Edexcel D1 2018 June — Question 3 7 marks

Exam BoardEdexcel
ModuleD1 (Decision Mathematics 1)
Year2018
SessionJune
Marks7
PaperDownload PDF ↗
Mark schemeDownload PDF ↗
TopicCritical Path Analysis
TypeIdentify guaranteed critical activities
DifficultyModerate -0.8 Part (a) is a standard network drawing exercise requiring careful dummy placement (5 marks), while part (b) requires simple logical deduction about critical path dependencies given that D is critical. This is routine D1 material testing basic understanding of critical activities with minimal problem-solving—easier than average A-level maths.
Spec7.05a Critical path analysis: activity on arc networks

3.
  1. Draw the activity network described in the precedence table below, using activity on arc and exactly four dummies.
    (5)
    ActivityImmediately preceding activities
    A-
    B-
    C-
    DA
    ED
    FA, B
    GA, B, C
    HA, B, C
    IE, F, G
    JE, F, G
    KE, F, G, H
    Given that D is a critical activity,
  2. state which other activities must also be critical.
    (2)

3.\\
\begin{enumerate}[label=(\alph*)]
\item Draw the activity network described in the precedence table below, using activity on arc and exactly four dummies.\\
(5)

\begin{center}
\begin{tabular}{|l|l|}
\hline
Activity & Immediately preceding activities \\
\hline
A & - \\
\hline
B & - \\
\hline
C & - \\
\hline
D & A \\
\hline
E & D \\
\hline
F & A, B \\
\hline
G & A, B, C \\
\hline
H & A, B, C \\
\hline
I & E, F, G \\
\hline
J & E, F, G \\
\hline
K & E, F, G, H \\
\hline
\end{tabular}
\end{center}

Given that D is a critical activity,
\item state which other activities must also be critical.\\
(2)\\
\end{enumerate}

\hfill \mbox{\textit{Edexcel D1 2018 Q3 [7]}}