Edexcel D1 2014 June — Question 6 7 marks

Exam BoardEdexcel
ModuleD1 (Decision Mathematics 1)
Year2014
SessionJune
Marks7
PaperDownload PDF ↗
Mark schemeDownload PDF ↗
TopicCritical Path Analysis
TypeExplain dummy activities
DifficultyModerate -0.5 This is a standard D1 critical path analysis question requiring students to draw an activity network with dummies and explain their necessity. While it requires understanding of precedence relationships and dummy activities, it follows a routine algorithmic approach taught in all D1 courses with no novel problem-solving required. The explanation part is straightforward once the network is correctly drawn.
Spec7.05a Critical path analysis: activity on arc networks

6. (i) Draw the activity network described in the precedence table below, using activity on arc and the minimum number of dummies.
ActivityImmediately preceding activities
\(A\)-
B-
C-
DA, \(C\)
EB
\(F\)E
GA
\(H\)\(D , F\)
I\(D , F\)
JH, I
(ii) Explain why each of your dummies is necessary.

6. (i) Draw the activity network described in the precedence table below, using activity on arc and the minimum number of dummies.

\begin{center}
\begin{tabular}{|l|l|}
\hline
Activity & Immediately preceding activities \\
\hline
$A$ & - \\
\hline
B & - \\
\hline
C & - \\
\hline
D & A, $C$ \\
\hline
E & B \\
\hline
$F$ & E \\
\hline
G & A \\
\hline
$H$ & $D , F$ \\
\hline
I & $D , F$ \\
\hline
J & H, I \\
\hline
\end{tabular}
\end{center}

(ii) Explain why each of your dummies is necessary.\\

\hfill \mbox{\textit{Edexcel D1 2014 Q6 [7]}}