessorsDuration (days)
A-2
BA5
CA8
DB8
EB10
FB4
G\(C , F\)7
\(H\)D, E4
I\(G , H\)3
  1. Complete the activity network for the project on Figure 1.
  2. Find the earliest start time for each activity.
  3. Find the latest finish time for each activity.
  4. Find the critical path.
  5. State the float time for each non-critical activity.
  6. On Figure 2, draw a cascade diagram (Gantt chart) for the project, assuming each activity starts as late as possible.

Question 1:
Part (a)
AnswerMarks Guidance
AnswerMarks Guidance
Activity network with correct structure showing nodes with earliest start time, latest finish time, durationM1 SCA
Almost correct (up to 2 slips)A1
Fully correct diagramA1 Total: 3
Part (b)
AnswerMarks Guidance
AnswerMarks Guidance
Forward pass for earliest start timesM1
All correctA1 Total: 2
Part (c)
AnswerMarks Guidance
AnswerMarks Guidance
Backward pass for latest finish timesM1
All correctA1 Total: 2
Part (d)
AnswerMarks Guidance
AnswerMarks Guidance
Critical path \(A\ B\ E\ H\ I\)B1 Total: 1
Part (e)
AnswerMarks Guidance
AnswerMarks Guidance
Non-critical activities \(C, D, F, G\) with floats \(4, 2, 3, 3\) respectivelyM1 At least one float time correct
All correctA1 Total: 2
Part (f)
AnswerMarks Guidance
AnswerMarks Guidance
Their critical path on chart\(\text{B1}\sqrt{}\)
\(C\) from 6 to 14 (with space 2–6)M1 One other activity (condone no slack or earliest start)
\(D\) from 9 to 17 (with slack 7–9)A1 2 other non-critical activities
\(F\) and \(G\) from 10 to 21 with appropriate slackA1 All correct; Total: 4
# Question 1:

## Part (a)
| Answer | Marks | Guidance |
|--------|-------|----------|
| Activity network with correct structure showing nodes with earliest start time, latest finish time, duration | M1 | SCA |
| Almost correct (up to 2 slips) | A1 | |
| Fully correct diagram | A1 | Total: 3 |

## Part (b)
| Answer | Marks | Guidance |
|--------|-------|----------|
| Forward pass for earliest start times | M1 | |
| All correct | A1 | Total: 2 |

## Part (c)
| Answer | Marks | Guidance |
|--------|-------|----------|
| Backward pass for latest finish times | M1 | |
| All correct | A1 | Total: 2 |

## Part (d)
| Answer | Marks | Guidance |
|--------|-------|----------|
| Critical path $A\ B\ E\ H\ I$ | B1 | Total: 1 |

## Part (e)
| Answer | Marks | Guidance |
|--------|-------|----------|
| Non-critical activities $C, D, F, G$ with floats $4, 2, 3, 3$ respectively | M1 | At least one float time correct |
| All correct | A1 | Total: 2 |

## Part (f)
| Answer | Marks | Guidance |
|--------|-------|----------|
| Their critical path on chart | $\text{B1}\sqrt{}$ | |
| $C$ from 6 to 14 (with space 2–6) | M1 | One other activity (condone no slack or earliest start) |
| $D$ from 9 to 17 (with slack 7–9) | A1 | 2 other non-critical activities |
| $F$ and $G$ from 10 to 21 with appropriate slack | A1 | All correct; Total: 4 |

---
1 [Figures 1 and 2, printed on the insert, are provided for use in this question.] A construction project is to be undertaken. The table shows the activities involved.

\begin{center}
\begin{tabular}{|l|l|l|}
\hline
Activity & Immediate Predecessors & Duration (days) \\
\hline
A & - & 2 \\
\hline
B & A & 5 \\
\hline
C & A & 8 \\
\hline
D & B & 8 \\
\hline
E & B & 10 \\
\hline
F & B & 4 \\
\hline
G & $C , F$ & 7 \\
\hline
$H$ & D, E & 4 \\
\hline
I & $G , H$ & 3 \\
\hline
\end{tabular}
\end{center}
\begin{enumerate}[label=(\alph*)]
\item Complete the activity network for the project on Figure 1.
\item Find the earliest start time for each activity.
\item Find the latest finish time for each activity.
\item Find the critical path.
\item State the float time for each non-critical activity.
\item On Figure 2, draw a cascade diagram (Gantt chart) for the project, assuming each activity starts as late as possible.
\end{enumerate}

\hfill \mbox{\textit{AQA D2 2006 Q1 [14]}}