Edexcel D1 2018 June — Question 3 7 marks

Exam BoardEdexcel
ModuleD1 (Decision Mathematics 1)
Year2018
SessionJune
Marks7
PaperDownload PDF ↗
Mark schemeDownload PDF ↗
TopicCritical Path Analysis
TypeIdentify guaranteed critical activities
DifficultyModerate -0.8 Part (a) is a standard network drawing exercise requiring careful dummy placement (5 marks), while part (b) requires simple logical deduction about critical path dependencies given that D is critical. This is routine D1 material testing basic understanding of critical activities with minimal problem-solving—easier than average A-level maths.
Spec7.05a Critical path analysis: activity on arc networks

3. (a) Draw the activity network described in the precedence table below, using activity on arc and exactly four dummies.
(5)
ActivityImmediately preceding activities
A-
B-
C-
DA
ED
FA, B
GA, B, C
HA, B, C
IE, F, G
JE, F, G
KE, F, G, H
Given that D is a critical activity,
(b) state which other activities must also be critical.
(2)

3. (a) Draw the activity network described in the precedence table below, using activity on arc and exactly four dummies.\\
(5)

\begin{center}
\begin{tabular}{|l|l|}
\hline
Activity & Immediately preceding activities \\
\hline
A & - \\
\hline
B & - \\
\hline
C & - \\
\hline
D & A \\
\hline
E & D \\
\hline
F & A, B \\
\hline
G & A, B, C \\
\hline
H & A, B, C \\
\hline
I & E, F, G \\
\hline
J & E, F, G \\
\hline
K & E, F, G, H \\
\hline
\end{tabular}
\end{center}

Given that D is a critical activity,\\
(b) state which other activities must also be critical.\\
(2)\\

\hfill \mbox{\textit{Edexcel D1 2018 Q3 [7]}}