Edexcel FD1 AS 2024 June — Question 2 8 marks

Exam BoardEdexcel
ModuleFD1 AS (Further Decision 1 AS)
Year2024
SessionJune
Marks8
PaperDownload PDF ↗
Mark schemeDownload PDF ↗
TopicCritical Path Analysis
TypeDraw activity network from table
DifficultyModerate -0.8 This is a standard textbook exercise in critical path analysis requiring routine application of well-defined algorithms: drawing an activity network from a precedence table (with specified dummy count), calculating early/late event times, identifying critical activities, and basic time calculations. All steps follow mechanical procedures with no problem-solving insight required, making it easier than average A-level material.
Spec7.05a Critical path analysis: activity on arc networks

2. A company manages an awards evening. The table below lists the activities required to set up the room for the evening, and their immediately preceding activities. Each activity requires exactly one person.
ActivityImmediately preceding activities
A-
BA
CA
DC
EC
FB, D, E
GE
HB
JH, F, G
Figure 1 shows a partially completed activity network used to model the project. Each activity is represented by an arc. \begin{figure}[h]
\includegraphics[alt={},max width=\textwidth]{ca57c64b-0b33-4179-be7f-684bd6ea2162-04_440_813_1689_726} \captionsetup{labelformat=empty} \caption{Figure 1}
\end{figure}
  1. Add the remaining five activities to Diagram 1 in the answer book to complete the activity network, using exactly two dummies. In addition to setting up the room, the company must prepare the meals for the guests. Figure 2 shows the activity network for preparing the main courses. The numbers in brackets represent the time, in minutes, to complete each task. \begin{figure}[h]
    \includegraphics[alt={},max width=\textwidth]{ca57c64b-0b33-4179-be7f-684bd6ea2162-05_793_1515_451_373} \captionsetup{labelformat=empty} \caption{Figure 2}
    \end{figure}
  2. Complete Diagram 2 in the answer book to show the early event times and the late event times for the activity network shown in Figure 2.
  3. State the critical activities.
  4. Given that the main courses need to be ready to be served (with all activities completed) at 8 pm , state the latest time that activity \(R\) can start.

Question 2:
Part (a)
AnswerMarks Guidance
Answer/WorkingMark Guidance
Network drawn with correct structureM1 1.1b
Activities E, F, H labelled and one dummy (including correct arrow) dealt with correctlyA1 (E,F,H) Ignore lack of or incorrect arrows on E/F/H for this mark only
CAO: completely correct diagram, all labels and arrows correct on activities and dummies, one finish and exactly two dummies (no additional nodes or activities)A1 "Dealt with correctly" means activity starts from correct event but need not finish at correct event
Part (b)
AnswerMarks Guidance
Answer/WorkingMark Guidance
All boxes completed, numbers generally increasing L to R (condone one "rogue") and decreasing R to L (condone one "rogue" or missing 0 in first box)M1 2.1
CAO (all top boxes correct)A1 1.1b
CAO (all bottom boxes correct)A1 1.1b
Part (c)
AnswerMarks Guidance
Answer/WorkingMark Guidance
Critical activities are L, Q, S, T and YB1 CAO
Part (d)
AnswerMarks Guidance
Answer/WorkingMark Guidance
7:33pmB1 CAO. Can also say 19:33. Do NOT accept 7:33 (without the pm)
# Question 2:

## Part (a)
| Answer/Working | Mark | Guidance |
|---|---|---|
| Network drawn with correct structure | M1 | 1.1b |
| Activities E, F, H labelled and one dummy (including correct arrow) dealt with correctly | A1 (E,F,H) | Ignore lack of or incorrect arrows on E/F/H for this mark only |
| CAO: completely correct diagram, all labels and arrows correct on activities and dummies, one finish and exactly two dummies (no additional nodes or activities) | A1 | "Dealt with correctly" means activity starts from correct event but need not finish at correct event |

## Part (b)
| Answer/Working | Mark | Guidance |
|---|---|---|
| All boxes completed, numbers generally increasing L to R (condone one "rogue") and decreasing R to L (condone one "rogue" or missing 0 in first box) | M1 | 2.1 |
| CAO (all top boxes correct) | A1 | 1.1b |
| CAO (all bottom boxes correct) | A1 | 1.1b |

## Part (c)
| Answer/Working | Mark | Guidance |
|---|---|---|
| Critical activities are L, Q, S, T and Y | B1 | CAO |

## Part (d)
| Answer/Working | Mark | Guidance |
|---|---|---|
| 7:33pm | B1 | CAO. Can also say 19:33. Do NOT accept 7:33 (without the pm) |

---
2. A company manages an awards evening.

The table below lists the activities required to set up the room for the evening, and their immediately preceding activities. Each activity requires exactly one person.

\begin{center}
\begin{tabular}{|l|l|}
\hline
Activity & Immediately preceding activities \\
\hline
A & - \\
\hline
B & A \\
\hline
C & A \\
\hline
D & C \\
\hline
E & C \\
\hline
F & B, D, E \\
\hline
G & E \\
\hline
H & B \\
\hline
J & H, F, G \\
\hline
\end{tabular}
\end{center}

Figure 1 shows a partially completed activity network used to model the project. Each activity is represented by an arc.

\begin{figure}[h]
\begin{center}
  \includegraphics[alt={},max width=\textwidth]{ca57c64b-0b33-4179-be7f-684bd6ea2162-04_440_813_1689_726}
\captionsetup{labelformat=empty}
\caption{Figure 1}
\end{center}
\end{figure}
\begin{enumerate}[label=(\alph*)]
\item Add the remaining five activities to Diagram 1 in the answer book to complete the activity network, using exactly two dummies.

In addition to setting up the room, the company must prepare the meals for the guests. Figure 2 shows the activity network for preparing the main courses. The numbers in brackets represent the time, in minutes, to complete each task.

\begin{figure}[h]
\begin{center}
  \includegraphics[alt={},max width=\textwidth]{ca57c64b-0b33-4179-be7f-684bd6ea2162-05_793_1515_451_373}
\captionsetup{labelformat=empty}
\caption{Figure 2}
\end{center}
\end{figure}
\item Complete Diagram 2 in the answer book to show the early event times and the late event times for the activity network shown in Figure 2.
\item State the critical activities.
\item Given that the main courses need to be ready to be served (with all activities completed) at 8 pm , state the latest time that activity $R$ can start.
\end{enumerate}

\hfill \mbox{\textit{Edexcel FD1 AS 2024 Q2 [8]}}