OCR Further Discrete 2020 November — Question 6 13 marks

Exam BoardOCR
ModuleFurther Discrete (Further Discrete)
Year2020
SessionNovember
Marks13
PaperDownload PDF ↗
Mark schemeDownload PDF ↗
TopicCritical Path Analysis
TypeFind missing early/late times
DifficultyStandard +0.3 This is a standard critical path analysis question requiring systematic application of forward/backward pass algorithms to find early/late times, identify critical activities, and consider resource constraints. While multi-part with several calculations, each step follows routine procedures taught in Decision Maths with no novel problem-solving insight required—slightly easier than average A-level questions.
Spec7.05a Critical path analysis: activity on arc networks7.05b Forward and backward pass: earliest/latest times, critical activities7.05c Total float: calculation and interpretation7.05d Latest start and earliest finish: independent and interfering float7.05e Cascade charts: scheduling and effect of delays

6 A project is represented by the activity on arc network below. \includegraphics[max width=\textwidth, alt={}, center]{cc58fb7a-efb6-4548-a8e1-e40abe1eb722-7_410_1095_296_486} The duration of each activity (in minutes) is shown in brackets, apart from activity I.
  1. Suppose that the minimum completion time for the project is 15 minutes.
    1. By calculating the early event times, determine the range of values for \(x\).
    2. By calculating the late event times, determine which activities must be critical. The table shows the number of workers needed for each activity.
      ActivityABCDEFGHIJK
      Workers2112\(n\)121114
  2. Determine the maximum possible value for \(n\) if 5 workers can complete the project in 15 minutes. Explain your reasoning. The duration of activity F is reduced to 1.5 minutes, but only 4 workers are available. The minimum completion time is no longer 15 minutes.
  3. Determine the minimum project completion time in this situation.
  4. Find the maximum possible value for \(x\) for this minimum project completion time.
  5. Find the maximum possible value for \(n\) for this minimum project completion time.

Question 6:
AnswerMarks Guidance
6For reference:
6(a) (i)
Early time 0 2 4 4 7 10 10+x 15
AnswerMarks
0 ≤ x ≤ 3M1
A1
B1
AnswerMarks
[3]Forward pass, early event times at every vertex, shown on
network or listed (increasing from 0)
All correct, apart possibly from 
≤ 3
AnswerMarks Guidance
6(a) (ii)
Late time 0 3 4 4 7 10 13 15
AnswerMarks
A, F, H, KM1
A1
B1
AnswerMarks
[3]Backward pass, late event times at every vertex
(decreasing, with start and finish matching the forward pass)
All correct, may have max{12+x, 15}or 12+x, 15 at 
A, F, H, K
Allow A, F, H, I, J, K (with both I and J) but no others
AnswerMarks Guidance
6(b) Max value for n is 2
2 do A while another does B then C
4 workers do K while the other does I then J
D, (E), F, G and H must be completed between time 4 and time 10
G needs 2 workers
so 3 workers are available for D, (E), F and H
G takes 5 minutes
F followed by H uses 1 worker for 6 minutes
E can be fitted in before D
AnswerMarks
so only 2 workers are neededB1
M1*
M1dep*
A1
AnswerMarks
[4]2
For reference:
Activity A B C D E F G H I J K
Workers 2 1 1 2 n 1 2 1 1 1 4
Reasoning may be seen on grids
D, F, G and H must be done between time 4 and time 10
3 workers available for D, F and H
(or implied from E followed by D or vice versa)
E done before D
AnswerMarks Guidance
Event
Early time0 2
Event
Late time0 3
ActivityA B
Workers2 1
(c)18 minutes
Time 0 2 4 6 8 11 16
Start A, B C E, F, D G H K I, J
AnswerMarks
(n = 1) (x = 0)B1
[1]18 or 18 + x
Working is not necessary but may be seen on grids
AnswerMarks Guidance
(d)0 minutes B1FT
[1]Their answer to part c minus 18
Working is not necessary but may be seen on grids
AnswerMarks Guidance
(e)1 worker B1
[1]1
Working is not necessary but may be seen on grids
AnswerMarks Guidance
Time0 2
StartA, B C
(n = 1)(x = 0)
PMT
OCR (Oxford Cambridge and RSA Examinations)
The Triangle Building
Shaftesbury Road
Cambridge
CB2 8EA
OCR Customer Contact Centre
Education and Learning
Telephone: 01223 553998
Facsimile: 01223 552627
Email: general.qualifications@ocr.org.uk
www.ocr.org.uk
For staff training purposes and as part of our quality assurance programme your call may be
recorded or monitored
Question 6:
6 | For reference:
6 | (a) | (i) | Event        
Early time 0 2 4 4 7 10 10+x 15
0 ≤ x ≤ 3 | M1
A1
B1
[3] | Forward pass, early event times at every vertex, shown on
network or listed (increasing from 0)
All correct, apart possibly from 
≤ 3
6 | (a) | (ii) | Event        
Late time 0 3 4 4 7 10 13 15
A, F, H, K | M1
A1
B1
[3] | Backward pass, late event times at every vertex
(decreasing, with start and finish matching the forward pass)
All correct, may have max{12+x, 15}or 12+x, 15 at 
A, F, H, K
Allow A, F, H, I, J, K (with both I and J) but no others
6 | (b) | Max value for n is 2
2 do A while another does B then C
4 workers do K while the other does I then J
D, (E), F, G and H must be completed between time 4 and time 10
G needs 2 workers
so 3 workers are available for D, (E), F and H
G takes 5 minutes
F followed by H uses 1 worker for 6 minutes
E can be fitted in before D
so only 2 workers are needed | B1
M1*
M1dep*
A1
[4] | 2
For reference:
Activity A B C D E F G H I J K
Workers 2 1 1 2 n 1 2 1 1 1 4
Reasoning may be seen on grids
D, F, G and H must be done between time 4 and time 10
3 workers available for D, F and H
(or implied from E followed by D or vice versa)
E done before D
Event |  |  |  |  |  |  |  | 
Early time | 0 | 2 | 4 | 4 | 7 | 10 | 10+x | 15
Event |  |  |  |  |  |  |  | 
Late time | 0 | 3 | 4 | 4 | 7 | 10 | 13 | 15
Activity | A | B | C | D | E | F | G | H | I | J | K
Workers | 2 | 1 | 1 | 2 | n | 1 | 2 | 1 | 1 | 1 | 4
(c) | 18 minutes
Time 0 2 4 6 8 11 16
Start A, B C E, F, D G H K I, J
(n = 1) (x = 0) | B1
[1] | 18 or 18 + x
Working is not necessary but may be seen on grids
(d) | 0 minutes | B1FT
[1] | Their answer to part c minus 18
Working is not necessary but may be seen on grids
(e) | 1 worker | B1
[1] | 1
Working is not necessary but may be seen on grids
Time | 0 | 2 | 4 | 6 | 8 | 11 | 16
Start | A, B | C | E, F, D | G | H | K | I, J
(n = 1) | (x = 0)
PMT
OCR (Oxford Cambridge and RSA Examinations)
The Triangle Building
Shaftesbury Road
Cambridge
CB2 8EA
OCR Customer Contact Centre
Education and Learning
Telephone: 01223 553998
Facsimile: 01223 552627
Email: general.qualifications@ocr.org.uk
www.ocr.org.uk
For staff training purposes and as part of our quality assurance programme your call may be
recorded or monitored
6 A project is represented by the activity on arc network below.\\
\includegraphics[max width=\textwidth, alt={}, center]{cc58fb7a-efb6-4548-a8e1-e40abe1eb722-7_410_1095_296_486}

The duration of each activity (in minutes) is shown in brackets, apart from activity I.
\begin{enumerate}[label=(\alph*)]
\item Suppose that the minimum completion time for the project is 15 minutes.
\begin{enumerate}[label=(\roman*)]
\item By calculating the early event times, determine the range of values for $x$.
\item By calculating the late event times, determine which activities must be critical.

The table shows the number of workers needed for each activity.

\begin{center}
\begin{tabular}{ | l | c | c | c | c | c | c | c | c | c | c | c | }
\hline
Activity & A & B & C & D & E & F & G & H & I & J & K \\
\hline
Workers & 2 & 1 & 1 & 2 & $n$ & 1 & 2 & 1 & 1 & 1 & 4 \\
\hline
\end{tabular}
\end{center}
\end{enumerate}\item Determine the maximum possible value for $n$ if 5 workers can complete the project in 15 minutes. Explain your reasoning.

The duration of activity F is reduced to 1.5 minutes, but only 4 workers are available. The minimum completion time is no longer 15 minutes.
\item Determine the minimum project completion time in this situation.
\item Find the maximum possible value for $x$ for this minimum project completion time.
\item Find the maximum possible value for $n$ for this minimum project completion time.
\end{enumerate}

\hfill \mbox{\textit{OCR Further Discrete 2020 Q6 [13]}}