Edexcel D1 2002 November — Question 2 6 marks

Exam BoardEdexcel
ModuleD1 (Decision Mathematics 1)
Year2002
SessionNovember
Marks6
PaperDownload PDF ↗
Mark schemeDownload PDF ↗
TopicCritical Path Analysis
TypeExplain dummy activities
DifficultyModerate -0.8 This is a straightforward application of activity network construction requiring students to identify where a dummy is needed (activity E precedes both H and I/J/K, while D and F only precede H). Part (b) tests basic understanding of dummy purpose. Standard D1 bookwork with minimal problem-solving.
Spec7.05a Critical path analysis: activity on arc networks

2. The precedence table for activities involved in manufacturing a toy is shown below.
ActivityPreceding activity
\(A\)-
\(B\)-
\(C\)-
\(D\)\(A\)
\(E\)\(A\)
\(F\)\(B\)
\(G\)\(B\)
\(H\)\(C , D , E , F\)
\(I\)\(E\)
\(J\)\(E\)
\(K\)\(I\)
\(L\)\(I\)
\(M\)\(G , H , K\)
  1. Draw an activity network, using activity on arc, and exactly one dummy, to model the manufacturing process.
  2. Explain briefly why it is necessary to use a dummy in this case.

2. The precedence table for activities involved in manufacturing a toy is shown below.

\begin{center}
\begin{tabular}{ | c | c | }
\hline
Activity & Preceding activity \\
\hline
$A$ & - \\
\hline
$B$ & - \\
\hline
$C$ & - \\
\hline
$D$ & $A$ \\
\hline
$E$ & $A$ \\
\hline
$F$ & $B$ \\
\hline
$G$ & $B$ \\
\hline
$H$ & $C , D , E , F$ \\
\hline
$I$ & $E$ \\
\hline
$J$ & $E$ \\
\hline
$K$ & $I$ \\
\hline
$L$ & $I$ \\
\hline
$M$ & $G , H , K$ \\
\hline
\end{tabular}
\end{center}
\begin{enumerate}[label=(\alph*)]
\item Draw an activity network, using activity on arc, and exactly one dummy, to model the manufacturing process.
\item Explain briefly why it is necessary to use a dummy in this case.
\end{enumerate}

\hfill \mbox{\textit{Edexcel D1 2002 Q2 [6]}}